Areas scheduled for road resurfacing

Overview

The areas listed below are scheduled for road resurfacing. Please note these dates are subject to change at any time due to site and weather conditions.

General timeframes are provided for areas where exact work dates are not yet available. As those dates become available, the information will be updated.

Contractors work on behalf of Council to deliver road resurfacing for the community. These resurfacing works are generally a like-for-like replacement to ensure roads continue to be safe and driveable. Upgrades for road infrastructure are evaluated and considered under our larger capital works program

If you are concerned about the condition of a road, please contact us to report the issue to our maintenance team.

Division 1

Street Suburb When Work hours Type Extents

Parkwood Street, Rochedale South

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Parfrey Road to Passerine Drive

Roseland Avenue, Rochedale South

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Rochedale Road to Chamberlain Avenue

 

Chamberlain Avenue to Anna Marie Street

Abel Street, Springwood

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Barbaralla Drive to Raleigh Street

Adair Street, Springwood

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Abel Street to the cul-de-sac

Edgehill Crescent, Springwood

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Raleigh Street to Jardine Drive

Raleigh Street, Springwood

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Orlando Crescent to Jardine Drive

 

Grenville Street to Orlando Crescent

Willoughby Crescent, Springwood

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Raleigh Street to Abel Street

Inglis Court, Springwood

February to August 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Jardine Drive to dead end

Jardine Drive, Springwood

February to August 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Inglis Court to Todd Street

 

Todd Street to Rholanda Crescent

 

Barbaralla Drive to Inglis Court

Light Street, Springwood

February to August 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Jardine Drive to dead end

Todd Street, Springwood

February to August 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Jardine Drive to Belinda Crescent

Morgan Court, Springwood

February to August 2025

Monday to Friday, 9:00am to 2:00pm

Asphalt

Magellan Road to cul-de-sac

Nelson Court, Springwood

February to August 2025

Monday to Friday, 9:00am to 2:00pm

Asphalt

Magellan Road to cul-de-sac

Drake Road, Springwood

February to August 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Service Road to Barbaralla Drive

Jamberoo Street, Springwood

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Acmena Street to Barbaralla Drive

Wootton Crescent, Springwood

February to August 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Westmoreland Boulevard to Acmena Street

Division 2

Street Suburb When Work hours> Type Extents

Juers Street, Kingston

30 January to 27 February 2025

Sunday to Thursday, 8 pm to 5 am

Asphalt

Kingston Road to Third Avenue

Fawcett Street, Kingston

February to August 2025

 

Asphalt

Mayes Avenue to cul-de-sac

George Street, Kingston

February to August 2025

7:00am to 6:00pm

Asphalt

Clare Road to Augustus Street

Greenwood Street, Kingston

February to August 2025

7:00am to 6:00pm

Asphalt

Woody Avenue to cul-de-sac

View Street, Kingston

February to August 2025

7:00am to 6:00pm

Asphalt

View Street to cul-de-sac

Woodash Street, Kingston

February to August 2025

7:00am to 6:00pm

Asphalt

Carcoola Street to Ashvale Street

Woodrose Street, Kingston

February to August 2025

7:00am to 6:00pm

Asphalt

Carcool Street to Poppy Street

Woody Avenue, Kingston

February to August 2025

7:00am to 6:00pm

Asphalt

Redwood Street to Ashvale Street

Millers Road, Underwood

February to August 2025

9:00am to 4:00pm

Asphalt

278-292 Millers Road - 360-364 Millers Road

360-364 Millers Road - Beenleigh Road

Candish Street, Woodridge

February to August 2025

9:00am to 4:00pm

Asphalt

Acacia Road to Louden Street

Mactay Street, Woodridge

February to August 2025

 

Asphalt

Nurdi Street to dead end

Douglas Street, Woodridge

February to August 2025

9:00am to 4:00pm

Asphalt

Bruce Road to Smith Road

Smith Road to Victoria Street

Victoria Street to Kenny Street

Shannon Street, Woodridge

February to August 2025

7:00am to 6:00pm

Asphalt

Victoria Street to Romilda Street

Dorothy Street, Woodridge

February to August 2025

7:00am to 6:00pm

Asphalt

Karen Street to Monash Street

Kelvin Street, Woodridge

February to August 2025

7:00am to 6:00pm

Asphalt

Marlow Street to Lawrence Street

Southgate Drive, Woodridge

February to August 2025

9:00am to 3:00pm

Asphalt

Ewing Road to Roblyn Street

Mawson Street, Woodridge

February to August 2025

9:00am to 2:00pm

Asphalt

Smith Road to Lindley Street

Mikaga Court, Woodridge

February to August 2025

9:00am to 2:00pm

Asphalt

Mikaga Court to cul-de-sac

Division 3

Street Suburb When Work hours Type Extents

Millicent Street, Shailer Park

24 February to 10 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Doretta Street to Marana Street

Winona Street, Shailer Park

24 February to 10 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Millicent Street to Oringa Street

Shane Street, Shailer Park

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Ronald Street to Mahogany Court

Bauhinia Court, Shailer Park

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Oregon Drive to cul-de-sac

Oringa Street, Shailer Park

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Doretta Street to Aletta Street

Oregon Drive, Shailer Park

3 March to 17 March 2025

Monday to Friday, 9:00am to 4:00pm

Asphalt

Hickory Court to cul-de-sac

Mahogany Court, Shailer Park

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Oregon Drive to cul-de-sac

Hickory Court, Shailer Park

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Hickory Court to cul-de-sac

Pepperina Court, Shailer Park

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Oregon Drive to cul-de-sac

Trevallyan Drive, Daisy Hill

February to August 2025

9:00am to 2:00pm School Days
9:00am to 4:00pm Non School Days

Asphalt

Kinloch Road to 50 Trevallyan Drive

49 Trevallyan Drive to Springwood Road

Brigalow Street, Shailer Park

February to August 2025

7:00am to 6:00pm

Asphalt

Oregon Drive to dead end

Alan Street, Slacks Creek

February to August 2025

9:00am to 4:00pm

Asphalt

Queens Street to Brian Street

Hart Street, Slacks Creek

February to August 2025

9:00am to 4:00pm

Asphalt

Queens Road to Plain Street

Plain Street, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Wagensveldt Street to Meakin Road

Wagensveldt Street, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Plain Street to Veldt Street

Andrew Street, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Royal Parade to Windsor Street

Arch Street, Slacks Creek

February to August 2025

9:00am to 4:00pm

Asphalt

Queens Road to Duke Street

Beryl Street, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Anders Street to cul-de-sac

Diamond Street, Slacks Creek

February to August 2025

 

Asphalt

Kingston Road to Garnett Street

Garnett Street to Anders Street

Duke Street, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Kings Street to Cul-De-Dac

Royal Parade to King Street

Queens Lane, Slacks Creek

February to August 2025

9:00am to 4:00pm

Asphalt

Arch Street to Queens Road

Royal Parade, Slacks Creek

February to August 2025

9:00am to 4:00pm

Asphalt

Queens Road to Andrew Street

Ruby Street, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Diamond Street to Beryl Street

Barcelona Place, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Valencia Way to cul-de-sac

Meakin Road, Slacks Creek

February to August 2025

9:00am to 4:00pm

Asphalt

Edna Street to Paradise Road

Para Street, Slacks Creek

February to August 2025

7:00am to 6:00pm

Asphalt

Binganah Street to cul-de-sac

Division 4

Street Suburb When Work hours Type Extents

Bannockburn Road, Belivah

February to August 2025

9:00am to 2:00pm school days
9:00am to 4:00pm non-school days

Asphalt

Beaudesert Beenleigh Road to Hindsdale Court

Dairy Creek Road, Waterford

February to August 2025

9:00am to 3:00pm

Asphalt

Waterford Tamborine - 31-69 Dairy Creek Road

31-69 Dairy Creek Road - 71-103 Dairy Creek Road

Plunkett Road, Kairabah

March to August 2025

7:00am to 6:00pm

Spray seal

Waterford Tamborine Road to 450-460 Plunkett Road

Albert River Place, Tamborine

March to August 2025

7:00am to 6:00pm

Spray seal

2410-2486 Waterford Tamborine Road to Waterford Tamborine Park 69-109 Albert River Place

