Operational plan report - Quarter 1, 2024 / 2025

1. Total projects for 2024 / 2025 Quarter 1: 43

Corporate Plan focus areas Total
Maintaining current levels of service (MS) 1
Proud city (PC) 8
Environment (EN) 7
Healthy connected community (HC) 3
Economy and growth (EG) 2
Infrastructure (IN) 7
High performing organisation (HP) 15
Total 43

Project status Total
On Track 38
Completed 0
Monitor 5
Not Completed 0
Not Proceeding 0
Total 43

You can view each priority focus area for Quarter 1, 2024 / 2025 below which includes a status update on Operational Plan key project delivery:

2. Maintaining current levels of service (MS)

Project Name Target Status Commentary
MS1.3.1 - Logan Listens: Residents' Survey Dec 2024 Monitor In the first quarter of 2024/25, the following actions were completed to support the delivery of the Logan Listens: Residents' Survey:
  • reviewed feedback from Directors and Managers on the previous survey
  • researched other Local Government approaches to Residents Surveys (Gold Coast, Brisbane, Moreton Bay)
  • consulted with Community Engagement to help develop survey options
  • requested two high level quotes, and further information from the previous supplier to deliver like for like, an option to change the questions, and details of Councils against whom our results will be benchmarked
  • additional quotes sourced to inform options analysis
  • finalised an options analysis paper for presentation to Council's Executive Leadership Team in November 2024, to guide direction for delivery of the Survey.

In line with the redeveloped project schedule, it is proposed to request an extension of the target date to June 2025. This is to accommodate the planned release of the survey in early 2025 and to allow sufficient time for the subsequent analysis and reporting of the survey outcomes.

3. Proud City (PC)

Project name Target Status Commentary
PC2.2.1 - Community Development Action Plan June 2025 On Track During the first quarter of 2024/25, no activities were conducted for this project, however the project is on track to be delivered within the target timeframe.
PC2.2.2 - Disability Action Plan June 2025 On Track During the first quarter of 2024/25, the following was delivered:
  • In partnership with Jigsaw, the Records Management Program employed 2 part time employees with disabilities earlier this year, with one being extended to continue until 31 December 2024. The staff member is gaining skills and experience in records operational tasks and print room product finishing.
  • People with disabilities participated in work experience at 3 libraries.
  • New braille and large print magnets were developed for Home Library Clients and made available at all libraries.
  • Finalised the social sensory story for Logan North Library which is availableonlineor in hard copy at each library.
  • The Accessibility Centre at Logan North Library had 1,128 visitors, and a there was a soft launch of the updated Sensory Room at Marsden Library which now includes a fibre optic fountain and STEM board.
  • A bus shelter upgrade, including installation of approximately 40 new shelters, is underway in partnership between Council and TransLink.
  • A new footpath data acquisition survey commenced in 2024.
  • The Community Safety Program supported Uniting Care and family and disability support services to deliver a Family Fun Day as part of Child Protection Week.
  • The Economic Development Program engaged with 15 local tourism and hospitality businesses and internal teams to develop content for the Accessible Tourism page on theExplore Logan website.A range of businesses and experiences were audited by Spinal Life and will be included in a Brisbane Region Destination Accessibility Guide later this year.
  • The Kingston Butter Factory ans Cultural Precinct was awarded 'Accessible Venue of the Year' at the 2024 Queensland Music Awards.
  • The Beenleigh Aquatic Centre employed a person in a wheelchair, as supported by the Mayor's Employment Taskforce.
  • Council's Community Development and Economic Development Programs partnered to support the Fresh Futures 2024 Expo to link young people in Logan living with a disability to employment and community participation opportunities.
  • The Community Development Program are working with BEST Weekly News team, young adult residents living with a disability, to create a video series on the role of Council in community. Four interview/ filming sessions have been scheduled, covering City Safety and Liveability, Parks, Libraries, Venues and Events
  • Council signed up to become a member of the Sunflower Initiative, a global initiative promoting inclusivity for people with hidden disabilities.
  • The Community Planning Program has commenced planning to conduct accessibility audits on all community and sporting facilities that are part of the Sports and Community Infrastructure branch asset list.
  • The new Logan Indoor Sports Centre (announced recently) will be universally accessible and will be able to accommodate a range of sports including wheelchair rugby, sitting volleyball and wheelchair basketball.
PC2.2.3 - Grants to Community June 2025 On Track During the first quarter of 2024/25, the following was delivered:
Community Benefit Fund (CBF):
CBF re-opened to the community for applications on 19 July:
  • 28 successful applications
  • $35,590.68 in funding allocated.
Community Event Funding (CEF):
  • 13 successful applications
  • $86,816.80 in funding allocated
  • A list of grant recipients is available on ourwebpage.

