Works

The following roads and drainage works will be carried out in Logan over the coming months.

Upcoming roads and drainage works in Logan
Suburb Street Description Start Date* End Date* Division
Barhs Scrub Wuraga Road Road widening February 2014 June 2014 4
Bahrs Scrub Bahrs Scrub Road  Reseal  Start April 2014  End April 2014 
Bahrs Scrub Windaroo Road Road construction Mid April 2014 Late April 2014 4
Bannockburn Emerald Road  Kerb & channel work  March 2014  Mid April 2014 
Beenleigh Sunnyview Street Road construction January 2014 Mid May 2014 12 
Boronia Heights Parklands Drive  Stormwater drainage works  Mid July 2013  Late November 2013 
Buccan Buccan Road  Reseal Start April 2014  End April 2014 
Buccan Grassdale Street 10mm PMB Reseal  Start April 2014 End April 2014 4
Buccan Luke Road  Reseal  Start April 2014  End April 2014 
Buccan Sharton Avenue 10mm PMB Reseal Start April 2014 End April 2014 4
Chambers Flat Sungold Road Road rehabilitation Mid February 2014 Early April 2014 9
Crestmead Julie Street  Profiler deeplift asphalt replacement  Start April 2014  End April 2014 
Crestmead Rai Drive Retaining wall works April 2014  May 2014 
Daisy Hill Daisy Hill Road   Road widening & kerb and channel rehabilitation February 2014 April 2014 1
Eagleby Albert Street  Reseal/final seal  Start April 2014 End April 2014 12 
Eagleby Stapylton Street  Reseal  Start April 2014 End April 2014 12 
Edens Landing Castile Crescent  Kerb & channel work  Mid February 2014  Mid March 2013 
Greenbank Andrew Road Road construction Mid November 2013 End November 2013  7
Holmview Holmview Road  Kerb & channel work  Mid April 2014  Mid May 2014 
Jimboomba  Cusack Lane  Road reconstruction  Mid April 2014  Mid May 2014  11 
Jimboomba Minugh, McDonald & Davidsons Roads Culvert upgrade May 2014 November 2014  11
Jimboomba Myrtle Road Reseal  Start April 2014

End April 2014

11
Kingston Antares Avenue  Master drainage works  Mid April 2013  November 2013
Kingston  Gilia Street  Master drainage works  April 2014  November 2014
Kingston Juers Street  Intersection signalisation  Mid March 2014  May 2014
Kingston Laughlin Street  Road extention  January 2014 April 2014  5
Kingston Nerine Street  Drainage works  Early April 2013  November 2013
Kingston Tecoma Street Master drainage works Early April 2013  November 2013
Kingston Third Avenue Third Avenue Kingston Road Extension Stage 3 November 2013 Mid December 2013 5
Loganholme Eastern Service Road Sami seal and asphalt overlay Start April 2014 End April 2014 6
Logan Reserve Logan Reserve Road Road construction December 2013 September 2014
Logan Village Pioneer Drive Road construction November 2013 May 2014 4
Logan Village Steele Road Culvert upgrade  April 2014  May 2014  4
Logan Village Steele Road  Road construction April 2014 Early May 2014
Marsden  Chambers Flat Road  Stormwater pipes and road surfacing  June 2013 

Mid October 2013 

5 & 9 
Marsden Demeio Road Car park & bikeway February 2014  April 2014 
Meadowbrook Logandowns Drive Profiler digouts and asphalt overlay - Night works End November 2013 Mid December 2013 9
Mt Warren Park Mt Warren Boulevard Road landscaping in the median Mid October 2013 Late October 2013  4
Munruben Janelle Court Reseal  Start April 2014  End April 2014 
Regents Park Emerald Drive  Profiler deeplift asphalt replacement  Start April 2014  End April 2014 
Rochedale South Karoonda Crescent  Master drainage  March 2014 July 2014 1
Rochedale South Rochedale Road Kerb & channel work (overlay only) January 2014 Mid April 2014
Rochedale South Underwood Road Kerb & channel work  January 2014  April 2014 
Shailer Park Chatswood Road  Profiler deeplift asphalt replacement  Start April 2014  End April 2014 10 
Shailer Park Kimberley Forest Park Erosion control March 2014 May 2014 10
Shailer Park Oak Street  Master drainage  March 2014  June 2014  10 
Slacks Creek Western Service Road  Profiler deeplift asphalt replacement  Start April 2014  End April 2014 
Tanah Merah Sewell Road Road construction Start April 2014 End April 2014
Waterford Old Logan Village Road 10mm pmb reseal Start April 2014 End April 2014
Woodridge North Road  Profiler keyins, sami seal and asphalt overlay  Mid October 2013 Mid November 2013 
Woodridge  Plunkett Street  Stormwater drainage works  Mid November  2013  Late October 2013 

* All works will commence as planned, weather permitting. Change to the works program may occur due to unforseen circumstances.

Both Council and known Contractor works have been listed, to ensure residents are aware of all works that may affect local roads.

For more information, please contact Roads Infrastructure Planning on 07 3412 5282.