Eagleby Master Drainage Project – Stage 2
- Project typeStormwater drainage network upgrades

Latest update
July 2025 Update
BMD will be starting works on Kelly Street and Anthony Street from 15 July 2025, with construction activities expected to take 3 months to complete in this area, site and weather conditions permitting.
Works are continuing on Tralee Road, Dongarven Drive, Kenmare Street & the pedestrian pathways connecting them until the end of October also, site and weather conditions permitting.
Residents are reminded, you will have local access to your property most of the time, even if signed as ‘road closed’. Please speak with the traffic controllers. They may escort you through the work zone or ask you to wait for a short time until it is safe to drive.
Thank you for your patience and cooperation while we complete these essential works.
Upcoming works schedule
Bradley Park on Lemongrove Street, will continue to be used as the contractor site office. Bradley Park and all other storage and work areas will be fully restored once works are complete.
Location |
Works |
Dates |
Works notice |
Tralee Road and pedestrian paths connecting to Dongarven Drive and Fryar Road
|
- tree removal, and installation of temporary fencing, as required
- installation of new stormwater pipes
- gullies and pits
- road resurfacing
- concrete works
- driveway reinstatement, as required
- updates to utility services
- landscaping works
|
15 May 2025 to 30 October 2025, 7:00am to 5:00pm
|
Contractor works notice - Tralee Road and Paths(PDF, 719KB)
|
Willowie Crescent
|
- tree removal, as required
- installation of new stormwater pipes
- gullies and pits
- road resurfacing
- concrete works
- driveway reinstatement, as required
- updates to utility services
- landscaping works
|
15 May 2025 to 15 July 2025, 7:00am to 5:00pm
|
Contractor works notice - Willowie Crescent(PDF, 502KB)
|
Kelly Street and Anthony Street |
- tree removal, as required
- installation of new stormwater pipes
- gullies and pits
- road resurfacing
- concrete works
- driveway reinstatement, as required
- updates to utility services
- landscaping works
|
15 July 2025 to 30 October 2025, 7:00am to 5:00pm |
Contractor works notice - Kelly Street and Anthony Street(PDF, 619KB) |
Project features
Project features for the Eagleby Master Drainage Upgrade include:
- installation of 2.6 kilometres of new drainage infrastructure, including larger pipes, maintenance holes and culverts
- resurfacing parts of the road impacted by the works
- driveway and fencing reconstruction works (where required)
- replacement of kerb and footpath (where required)
- vegetation removal and tree trimming (where required)
- and replacement/relocation of services and restoration activities.
Project timeline
Works commenced on the Cowper Avenue catchment in January 2023, followed by the Kelly Street catchment in March 2023.
In early March 2024, works on the Eagleby master drainage project were placed on hold when the contractor responsible for the works, Allroads, was placed into administration.
In May 2024, BMD took over as the newly appointed contractor to complete all open works. These works concluded December 2024.
BMD successfully secured the new tender for stage 2 works. These works started on 17 February 2025 and should take approximately 10 months to complete (weather and contractor conditions permitting).
Project benefits
A range of benefits will be delivered as part of this project, including:
- allowing stormwater to drain more easily during wet weather events
- helping to protect people and property during these weather events
- building a more resilient and reliable stormwater network.
Project impacts
Given the nature of the work, unfortunately some impacts are unavoidable. This includes but are not limited to:
- increased noise, dust, and vibration
- temporary footpath closures or diversions, and/or temporary bus stop relocations (changes will be signed)
- temporary loss of street parking and driveway access (affected residents will be notified in advance)
- temporary closure of some local parks
- temporary water, sewer and power disruptions
- intermittent night works where required (residents will be notified).
Local traffic
Impact to local traffic conditions are to be expected.
- Changed traffic conditions including reduced speed limits, road/lane closures and detours (as needed).
- Traffic controllers will be available during working hours to assist as required.
- Motorists are advised to plan their journey and allow extra travel time. We thank you for your cooperation and patience as we work to provide a safer, more resilient, and reliable stormwater drainage network.