Community Development Funding (CDF):

  • 4 successful applications
  • $25,634.00 in funding allocated
  • A list of grant recipients is available on ourwebpage.
PC2.2.4 - Community Infrastructure accessibility audit - Stage 1 June 2025 On Track In the first quarter 2024/25, the request for quote for the Community Infrastructure accessibility audit was finalised to include key stakeholder feedback to ensure alignment with other projects in Council.

At the end of the first quarter, identification of all facilities to be part of the audit were completed, the project plan was developed and the request for quote was finalised.

Next steps include the Request for Quote to be uploaded via VendorPanel to secure a supplier and to commence the project in October 2024.
PC2.3.1 - Logan Youth Action Group (LYAG) June 2025 On Track During the first quarter of 2024 / 25, the following was delivered:
  • The Logan Youth Action Group (LYAG) hosted their inaugural networking breakfast with the Mayor, Councillors, and senior staff to learn about leadership and decision-making at Council. 15 young people, 5 Councillors and 6 staff attended.
  • Community Development supported LYAG members to partner with the Logan Seniors Network to develop a first draft of their Logan Seniors Digital Guide.
  • 3 working bees took place at Jimboomba Community Garden with 8 LYAG members volunteering.
  • 10 Logan Youth Action Group (LYAG) members attended a workshop about how to engage older people in using technology. The workshop was delivered by a local volunteer.
  • 8 LYAG members volunteered at the Uniting Care Family Fun Day for Child Protection Week.
PC2.3.2 - Reconciliation Action Plan June 2025 Monitor During the first quarter of 2024/25 no activities were conducted for this project.

Council is reviewing its broader position on opportunities to support and engage with Logan's First Nation's community.
PC2.4.1 - Abandoned and derelict houses project June 2025 On Track During the first quarter of 2024/25, the research and engagement phase of the Abandoned and Derelict House Project progressed.

Proposed recommendations addressing the problems of abandoned and derelict houses across the City of Logan will be discussed in future Councillor meetings. Content was provided for the July Councillor newsletter and website content has been developed for sharing, post completion of the engagement phase.
PC2.4.2 - Targeted local law reform to improve city amenity and public health and safety. June 2025 Monitor Council has a legislative obligation under the Local Government Act 2009 (Division 2 – Making, recording and reviewing local laws) to review its Local Laws.

Local Law No. 10 (Public Health) 1999 and Subordinate Local Law No. 10.1 (Public Health) are diverse pieces of legislation that were last amended in 2015. Some elements of these local laws work well and will not need to be changed. The primary focus of this local law review will be to develop rigour for existing identified nuisances and develop frameworks for emerging nuisances to meet the future needs and demands of the greater community. The intent of Local Law No. 10 (Public Health) 1999 is a to:
  • Protect public health and safety
  • Uphold the amenity of neighbourhoods and mitigate property damage
  • Prevent unnecessary environmental harm or nuisance
  • Provide good governance, accountability, community education and enforcement for any confirmed breaches of the Local Law.

A report will be tabled at the City Lifestyle Committee in early 2025 to seek Council support to undertake a detailed review of Local Law No. 10 (Public Health) 1999. This local law provides Council the ability to administer compliance and enforcement outcomes for breaches of public health, city amenity and public safety.

It is envisaged that the review and subsequent proposed local law will provide greater enforcement outcomes and better manage community expectations.

In line with the developed project schedule, it is proposed to request an amendment to the project description and an extension of the target date to June 2025. This is to accommodate the legislative processes required to deliver a review of the identified Local Law, and the tasks for completion within the 2024/25 financial year.

