Operational plan report - Quarter 1, 2022 / 2023

Total projects for 2022 / 2023 Quarter 1: 87

Corporate Plan focus areas Total
Maintaining current levels of service (MS) 3
Proud city (PC) 13
Environment (EN) 9
Healthy connected community (HC) 14
Economy and growth (EG) 8
Infrastructure (IN) 16
High performing organisation (HP) 12
Total 75

Project status Total
On Track 70
Completed 2
Monitor 3
Not Completed 0
Not Proceeding 0
Total 75

You can view each priority focus area for Quarter 1, 2022 / 2023 below which includes a status update on Operational Plan key project delivery.

Maintaining current levels of service

Project Target Status Commentary

MS1.1.1 - Logan Listens Residents' Survey

Deliver the Logan Listens: Residents' Survey, including a review to identify and apply improvements.

Purpose: To monitor the level of community satisfaction with major services.

June 2023 On Track As at the end of the first quarter, the project achieved the following:
  • The survey questionnaire was reviewed and finalised with input from participating branches.
  • The finalised questionnaire was approved for release.
  • The survey commenced on Monday 5 September and was delivered by Taverner Research Group on behalf of Council.
  • A marketing plan was developed and activated in the week prior to survey release. The plan included coverage by social media, Council's customer services centres, libraries and the Beenleigh big screen as well as information for dissemination by Councillors.
  • Once the survey has been completed, feedback will be analysed and findings presented via an official report to ELT and then to Council.
About the Residents' Survey

Every 2 years Council conducts its 'Logan Listens' Residents' Survey. This survey provides a unique insight into how the community views our performance on a range of services and facilities we deliver. The results from this survey assist us in determining which areas require greater attention as well as identifying other potential opportunities to improve the community's overall satisfaction with Council.

MS1.2.1 - Customer Service charter and standards update

Deliver an update to the Customer Service Charter and standards.

Purpose: To support Council to meet the needs and expectations of the community.

June 2023 Monitor As at the end of the first quarter the following actions were completed to support the delivery of the customer service charter:
  • Draft Charter Completed
  • An update was provided to ELT on progress
  • The CEO advised that the whole of Council consultation is to be rescheduled for the new year. This is due to the amount of change happening across the organisation. For example, the organisational restructure
Recovery actions
  • The project will commence whole of Council consultation early in the new year. It is not anticipated that this will impact the project's delivery date (June 2023) at this stage.
  • Planning for expediting this process is being looked at to help ensure the project's schedule remains on track

MS1.3.1 - Data analytics and customer insights

Deliver a data analytics and customer insights system.

Purpose: To better understand what our customers, and the community are saying and experiencing when interacting with Council.
Those insights will be used to make more meaningful data-driven decisions.

June 2023 On Track As at the end of the first quarter the following actions were completed to support the delivery of data analytics and customer insights:
  • The service enhancement for the project was approved (June 2022) from the 2022/2023 budget process.
  • A tender committee was formed in July 2022.
  • Tender documents were completed first week of September 2022.
  • The tender was released to market 30 September 2022.

Proud City

Project Target Status Commentary
PC2.1.1 - City of Logan corporate rebrand

Deliver the citywide rebrand project in line with the project plan.

Purpose: To bring a valued and unified visual identity to Council and the City of Logan.
June 2023 On Track As at the end of the first quarter, the project achieved the following:
  • Branding review of all Community Centres completed and report submitted
  • Rebranding and installation of new signage of 20 Community Centres completed
  • Rebranding and installation of new signage at Councils Transfer Stations and Recycle Market completed
  • Branding updates completed at the Parks Depot, Roads Construction Maintenance and Plant Fleet Services buildings
  • Parks Statutory Signage manual developed and implemented
  • Review of Welcome to Logan signs completed, signs removed and assets written off
  • Review of proposed sites for new welcome signage underway. Draft designs received, quotes for production and installation being sought
  • Phase 1 of the development of corporate signage manual commenced including internal stakeholder consultation and existing signage review
PC2.2.1 - City of Logan: Safe City Strategy and Action Plan 2021-2025

Deliver the second-year actions outlined in the City of Logan: Safe City Strategy and Action Plan 2021-2025 through a broad range of crime prevention and community-based safety initiatives.

Purpose: To create a safer City of Logan.
June 2023 On Track During the first quarter of 2022/2023, delivery of a range of actions from the City of Logan: Safe City Strategy and Action Plan 2021-2025 continued. The following key highlights were achieved:
  • 25% of planned activities for the year were achieved. This is in line with the project's schedule for the end of quarter 1.
  • The Safe City Awards Evaluation Panel met to evaluate nominations and determine award recipients, in preparation for the awards ceremony on 27 October 2022. A total of 12 nominations were received for the 2022 Safe City Awards, which exceeded the target number of nominations for the awards.
  • Completion of 6 Crime Prevention Through Environmental Design (CPTED) audits in response to reports of anti-social behaviour in parks and community leased facilities.
  • Providing CPTED advice to internal stakeholders including:
    • Sport Leisure and Facilities Branch in relation to 2 community leased facilities,
    • Economic Development and Strategy Branch regarding the Draft Streetscape Character Strategy,
    • Road Infrastructure Planning Branch regarding the extension of an existing cycle network project,
    • Economic Development and Strategy Branch regarding the second draft of the Streetscape Character Strategy
    • Social Planning Program regarding a community space.
  • Community safety feedback provided on 10 liquor licence applications and general feedback provided regarding a proposal for an additional large, licensed venue within the City of Logan.
  • Investigation and provision of Community Safety feedback to Economic Development and Strategy Branch in relation to the Roadmap Consultation Pack for the 2032 Olympic and Paralympic Games.
  • Delivery of the Services at the Square event on 21 July 2022, in partnership with Beenleigh Probation and Parole. This event engaged approximately 20 community members, connecting them with local support services.
  • Delivery of the Youth Street Hubz event on 27 July 2022, at Tudor Park. This event engaged approximately 40 young people, connecting them with youth-specific local service providers.
  • Hosted a Community Safety information stall at the rescheduled Logan NAIDOC event, sharing information and connecting with First Nations community members and local community service agencies.
  • Delivered a Crime Time Trivia activity to approximately 35 community members, supporting Daisy Hill Neighbourhood Watch with their annual Seniors Morning Tea event.
  • Delivery of the Services on Station event on 15 September 2022, in partnership with Logan Probation and Parole. This event engaged approximately 20 local community members, connecting them with Logan-based support services.
  • Delivery of a Youth Street Hubz event on 7 September 2022, at Crestmead Park. This event engaged approximately 80 young people and their families, connecting them with youth-specific local service providers.
  • Hosted a community safety information stall at the Forde Seniors Expo on 30 September 2022, attended by approximately 700 senior community members.
  • Submitted a grant application through the Investing in Queensland Women's Grant to seek financial support to deliver additional community safety activities in 2023 focused on supporting those impacted by Domestic and Family Violence in Logan City.
  • Hosted a meeting with the Logan District Crime Prevention Unit to discuss upcoming events/ activities, shared priorities and emerging trends or issues.
  • Attended the Logan Youth Network meeting to discuss emerging issues amongst Logan youth and identify collaboration opportunities to assist service providers with addressing these.
  • Investigated and responded to resident's concerns regarding hooning activity and liaised with local Police to undertake a targeted hooning operation.
PC2.2.2 - