Suburb Street Description Start Date* End Date* Division
Marsden Macarthy Road  Excavation of footpath for new development Late April 2012  Early June 2012 
Regents Park  Solandra Circuit  New footpath  Early May 2012  Late May 2012 

* All programs will commence as planned, weather permitting. Changes to the program may occur due to unforseen circumstances.