The proposed amendments to the project description are:
  • Project Name: PC2.4.2 - Targeted local law reform to improve city amenity and public health and safety
  • Purpose: To ensure that local laws relating to public health, city amenity and public safety adequately respond to evolving community need.
  • Action: Prepare a report to Council to propose to make a Local Law and develop a Local Law Reform policy direction and community engagement plan.
  • Outcome: Increased city liveability resulting from greater definition of regulatory compliance and enforcement actions and incorporation of emerging nuisances to respond to future need.
  • Target date: June 2025

4. Environment (EN)

Project name Target Status Commentary
EN3.1.1 - Logan and Albert River Litter Clean Ups June 2025 On Track During the first quarter of 2024/25, planning for the Logan and Albert River Litter Clean Ups was progressed to schedule.

On ground clean up works are due to recommence in January 2025.
EN3.1.2 - Mabel Park natural channel design project June 2025 On Track During the first quarter of 2024/25, the following works for the Mabel Park waterway naturalisation project were undertaken:
  • phase 1 community engagement activities undertaken
  • initial meeting with First Nations group Danggan Balun
  • fish and geomorphic site assessment completed
  • baseline water quality monitoring completed
  • engagement with Mabel Park State School and Mabel Park State High School commenced.
EN3.2.1 - Riverbank Restoration Projects June 2025 On Track During the first quarter of 2024/25, the following Riverbank Restoration Project works were undertaken:
  • maintenance works were undertaken at previously planted Logan and Albert River restoration sites
  • infill planting was undertaken at Logan River Parklands, with 550 tubestock planted in September 2024
  • project planning for additional sites is underway.
EN3.3.1 - Tree Planting Offset Projects June 2025 On Track During the first quarter of 2024/25, the following offset project works undertaken were:
  • ongoing maintenance works on 100 hectares of planted land
  • site preparation works at Bahrs Hill Park and Denaman court
  • planting of over 25,000 trees at Ooah and Mundoolun parks.

All Tree Planting Offset Projects are on track.
EN3.4.1 - Environmental conservation partnerships June 2025 On Track During the first quarter of 2024/25, Environmental Conservation Partnerships achieved the following:
  • 1,135 members in total, participating in the program
  • 29 new Habitat Connections members joined the program (2 de-registrations) - 626 properties in total
  • 25 new Land for Wildlife properties were registered (6 de-registrations) - 509 properties in total
  • formal agreements remain at 30 (Voluntary Restoration Agreement, Voluntary Conservation Agreement and Voluntary Conservation Covenant)
  • 16 Land for Wildlife property revisits were conducted
  • 406 individual community engagement interactions were provided to ECP members
  • 110.06 hectares were added to the Land for Wildlife habitat network, bringing the total to 6556.85 hectares
  • 7 threatened species were recorded on Land for Wildlife properties including a koala, swamp tea tree and a tusked frog (19 threatened species have been recorded in total)
EN3.7.1 - Resource Recovery Infrastructure options report June 2025 On Track In the first quarter of 2024/25, a draft Resource Recovery Infrastructure Plan was prepared to help guide Council's decision on waste and recycling facilities.

An internal review process was conducted on the draft. Feedback from this review was provided to the consultant for incorporation into a final report.

The final report will be presented to a future meeting of Council's Executive Leadership Team for consideration.
EN3.8.1 - Green Fleet Strategy June 2025 On Track During September two staff Electric Vehicle Driver (EV) Training sessions were run. Investigations into the potential to install further EV chargers at the Council Administration Centre continued. Arrangements for the ongoing maintenance of Council's EV chargers were established. Two local government EV knowledge sharing forums were attended.

5. Healthy connected community (HC)

Project name Target Status Commentary
HC4.1.1 - Sport and Community Infrastructure Capital Works Program June 2025 On Track By the end of the first quarter 2024/25, all projects are on track for delivery of the Capital Works Program:
  • Approximately $18.2 million (58%) worth of projects are in construction
  • $2.5 million (8%) of projects are complete
  • There is approximately $6.7 million (21%) of projects currently in design or pre-construction phase.
  • The remaining 13% are in scoping and planning stage.

