Mundoolun Road Rehabilitation Project
- Project typeRoad upgrades
- Project scheduleCompleted

Latest update
The upgrading of the sections of Mundoolun Road from the East Street / Edelsten Road roundabout to just north of Monmouth Court, and from John Collins Drive to Collins Creek Road was completed in December 2023.
Project overview
We are upgrading 4.5 kilometres of Mundoolun Road, from the East Street / Edelsten Road roundabout to just north of Monmouth Court, and from John Collins Drive to Collins Creek Road.
This project is being delivered under our Capital Roadworks and Drainage Program and is funded in part by the Australian Government through the 2022/23 Roads to Recovery Program. Improvements include a smoother road with wider lanes and shoulder, improved flood immunity and better intersections to keep you moving.
Project timeline
Early works, including clearing and the relocation of services started in January 2023. All early work activities are now complete. Main construction works commenced in late May 2023
It is expected that the road restoration works will be done between July and August 2023. Construction, including landscaping, lighting and line marking is anticipated to be completed December 2023, subject to weather and construction conditions.
Project features
The road upgrade will maintain safety as traffic increases. This means:
- raising the road in some sections to improve flood resilience
- improving how the road curves
- widening lanes and building wider shoulders
- road resurfacing in some sections
- improving drainage
- minor changes at some intersections to make turning easier for heavy vehicles.
Project benefits
The road upgrade will deliver a range of benefits, including:
- improve road conditions
- improve safety for all road users via lane and shoulder widening and smoothing out of some bends
- provide better flood protection for parts of the road corridor.
Project impacts
We will make every effort to minimise disruption. Given the nature of work, some temporary construction impacts can be expected:
- changed traffic conditions (including reduced speed limits, detours, and some traffic congestion)
- temporary disruption to driveway access (affected residents will be notified)
- increased noise, dust, and vibration
Motorists are encouraged to plan their journey and allow extra travel time. We thank you for your cooperation and patience as we work to provide a safer, more resilient, and reliable road network.