Plunkett Road, Tamborine

March to August 2025

7:00am to 6:00pm

Spray seal

Waterford Tamborine Road to 450-460 Plunkett Road

Benj amin Road, Logan Village

March to August 2025

7:00am to 6:00pm

Spray seal

Railway Parade to Pioneer Drive

Jillian Court, Logan Village

March to August 2025

7:00am to 6:00pm

Spray seal

Pioneer Drive to cul-de-sac

Pioneer Drive, Logan Village

March to August 2025

7:00am to 6:00pm

Spray seal

1404 Waterford Tamborine Road to cul-de-sac

Sarah Court, Logan Village

March to August 2025

7:00am to 6:00pm

Spray seal

Pioneer Drive to cul-de-sac

Steele Road, Logan Village

March to August 2025

7:00am to 6:00pm

Spray seal

79-87 Steele Road to 205-215 Steele Road

Malling Street, Waterford

March to August 2025

7:00am to 6:00pm

Spray seal

Waterford Tamborine to dead end

Division 5

Street Suburb When Work hours Type Extents

Browns Plains Road, Berrinba, Browns Plains and Heritage Park

20 February to 9 March 2025

Sunday to Thursday, 8:00pm to 5:00am

Asphalt

Bayliss Road to Wembley Road

 

Dean Street, Marsden

February to August 2025

7:00am to 6:00pm

Asphalt

Hickory Street to Leaza Street

Leaza Street, Marsden

February to August 2025

9:00am to 2:00pm School Days
9:00am to 4:00pm Non School Days

Asphalt

Hickory Street to Kim Street

Woodrow Place, Marsden

February to August 2025

 

Asphalt

Leatrice Street to Riverview Street

Bowman Lane, Waterford West

February to August 2025

7:00am to 6:00pm

Asphalt

end of seal to dead end

Francesca Street to end of seal

Division 6

Street Suburb When Work hours Type Extents

Loganlea Road,

2 June to 12 June 2025

Sunday to Thursday, 8:00pm to 5:00am

Asphalt

 

Starshine Street, Meadowbrook

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Allenby Drive to Fairway Drive

Links Avenue, Meadowbrook

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Allenby Drive to Fairway Drive

Fairway Drive, Meadowbrook

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Pavement Change to dead end

Fuller Avenue, Meadowbrook

3 March to 17 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Golfcourse Drive to Golfgreen Terrace

Carnival Street, Loganlea

10 March to 24 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Station Road to Catalina Street

Coral Street, Loganlea

10 March to 24 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Jean Street to Catalina Street

Surman Street, Loganlea

10 March to 24 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

O'malley Street to Coral Street

O’Malley Street, Loganlea

10 March to 24 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Haig Road to Surman Street

Mary Court, Loganlea

10 March to 24 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Surman Street to cul-de-sac

Elizabeth Court, Loganlea

10 March to 24 March 2025

Monday to Friday, 7:00am to 6:00pm

Asphalt

Surman Street to cul-de-sac

Beatty Street, Loganlea

February to August 2025

7:00am to 6:00pm

Asphalt

Jellicoe Street to Sturdee Street

Douglas Street, Loganlea

February to August 2025

7:00am to 6:00pm

Asphalt

Jellicoe Street to Douglas Street

Edward Street, Loganlea

February to August 2025

7:00am to 6:00pm

Asphalt

Jellicoe Street to cul-de-sac

Keyes Street, Loganlea

February to August 2025

9:00am to 4:00pm

Asphalt

Sturdee Street to Jellicoe Street

Haig Road to Sturdee Street

Roslyn Court, Loganlea

February to August 2025

7:00am to 6:00pm

Asphalt

Robert Street to cul-de-sac

Teys Road, Holmview

March to August 2025

7:00am to 6:00pm

Spray seal

21-31 Stoneleigh Way to 46 Teys Road

Division 7

Street Suburb When Work hours Type Extents

Browns Plains Road, Berrinba, Browns Plains and Heritage Park

20 February to 9 March 2025

Sunday to Thursday, 8:00pm to 5:00am

Asphalt

Bayliss Road to Wembley Road

 