During the first quarter, the following projects were completed:
  • Beenleigh Aquatic Centre Demolition
  • Homestead Park/Forestglen Park/Alexandra Clark Park Toilets
  • Bishop St Park/Lowe Oval Field lights
  • Wilbur St Solar Panels
  • Jimboomba Park Clubhouse
  • Middle Green roof replacement
  • Chris Green Clubhouse.
HC4.2.1 - Libraries Learning and Discovery Plan 2024-2028 June 2025 On Track Libraries Learning and Discovery Plan 2024-2028 outcomes for September included:
  • The Australian Poetry Festival Logan Heat was held on Thursday 19 September. This was the first year the slam workshop and the Logan Heat were held at the Kingston Butter Factory. There were 7 participants at the slam workshop, 13 competitors for the Logan Heat and 40 audience members. The winner with the most points was Daisy Hill resident, Justin Geange.
  • 72,611 residents visited our 9 library locations in September, and we joined 1,815 new members.
  • Our community loaned 189,380 items including books, magazines, CDs and DVDs.
  • Our library staff facilitated 70 tech help sessions which supported 796 community members.
  • 4,093 community members accessed free wi-fi across the 9 library locations and 9,772 community members accessed the internet on computers within the libraries.
  • 83 local small businesses accessed the HIVE co-working space.
  • For those unable to access our libraries, 412 individuals including 23 aged care facilities and 26 retirement villages received home delivery services.
  • Our library service was supported by (library 171 volunteers) community volunteers who donated 330 hours of their time.
  • 6,766 community members connected with staff at 358 programs to improve sustainability, learning and wellbeing.

Outcomes for first quarter of 2024/25 included:
  • Libraries Learning and Discovery Plan 2024-2028 was endorsed by Council and is preparing for the 'Have Your Say' consultation process.
  • Delivery of face to face library programming and events for children and adults, with 25,704 attendees
  • Library loans of 588,165.
  • Delivery of home library service to 473 individual library members and 23 aged care facilities.
  • Library visitation of 274,852 community members.
  • 2,593 programs delivered in support of library programming and community engagement outcomes.
HC4.4.1 - Arts Culture and Heritage Plan 2023-2027 June 2025 On Track Arts, Culture and Heritage Plan outcomes for September included:
  • Creative Industries worked with the Disaster Resilience team to host a Psychological First Aid workshop for local creatives and a Creative Recovery Stitching training workshop at the Kingston Butter Factory in which 12 people participated.
  • Artwaves 2024 exhibition opened at the Logan Art Gallery featuring over 300 local high school students' art works.

Outcomes for the first quarter of 2024/25 included:
  • Logan Artist Soft Pitch event on 16 August at the Kingston Butter Factory Cultural Precinct, with 31 attendees
  • School tours at Logan Art Gallery, Living Museum of Logan and Mayes Cottage, with 760 attendees
  • Grug School performance on 21 August at the Kingston Butter Factory Cultural Precinct, with 480 attendees
  • Youth Alive Wonderworld event on 30 August at the Kingston Butter Factory Cultural Precinct, with 5400 attendees
  • 883 people visited the 'Brett Whiteley Inside the Studio' exhibition at Logan Art Gallery
  • 'Progression Playground' exhibition opening at the Living Museum of Logan, with 106 attendees
  • 'Brett Whiteley: Inside the Studio' exhibition opening, teachers preview and first weekend, with a total of 869 attendees.

6. Economy and growth (EG)

Project name Target Status Commentary
EG5.1.1 - 2032 City of Logan Legacy Roadmap June 2025 On Track The City of Logan Legacy Roadmap (Roadmap) was endorsed by Council on 13 June 2023 (Minute No. 52/2023).

In the first quarter of 2024/25, planning commenced for a Community Forum to seek feedback on the initiatives in the Roadmap. It is anticipated that the Forum will be held in March 2025.

Progress was also made on a number of identified initiatives in the Roadmap, including:

Deliver new community facilities and infrastructure

  • Council continued to work with the Queensland Government and Games Venues and Legacy Delivery Authority to progress and finalise the Detailed Business Case for the Logan Indoor Sports Centre. In September the Australian and Queensland Governments announced funding to build the multipurpose 9-court indoor sports centre in Logan Central. Council and the Games Delivery Authority executed one of the project agreements (Initiative No.1).
  • Internal discussions commenced relating to carbon offset programs (Initiative No. 8).
  • Stimulate economic growth
  • Progress was made on the short-term accommodation study to understand demand drivers and delivery constraints (Initiative No.11)
  • Discussions commenced with industry specialists regarding attracting pre-games training camps (Initiative No. 13).

Improve the health of Logan residents

  • Council supported an NFL Flag Come and Try day in July, with a second event scheduled for the second quarter of 2024/25 (Initiative No.10).
  • Leverage the cultural diversity of the Logan community
  • Working with partners to investigate barriers to volunteerism across multicultural groups (Initiative 4).

