Works
The following footpaths and bikeways works will be carried out in Logan over the coming months.
| Suburb | Street | Description | Start Date* | End Date* | Division |
|---|---|---|---|---|---|
| Marsden | Macarthy Road | Excavation of footpath for new development | Late April 2012 | Early June 2012 | 5 |
| Regents Park | Solandra Circuit | New footpath | Early May 2012 | Late May 2012 | 8 |
* All programs will commence as planned, weather permitting. Changes to the program may occur due to unforseen circumstances.
Please contact Council on 07 3412 5282 for more information.