Coronado Street, Browns Plains

February to August 2025

7:00am to 6:00pm

Asphalt

Browns Plains Road to Saratoga Street

Zorina Street, Browns Plains

February to August 2025

7:00am to 6:00pm

Asphalt

Saratoga Street to Tiffany Street

Silvertop Street, Hillcrest

February to August 2025

9:00am to 4:00pm

Asphalt

Anzac Avenue to Vinca Street

Vinca Street to Conifer Street

Division 8

Street Suburb When Work hours Type Extents

Lake Amaroo Court, Logan Reserve

February to August 2025

7:00am to 6:00pm

Asphalt

Lake Amaroo Court to dead end

Lake Bogong Court, Logan Reserve

February to August 2025

7:00am to 6:00pm

Asphalt

Lakeview Drive to cul-de-sac

Lake Borumba Street, Logan Reserve

February to August 2025

7:00am to 6:00pm

Asphalt

Lakeview Drive to Lake Manchester Street

Lake Kurwongbah Court, Logan Reserve

February to August 2025

7:00am to 6:00pm

Asphalt

Lakeview Drive to dead end

Lake Somerset Court, Logan Reserve

February to August 2025

7:00am to 6:00pm

Asphalt

Lake Borumba Street to cul-de-sac

Division 9

Street Suburb When Work hours Type Extents

Alvisio Court, Cedar Grove

March to August 2025

7:00am to 6:00pm

Spray seal

Whitaker Road to cul-de-sac

Arthy Drive, Cedar Grove

March to August 2025

7:00am to 6:00pm

Spray seal

Whitaker Road to Irwin Road

Boondarn Court, Cedar Grove

March to August 2025

7:00am to 6:00pm

Spray seal

Deltoro Road to cul-de-sac

Errol Court, Cedar Grove

March to August 2025

7:00am to 6:00pm

Spray seal

Arthy Drive to cul-de-sac

Saturn Court, Cedar Vale

March to August 2025

7:00am to 6:00pm

Spray seal

Bamboo Drive to cul-de-sac

Sirius Court, Cedar Vale

March to August 2025

7:00am to 6:00pm

Spray seal

Bamboo Drive to cul-de-sac

Dianne Court, Glenlogan

March to August 2025

7:00am to 6:00pm

Spray seal

Victoria Drive to cul-de-sac

Victoria Drive, Glenlogan

March to August 2025

7:00am to 6:00pm

Spray seal

Henderson Road to cul-de-sac

Avery Court, Glenlogan

March to August 2025

7:00am to 6:00pm

Spray seal

Victoria Drive to cul-de-sac

Christopher Place, Jimboomba

March to August 2025

7:00am to 6:00pm

Spray seal

Heritage Road to cul-de-sac

Joy Place, Jimboomba

March to August 2025

7:00am to 6:00pm

Spray seal

Heritage Road to cul-de-sac

Heritage Road, Jimboomba

March to August 2025

7:00am to 6:00pm

Spray seal

Hughes Road to cul-de-sac

Mountain Ridge Road, South Maclean

March to August 2025

7:00am to 6:00pm

Spray seal

232-240 Mountain Ridge Road to 262-270 Mountain Ridge Road

Rosewood Road, Munruben

March to August 2025

7:00am to 6:00pm

Spray seal

Grevillea Road to Geraldton Road

Albert River Place, Tamborine

March to August 2025

7:00am to 6:00pm

Spray seal

2410-2486 Waterford Tamborine Road to Waterford Tamborine Park 69-109 Albert River Place

Geraldton Road, Chambers Flat

March to August 2025

7:00am to 6:00pm

Spray seal

Myall Terrace to Rosewood Road

Sheils Road, Chambers Flat

March to August 2025

7:00am to 6:00pm

Spray seal

Rossmore Road to Mcpherson Road

Division 10

Street Suburb When Work hours Type Extents

Benwerrin Road, Loganholme

February to August 2025

7:00am to 6:00pm

Asphalt

Cul-de-sac to Constellation Drive

Elgata Avenue, Loganholme

February to August 2025

7:00am to 6:00pm

Asphalt

25 Elgata Avenue to Barah Street

Tarandi Street, Loganholme

February to August 2025

7:00am to 6:00pm

Asphalt

Pavement Change to Constellation Drive

 

17 Tarandi Street to 22 Tarandi Street

Honeysuckle Court, Cornubia

March to August 2025

7:00am to 6:00pm

Spray seal

Wuduru Road to cul-de-sac

Woodhaven Place, Cornubia

March to August 2025

7:00am to 6:00pm

Spray seal

Wuduru Road to dead end

Hals Place, Cornubia

March to August 2025

7:00am to 6:00pm

Spray seal

Woodhaven Road to dead end

Division 11

Street Suburb When Work hours Type Extents

Brightwell Street, Greenbank

March to August 2025

7:00am to 6:00pm

Spray seal

Stoney Camp Road to cul-de-sac

New Beith Road, Greenbank

March to August 2025

7:00am to 6:00pm

Spray seal

88-96 New Beith Road to Hobury Road

Division 12

Street Suburb When Work hours Type Extents

Peacock Avenue, Beenleigh

February to August 2025

7:00am to 6:00pm

Asphalt

Blackbird Street to dead end