Conveniently Connected (CC) - Quarter 4 2020/2021

Project Target Status Commentary

CC1.1.1 - Deliver a report on the medium term needs for Logan's public transport system.

Purpose: Identify infrastructure requirements for the City of Logan for the next five to 15 years.

June 2021 Completed A report on the medium-term needs for Logan's public transport system was written to Council to fund the medium-term passenger transport strategy. Council after considering the report indicated that the matter may be considered in a future budget.

CC1.2.1 - Complete a condition survey of the sealed road network.

Purpose: Assess overall condition and prioritise future rehabilitation.

June 2021 Not Completed Field work is completed and 2000km of imagery and data has been provided by the contractor. Due to COVID-19 the processing was delayed but expecting final data of full network condition survey by the first week of August 2021.

It is recommended that this project be moved to the 2021/2022 Operational Plan to track its completion.

CC1.2.2 - Deliver the annual Road Maintenance Program.

Purpose: Maintain the quality of the local road network.

June 2021 Completed As at the end of June 2021, 100% of the annual Road Maintenance program of works was delivered.

CC1.2.3 - Deliver the annual road and drainage capital program.

Purpose: Improve active transport across the city.

June 2021 Completed Q4 delivery of the 20/21 Capital Works Program saw a significant increase in expenditure compared to the prior quarter (from $6.5M to $28.7M). At the end of the Fourth Quarter of the 2020/2021 Financial Year, delivery of the Capital Roadworks and Drainage Program has now achieved $63.4 million in overall expenditure. With a number of significant projects recently commencing construction and further key projects well progressed through the procurement stage this momentum is expected to continue into the 21/22 FY.

Significant projects, which were underway or completed in the Fourth Quarter include the following:
  • Black Spot Upgrade Grand Plaza Drive Pedestrian Improvements, Browns Plains ($0.3 Million)
  • Compton Road Shared footpath / cycleway, Slack Creek between Allgas Street and Baker Street ($3.2 Million)
  • Park Ridge State High School Carpark Upgrade, Park Ridge ($230,000)
  • Loganlea Healthy Street Project, Loganlea – In collaboration with ED&S ($5.7 Million - $2m Savings Expected)
  • Major Intersection Upgrade of Logan Reserve Road / Muchow Road, Marsden ($1.2 Million)
  • Early works for the Chambers Flat Road Upgrade, Kings Way to Mount Lindesay Highway, Chambers Flat ($25 Million)
  • Local road upgrade of Schmidt Road, Eagleby ($0.4 Million)
  • Local road upgrade of Stockleigh Road, Stockleigh ($1.0 Million)
  • Local road upgrade of Friar Street, Munruben ($1.5 Million)
  • Holmview Road local road kerbing and stormwater drainage upgrade, Beenleigh ($0.9 Million)
  • Early works associated with Stage 1 of local road kerbing and stormwater drainage upgrades to streets in Jimboomba ($8.6 million)
  • Local road kerb and stormwater drainage upgrade of Webb Road, Loganlea ($2.9 million)
  • Local road kerbing and stormwater drainage upgrades to Dickman Road, Forestdale ($0.45 Million)
  • Stormwater drainage upgrade in Stage 2 of the Defiance Road Catchment, Woodridge ($1.8 Million)
  • Pipe manufacture underway for stormwater drainage upgrades in Stages 2 & 9 of the Woodlands Drive Catchment, Rochedale South ($18 Million)
  • Grand Plaza Drive Culvert Rehabilitation, Browns Plains ($3.88 Million)
  • Teese Bridge timber bridge replacement with new concrete bridge, Veresdale Scrub ($1.7 Million jointly funded)
  • Kerb and channel rehabilitation at numerous locations to support future asphalt resurfacing works ($1.3 million)
  • Pavement resurfacing & reconstruction works across a number of locations ($5.9 Million)
There is currently $87.1 million of projects currently in various stages of pre-construction (including procurement and pre-award assessment) in preparation for construction commencement. This includes:
  • Major Intersection Upgrade of Browns Plains Road & Scrubby Creek Road, Browns Plains ($1.8 Million)
  • Major Intersection Upgrade of Albert Road & Station Road Intersection, Bethania ($1 Million)
  • Priority Infrastructure Upgrade of Gilmore Road, Berrinba ($11 Million)
  • Chambers Flat Road Upgrade, Kings Way to Mount Lindesay Highway, Chambers Flat ($25 Million)
  • Local road upgrade of Leopardwood Road, Cedar Grove ($1.2 Million)
  • Stage 1 of local road kerbing and stormwater drainage upgrades to streets in Jimboomba (South Street, Nichols Street, John Street, Mary Street & Hill Street) ($7.8 million)
  • Stormwater drainage upgrades of Woodbeck Street & Pheasant Street Catchment, Beenleigh ($1.6 Million)
  • Stormwater drainage upgrades of Stages 1-5 of the Kelly Street Catchment, Eagleby ($10 Million)
  • Stormwater drainage upgrades of Stages 1 & 2 of the Cowper Street Catchment, Eagleby ($10 Million)
  • Pavement reconstruction across a number of locations ($3.5 Million)
  • Stormwater Infrastructure Rehabilitation across a number of locations ($800,000)
  • Tully Bridge timber bridge replacement with new concrete bridge, Lyons ($1.4 Million)
  • 21-22 Asphalt Resurfacing Package 1 & 2 ($5 Million)
  • Scott Lane Culvert Replacement, North MacLean ($7.0 million)

CC1.3.1 - Deliver construction works for the Compton Road cycleway project.

Purpose: Link the cycleway to Logan Road and provide connections to the Springwood Bus Station.

June 2021 Completed As at the end of the fourth quarter, planned construction works for this project have commenced for this financial year. Construction of the Compton Road Cycleway is currently ongoing and is scheduled to be completed by August 2021.

CC2.1.1 - Commission the Cedar Grove Wastewater Treatment Plant (WWTP) in the Cedar Grove Environment Centre.

Purpose: Improve services to the southern region of the City of Logan.

June 2021 Completed The Cedar Grove Wastewater Treatment Plant (WWTP)  has been commissioned and is treating wastewater from the Greater Flagstone Priority Development Area (PDA).

CC2.1.2 - Deliver master planning works for the Chambers Flat Wastewater Treatment Plant (WWTP) and associated trunk infrastructure.

Purpose: Improve services to the southern region of the City of Logan.

June 2021 Completed

Master planning works of the Chambers Flat Wastewater Treatment Plant site has commenced.

The next stage for its completion is dependent on the clarification of a diversion of Chambers Flat Road onto the site.

CC2.2.1 - Deliver a review of the planning scheme.

Purpose: Enable well planned development for residents and businesses.

June 2021 Completed Work on the version 9 Logan Planning Scheme 2015 amendment has been completed and documents are pending delegate sign-off before submission to the State.

CC2.3.1 - Deliver a review of the Local Government Infrastructure Plan.

Purpose: Deliver trunk infrastructure in the City of Logan.

June 2021 Completed As at the end the end of the fourth quarter, the land valuation and feasibility test of the Schedules of Work have been completed and the preparation for community consultation has commenced.