Proud City - Quarter 1, 2023 / 2024

Project Target Status Commentary
PC2.2.1 - City of Logan Safe City Strategy and Action Plan 2021-2025 June 2024 On Track During the first quarter of 2023 / 24, key actions of the City of Logan: Safe City Strategy and Action Plan 2021-2025 were delivered, including:
  • the annual City of Logan Safe City Awards
  • the launch of the 'You hold the key to prevent car theft' campaign
  • the completion of nine (9) Crime Prevention Through environmental Design (CPTED) audits throughout the city
  • the completion of six (6) community safety assessment for liquor licence applications
  • attendance at five (5) community engagement events specific to resident concerns relating to personal safety, perceptions of crime, frauds and scams and home and vehicle security.
PC2.3.1 - Disability Action Plan June 2024 On Track

September 2023 key highlights include:

  • 1 action completed
  • 8 actions progressed
  • 10 internal working group members attended the quarterly meeting where they provided updates on their actions and information on additional actions they are completing.

During the first quarter of 2023/24, the following key highlights were achieved: 

  • 17 actions completed 
  • 32 actions in progress 
  • 8 internal working group members attended disability and inclusion training
  • 10 internal working group members attended the quarterly meeting where they provided updates on their actions and information on additional actions they are completing.
PC2.3.2 - Reconciliation Action Plan June 2024 Monitor

September 2023 key highlights include:

  • lthe development of Council's third RAP has been delayed due to continued discussions regarding priorities, resourcing and recruitment.  A meeting with ELT will occur in October. 
  • the Reconciliation Ambassador webpage has been updated to include new ambassadors and has become the main platform for sharing updates and information between Ambassadors. 

During the first quarter of 2023/24, the following key highlights were achieved: 

  • attended ELT on 20 July to discuss priorities, resourcing and recruitment
  • 60 new Reconciliation Ambassadors were inducted on 27 July
  • the Reconciliation Ambassador webpage has been updated to include new ambassadors and has become the main platform for sharing updates and information between Ambassadors
  • held 1 sharing circle at Berrinba Wetlands with 31 Ambassadors in attendance