It is proposed to clarify the project description by amending the action and outcome statements to:
Action: Progress the feasibility analysis and delivery of 2024/25 identified initiatives and priorities of the 2032 City of Logan Legacy Roadmap.
Outcome: Logan can leverage the opportunities that the 2032 Games offer, including:
  • deliver new community facilities and infrastructure
  • stimulate economic growth
  • improve the health of Logan residents
  • leverage the cultural diversity of the Logan community.

The purpose of this amendment is to more accurately align planned deliverables and outcomes for 2024/25 to the endorsed Roadmap. Since endorsement in June 2024, future deliverables have been more clearly identified, including those for the 2024/25 financial year. The revised project description better reflects this alignment.
EG5.5.1 - Logan Plan Public Consultation June 2025 Monitor Council is awaiting advice from the Queensland Government (State) on several matters. The State recently advised that Council's updated growth projections are satisfactory, however direction on key matters remains outstanding. For this reason, the project is reported as monitor. A report will be presented to Council in November, 2024 to advise status and seek direction.

It is proposed to amend the project name to:
Logan Plan Public Consultation

The reference to 2025 is to be removed due to the negotiations with the State having extended beyond 12 months with little progress, therefore the Logan Plan date is no longer viable.

It is further proposed to clarify the project description by amending the action statement to:
Action: Progress the State Interest Review with the Queensland Government to achieve approval for statutory (formal) public consultation for Logan's proposed new planning scheme.

This reflects the State's direction mid-year to extend the State Interest Review period to improve alignment with the updated SEQ Regional Plan prior to State approval of the draft scheme for public consultation. Officers are still waiting to receive clear information on the required changes. Further delays will result from the caretaker period ahead of the State election and the potential machinery of government changes.

7. Infrastructure (IN)

Project name Target Status Commentary
IN6.1.1 - Captial Works Design Program June 2025 On Track There are a total of 37 Detailed Engineering Design Projects in the Capital Works Design Program scheduled to be completed in the 2024/25 financial year.

In the first quarter of 2024/25, a total of 11 Detailed Engineering Designs were completed and issued for the next phase of the project lifecycle (i.e. Delivery).
IN6.1.2 - Design of Bethania to Logan Village rail trail June 2025 On Track Detailed design for the Bethania to Logan Village rail trail is on track to completed by June 2025.

During the detailed design, it was determined that the funding allocation to deliver this project was insufficient. Council endorsed to write to the state government (TMR) seeking additional funding to deliver this project in full.

The state government has gone into caretaker mode for the upcoming state election, so Council will not receive a response until after the state election.

Negotiations are on-going with Palm Lakes Resort regarding security / safety measures for Palm Lakes.
IN6.1.3 - Road and Drainage Capital Works Program June 2025 On Track At the end of the first quarter, delivery of the Capital Roadworks and Drainage Program achieved $40.8 million in overall expenditure, which was ahead of planned budget expenditure at 123% of adopted budget milestone targets.

Notable projects under construction throughout the first quarter include:
  • Loganlea Road Upgrade from University Drive to Pacific Motorway (6 lanes)
  • Chambers Flat Road Upgrade, Chambers Flat from Mount Lindesay Highway to Kings Way
  • Stormwater drainage upgrades to Stage 1 and 2 of the Cowper Avenue Catchment Master Drainage Project, Eagleby
  • Stormwater drainage upgrades to Stage 1 to 5 of the Kelly Street Catchment Master Drainage Project, Eagleby
  • Stage 2 of local road kerbing and stormwater drainage upgrades to streets in Jimboomba (Anders Street, Cross Street, Spring Street and Manning Street)
  • Leopardwood Road Local Road Upgrade, Cedar Grove
  • Cinderella Drive Shared Path, Springwood
  • Dennis Road, Cinderella Drive and Barbaralla Drive, Springwood Intersection Upgrade
  • Park Ridge Road, Clarke Road and Lindenthal Road, Park Ridge Intersection Signalisation
  • Teviot Road and Cusack Lane, Riverbend and South Maclean Intersection Signalisation
  • Grand Plaza Drive and Eastern Drive Shared Path, Browns Plains.

