Healthy connected community - Quarter 1, 2023 / 2024

Project Target Status Commentary
HC4.1.1 - Community Infrastructure Network Plan March 2024 On Track

Detailed network planning for indicative future locations and timing for Integrated Lifestyle Infrastructure Network Plan is progressing, in consultation with internal stakeholders. 

Final draft recommendations for the updated Community Infrastructure Plan are being finalised. 

The Sports Infrastructure Plan draft report and recommendations are being reviewed.  

The Parks Plan is in development. 

Milestones achieved: 

  • internal stakeholder consultation on the draft community infrastructure network plan was completed
  • draft Sports and Recreation Plan was developed
  • approach, feedback and timeframes were confirmed with council's Chief Executive Officer
  • mapping for the network was developed.

Proposed actions: 

  • draft plans are to be delivered in quarter 3, 2023 / 24
  • Councillor breifing session to be held in October 2023.
HC4.1.2 - Sport and Community Infrastructure Capital Works Program June 2024 On Track

Projects remain on track for delivery of the capital works program, with approximately $9.4 million (28%) worth of projects currently in construction. 

There are approximately $12.8 million (38%) of projects currently in procurement phase / pre-construction. 

Design and scoping is progressing for the remaining 34% of the Capital Works Program. 

Approximately $2.9 million (8.5%) of the Capital Works Program has been delivered.

Milestones achieved: 
l  construction commenced for Jimboomba Park Rugby League Clubhouse 
l  contract was awarded for Chris Green Clubhouse
l  a letter of intent was issued to the preferred supplier for the Everleigh Park Clubhouse with award of contract to follow.

HC4.2.1 - Libraries Learning and Discovery Strategy June 2024 On Track The following was achieved during the first quarter of  2023/24:
  • delivery of activities in Libraries including Baby Time, Page Turners, Tech Help and English Conversation sessions
  • delivery of 2,918 take-home packs for families
  • delivery of school holiday activities for children, with 964 attendees
  • delivery of face to face library programming and events for children and adults, with 16,803 attendees
  • delivery of home library service to 473 individual library members and 23 aged care facilities
  • Library staff developed, implemented and evaluated purposeful and engaging library programming and community engagement in support of the Libraries Learning and Discovery Strategy. 368 outreach events were delivered across the City with 6747 people participating in these outreach events.
HC4.4.1 - Arts Culture and Heritage Strategy 2023-2027 June 2024 On Track During the first quarter of  2023/24, the Arts, Culture and Heritage Plan 2023-2027 was endorsed by Logan City Council on 17 August 2023. 
Arts, Culture and Heritage highlights for quarter one include:
  • Logan NAIDOC Family Fun Day with 2,500 attending the event
  • Logan Entertainment Centre's 21st celebration program with 940 attending the program of events
  • the opening of the Big Voices: Children's Art Matters exhibition at the Living Museum of Logan in July with 35 people attending the event
  • the launch of the Education Arts program in August with 45 teachers attending the event 
  • the display of the Artwaves 2023 exhibition at Logan Art Gallery in September with 502 people attending the event.