Infrastructure - Quarter 3, 2024 / 2025

Branch Project name Priority area Target Status Commentary
Road Infrastructure Delivery IN6.1.1 - Capital Works Design Program IN6.1 June 2025 On Track There were 37 detailed engineering designs scheduled for completion in the 2024/25 program.

By the end of the third quarter of 2024/25, a total of 26 projects were completed and issued for construction.
Road Infrastructure Delivery IN6.1.2 - Design of Bethania to Logan Village rail trail IN6.1 June 2025 Completed The feasility study and the detailed design for the Bethania to Logan Village section of the rail trail has been completed.

The construction of the Bethania to Logan Village section of the rail trail will be implemented in accordance with the detailed design subject to available funding.

This project is now complete.
Road Infrastructure Delivery IN6.1.3 - Road and Drainage Capital Works Program IN6.1 June 2025 On Track At the end of the third quarter 2024/25, delivery of the Road and Drainage Capital Works Program achieved $100.6 million in expenditure.

A review of the capital works program has been carried out, considering the impact of recent adverse weather. A recommendation will be provided to Council in May 2025 to amend the Road and Drainage Capital Works Program budget to align with anticipated delivery this financial year.

Notable projects under construction throughout the quarter include:
  • Loganlea Road Upgrade from University Drive to Pacific Motorway (6 lanes)
  • Stormwater drainage upgrades to Stage 1 and 2 of the Cowper Avenue Catchment Master Drainage Project, Eagleby
  • Stormwater drainage upgrades to Stage 1 to 5 of the Kelly Street Catchment Master Drainage Project, Eagleby
  • Park Ridge Road, Clarke Road and Lindenthal Road, Park Ridge Intersection Signalisation
  • Teviot Road and Cusack Lane, Riverbend and South Maclean Intersection Signalisation
  • Teviot Road, Middle Road to Greenbank Road – Stage 1A
  • Chambers Flat Road (Holloway to Kenny Road) Safety Improvements, Chambers Flat
  • Alamein Street, Main Street and George Street Intersections Upgrade
  • Woodlands Drive - Stormwater Drainage Upgrade Stages 10, 11 & 12
  • Underwood Road Bus Turnaround, Priestdale
  • Goodna Road Carpark Upgrade, Greenbank
  • Beenleigh Road Widening, Underwood
  • Pavement Rehabilitation works to the value of $11.1 million at numerous locations across the city.

The Road and Drainage Capital Works Program delivers enhanced transport and drainage infrastructure across the City of Logan. The Program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure network.
Road Infrastructure Planning IN6.1.4 - Way2Go Refresh IN6.1 June 2025 Monitor During quarter 3 of 2024/25, the Way2Go review and actions audit were completed in line with the project requirements.

Presentation of the project report to the Executive Leadership Team (ELT) was deferred due to the recent severe weather event and the annual budget deliberations.

It is anticipated that the report will be presented to ELT during quarter 4 of 2024/25, at which time the project will be closed.
Logan Water HP7.3.3 - Review and update Council’s Water Netserv Plan IN6.2 June 2025 Completed During the second quarter of 2024/25, Logan Water provided notice to the Planning Minister (in accordance with section 99BRAB (5) of the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009 (SEQ Water Act), that Council adopted the Water Netserv Plan Part A and its Connections Policy in December 2024.

The project to undertake a formal review of the Water Netserv Plan Part A and its Connections Policy is now completed and the Water Netserv Plan (Part A): 2022–2026 and Connections Policy are now published on Logan City Council's website.

This project is now complete.
Logan Water IN6.2.1 - Water and Wastewater Capital Works Program IN6.2 June 2025 Not Complete At end of the third quarter of 2024/25, the Water and Wastewater Capital Works Program expenditure was tracking at 78% against the original phased budget. 

Green energy projects form a significant component of this year's program, which have been delayed due to reaching an agreement with Council's preferred energy partner. While these have commenced following the appointment of the energy partner, full expenditure against the original Water and Wastewater Capital Works Program budget will not be achieved by June 2025.

To address delays with green energy projects, a recommendation will be provided to Council in May 2025 to amend the Water and Wastewater Capital Works Program budget to align with anticipated delivery this financial year.

Good progress is continuing to be made on various other new water and wastewater projects and asset renewal programs.
Parks IN6.3.1 - 2024/2025 Parks Capital Works Program delivery IN6.3 June 2025 Not Complete At end of the third quarter 2024/25, the Parks Capital Works Program expenditure was tracking at 49% against the original phased budget. 

Waterford West District Park and Rochedale South land acquisition projects have been reprogrammed for delivery in a future financial year. As a result, full expenditure against the original Parks Capital Works Program budget will not be achieved by June 2025.
 
To address the reprogramming of the Waterford West District Park and Rochedale South land acquisition, a recommendation will be provided to Council in May 2025 to amend the Parks Capital Works Program budget to align with anticipated delivery this financial year.
 
Good progress is continuing to be made on various other Parks projects and asset renewals.