The Capital Roadworks and Drainage Program delivers enhanced transport and drainage infrastructure across the City of Logan. The Program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure network.
IN6.1.4 - Way2Go Refresh June 2025 Monitor In the first quarter of 2024/25, the following progress has been made towards the Way2Go Refresh:
  • Way2Go audit report was prepared and reviewed by Transport and Infrastructure Planning programme; the consultant has addressed comments and provided an updated draft. Audit report not yet shared with internal stakeholders.
  • A funding source for Council project managers has been identified.
  • Proposed scope for strategy refresh has been drafted but not yet presented to Council's Executive Leadership Team (ELT).
  • A funding source for the refresh has yet to be identified. For this reason, the project is being reported as 'monitor'. Financial year 2025/26 Service Enhancement is likely to be submitted with the interim period used to agree on scope and to undertake procurement.

Quarter 1 progress summary:
The implementation of Council's Way2Go Transport Strategy has been audited and a scope for updating the strategy has been prepared. The next stages are internal stakeholder consultation on the audit findings, agreement on the refresh scope and underlying planning principles, budget securement and procurement of a consultant to undertake the refresh.
IN6.2.1 - Water and Wastewater Capital Works Program June 2025 On Track At the end of the first quarter of 2024/25, the Water and Wastewater Capital Works Program expenditure is tracking at $30.1 million against a phased budget of $34.8 million.

Expenditure will ramp up in coming months as more scheduled projects enter the construction phase.

The commencement of various green energy projects (solar) was activated following the completion of Council's energy Request for Proposal (RFP) process.
IN6.3.1 - 2024/2025 Parks Capital Works Program delivery June 2025 On Track Parks Capital Delivery achieved a year to date spend of $2.2 million against and forecast of $6 million.

This underspend relates to the phasing of the capital works program, with some projects completed ahead of schedule in the 2023/24 financial year, and delays in the asset renewal program. Phasing will be corrected in the first budget amendment. The overall program remains on track.

8. High performing organisation (HP)

Project name Target Status Commentary
HP7.1.1 - Rates Reform April 2025 On Track In the first quarter of 2024/25, the structural reform of the rating system progressed in line with the project management plan.

A high-level report, detailing rates reform for the 2025/26 budget, is scheduled for presentation to Council's Executive Leadership Team (ELT) in October 2024.

Following presentation to ELT, the report will be presented to Council's 'Setting the Scene' meeting later that month. Feedback received will inform additional aspects for investigation.
HP7.1.2 - Payment Channels June 2025 On Track In the first quarter of 2024/25, the following actions were completed towards delivery of the review of current payment channels:
  • report drafted ready for review
  • consultation undertaken with Council's Rates Department (Rates) to provide input
  • initial assessment of data completed
  • continuation of review of report with Rates.
HP7.2.1 - Disaster Management Capability and Capacity June 2025 On Track

In the first quarter of 2024/25, the following initiatives were undertaken towards strengthening the safety and wellbeing of the Logan community:
Voluntary Home Buy Back Scheme

Activities conducted:

  • demolition / removal of properties in Packages 3 – 6 progressed
  • liaison with various stakeholders – Logan City Council Properties, Abyss Demolitions, Buildable Approvals
  • property inspections
  • reporting to key stakeholders.

Challenges encountered:

  • lack of internal notifications of completion of internal works (removal of water meter and/or sewer capping) – this was addressed by constant follow up.

Guardian Incident Management System

Activities conducted:

  • Guardian Incidence Management System enhancements: Meetings with Vendor, conducted testing
  • support tickets – communication with vendor re: new tickets, follow up, testing and closeout
  • maintenance and updates – Users, Configurations, creation of templates
  • Flood Intel System – meeting with River and Catchment Engineering re Flood Intel System project status and training requirement

Challenges encountered:

  • development cycle – Development & Quality Assurance to deployment to Training environments.

Lessons Management

Activities conducted:

  • Community and Corporate Resilience Standard Operating Procedure - finalised
  • followed up existing Lessons Management actions / tasks outstanding.

Training

Activities conducted:

  • LDCC Refresher training
  • 2024 Guardian Incident Management System training
  • DLC training
  • Internal Cyber Security Training.
HP7.2.2 - Disaster Management Recovery and Resilience June 2025 On Track In the first quarter of 2024/25, the following initiatives were undertaken towards supporting enhanced resilience and recovery to disaster events for the Logan community.

