Greater Flagstone

The Greater Flagstone Strategic Plan provides the strategic direction for development within the study area to 2051.

The centres-based approach encourages a self-contained development pattern through the creation of communities with a desirable mix of centre activities and dispersed local employment opportunities. It also supports the principles of transit orientated development.

In October 2010 an Urban Development Area (UDA) was declared over the Greater Flagstone site. The Urban Land Development Authority (ULDA) became the planning authority for Flagstone and took over the land use planning role for the area.

The strategic plan developed by Council prior to the ULDA's take over formed the basis of our input into the ULDA's land use planning for Flagstone. In October 2011, the land use planning for Flagstone was approved for the Greater Flagstone UDA Development Scheme.

The Flagstone Strategic Plan Report is available by contacting Council on 07 3412 3412 or council@logan.qld.gov.au.

Milestones

Greater Flagstone Strategic Plan project milestones
Date Milestone
16 February 2010 Council resolved to progress Option 1 Centres as the base plan for developing the Greater Flagstone Strategic Plan. Option 1 Centres has been further refined using detailed population and employment modelling and infrastructure planning, culminating in the Greater Flagstone Strategic Plan.
May 2010 Background studies for the draft Greater Flagstone Strategic Plan completed.
May 2010 Queensland Government announces its intent for the ULDA's control over future structure planning for Greater Flagstone.
June 2010 Engagement commences with ULDA on land use planning and infrastructure issues.
September 2010 Council's final Greater Flagstone Strategic Plan completed.
October 2010 Council endorses Final Greater Flagstone Strategic Plan.
October 2010 Queensland Government declares an Urban Development Area over the Greater Flagstone Area.
 November 2010 - March 2012 Engagement continues with ULDA on land use planning and infrastructure issues.
October 2011  Greater Flagstone UDA Development Scheme approved.