Community Engagement:
  • Elders, Aboriginal and Torres Strait Islander organisations and Queensland Police Service representatives' engagement was held 9 September at Logan Central, to discuss the development of a 'First Nations disaster resilience strategy'.
  • An Elders co-design meeting with Jinndi Mibunn (an Aboriginal and Torres Strait Islander not-for-profit organisation) was held at Eagleby on 10 September. The meeting provided an opportunity for co-design of the upcoming Jinndi Jarjums Emergency Service Event.
  • An Emergency Services logistics meeting for Jinndi Jarjums emergency services event was held online on the 11-9-24.
  • A Jinndi Jarjums Emergency event, an Identified event for young Aboriginal and Torres Strait Islanders from the Jinndi Milbunn school holiday program and Foster Care program, was held on 18 September. Project partners included Jinndi Milbunn, Rural Fire Services, State Emergency Service, Queensland Fire Department and Queensland Police.The event provided an opportunity for young Jarjums to learn about emergency services, vehicles and equipment, and the people behind the uniform.
  • A meeting was held with Public Safety Training & Response Group Pty Ltd on the 13 September, to discuss the services they provide.
  • A presentation was provided on 17 September to all Councils, about the City of Logan - Voice of Students in Disaster Resilience' project, at the Get Ready Queensland, all Councils online meeting.
  • A meeting was held with Bunnings Underwood team on the 17 September, at their request, to develop an event in October for 'Get Ready Week'. We will partner with Bunnings to deliver a children's get ready activity on 5 October, and handout emergency plan booklets to families.
  • The Resilience and Recovery Officer attended the National Gathering First Nations Disaster conference, held 24 to 26 September.
  • A 'Whose Responsibility Is It' workshop was delivered at Yarrabilba on the 27 September.
During the month of September, logistics work has been substantial in the leadup to a large number of engagements scheduled for the October to December period. During this time 'Whose Responsibility Is It', Creative Recovery and Psychological First Aid workshops are planned to be held.
HP7.2.3 - Value for Money (VfM) Program June 2025 On Track The Value for Money (VfM) Program was introduced to Council in March 2022 and continues to deliver value to the organisation.

In the first quarter of 2024/25, the following was achieved:
A review was completed of all VfM initiatives implemented throughout financial year 2023/2024 and those completed were finalised. This information was included in the report delivered to Council in September.

A number of identified initiatives, led by various branches within Council, were closed as they achieved or overachieved the target set at the outset. The outcomes of those initiatives were hard savings, cost avoidance and reduction in organisational risk.

Two new potential VfM projects were identified and progressed, as detailed below:
  • Additional in-depth analysis of performance data for removal of litter and illegally dumped items to identify the benefits of consolidating those services into one service owner.
  • Development of a discovery action plan for the interbranch service level agreement initiative prior to taking it to the Gate 1 Gateway Moderation Team (GMT) meeting. The GMT determines how complex an initiative is, i.e., the initiative tier. This in turn drives the supporting documentation of an initiative.
HP7.2.4 - School Immunisation Program Review - Round 2 June 2025 On Track In September 2024, Round 2 of the School Immunisation Program is nearing completion.

Two super school clinics were planned for delivery in October to provide catch up opportunities for Year 7 and 10 students.

2025 planning is well underway with improvements being made to the schedule to improve uptake and vaccination rates.
HP7.2.5 - South-West Depot June 2025 On Track The live connection of the water main was completed in late September, with Certificate of Occupancy (COC) and final handover to Council occurring in early October.
HP7.2.6 - 2022-2026 People Plan June 2025 On Track Organisational people development for 2024/25 is focussing on the delivery of identified projects. In the first quarter of 204/25 the following was delivered:
Culture and engagement
  • Leaders are undertaking sessions with their teams to understand specifics and put meaningful actions in place.
  • Workforce planning
  • Organisational workforce plan data collection is underway. Operational workforce plan support is being provided upon request. Next steps include progressing the Policy through the correct processes.
  • Excellence in performance
  • Training is well underway, with 520 leaders and employees trained in the new way of working.
  • Succession management
  • Business critical roles have been identified through business continuity plans. A business engagement schedule has been planned.
Leadership development
  • Commenced analysis of the capabilities in the leadership levels against existing leadership programs. The Program Leader Academy is running as intended, and remaining Organisational Proficiency modules have been completed and launched.
HP7.3.1 - Digital Transformation Program delivery June 2025 On Track The Digital Transformation Program is working towards provision of a future, seamless, digital experience for Council staff and the community.

During the first quarter of 2024/25, the following progress was made towards delivery of projects under the Digital Transformation Program:

Financial Supply Chain and Enterprise Content Management
  • workshop conducted, positive feedback received
  • TechOne on track.
Human Resource and Payroll
  • TechOne progressing
  • Humanforce progressing.
Enterprise Asset Management Solution (EAMS) and Project Lifecycle Management
  • EAMS team coordinating, validation ongoing
  • Roads and Water configurations reviewed.
Geographical Information System (GIS)
  • business engagement established
  • Enterprise 10.9.1 in testing.
Integrations
  • integration stream and Boomi platform ready.
Data
  • data stream established
  • migration analysis started.
Business Readiness
  • control packs under development
  • SharePoint content and training workshops progressing.
Tranche 1 and 2
  • onboarding, testing, and upgrades progressing.

Program Management

  • health check, budget, and schedule on track
  • governance ongoing.
HP7.3.2 - Cemetery study June 2025 On Track In the first quarter of 2024/25, work progressed on the Cemetery Study to determine the current capacity and inform future planning.

Subject matter experts were engaged early to help inform the project.

A key achievement was the survey of the Beenleigh Cemetery.

Works for the Cemetery Study remain on track with site visits and interrogation of data planned for October.
HP7.3.3 - Review and update Council’s Water Netserv Plan June 2025 On Track Logan Water submitted the Water Netserv Plan (Part A) and Connections Policy on 5 August 2024 to the Department of Housing, Local Government, Planning and Public Works requesting endorsement of the plan by the Planning Minister.

On 17 September 2024, in accordance with section 99BR(5) of the Act, the proposed part A was taken to be endorsed as the Planning Minister had not refused or asked the SEQ service provider to make changes to the proposed part A within 30 business days of receipt.

Next steps include submission of a report to Council meeting (29 October) requesting adoption of the Water Netserv Plan Part A and its Connection Policy, and subsequent notice of adoption via letter to be given to the Planning Minister.
HP7.5.1 - Financial Policy Review April 2025 On Track In the first quarter of 2024/25, Initial discussions were held to inform the new process to amend the policy.

Work will commence shortly to draft amended wording to the relevant policies in preparation for the hold on policy reviews to be lifted.
HP7.5.2 - Safety in Design Processes June 2025 On Track In the first quarter of 2024/25, improvements to Council's Parks Branch Safety in Design (SiD) progressed.

Enhancements have been made to more effectively integrate risk assessments into the design process for park projects.

Formal and informal staff training opportunities have been identified.

The review of Parks Branch SiD processes is on track, with further progress being made in updating internal SiD documentation as well as preliminary internal training.
HP7.6.1 - Delivery of new Red Imported Fire Ant (RIFA) Suppression Taskforce Dec 2024 On Track During the first quarter of 2024/25, the Red Imported Fire Ant (RIFA) Taskforce worked alongside the National Fire Ant Suppression Team undertaking responsiveness and broadscale suppression throughout the City of Logan.
HP7.6.2 - Direct Hire Model - Process Creation and Implementation June 2025 On Track In the first quarter of 2024/25, the following has been achieved:
  • The annual traineeship and apprenticeship process kicked off in July and is on track for the quarter.
  • Bidding outcomes for 2025 positions have been shared with the business. Background work to set up positions to match the Award conditions completed with HR teams.
  • Preparation for the current year 2024 Traineeship and Apprenticeship Awards night is continuing. A coordinator position is temporarily vacant due to medical leave. This is expected to be resolved by mid-October. Some general business activities for the management of the 2024 cohort have fallen behind as a result of the resource constraint, however all critical items are on track.
HP7.6.3 - Talent Pathways June 2025 On Track During the first quarter 2024/25, the following activities were delivered:
  • The employment pathways project plans were drafted and put in motion in July.
  • At the end of the quarter, the research phase was completed on all initiatives.
  • Market and industry analysis, as well as a review of internal Council operations relating to these initiatives, has been conducted.
  • Findings have been drafted into Discovery reports and are scheduled for review with People and Culture Leaders in October.
  • Next steps will include Council's internal gateway approval and planning of the project schedule.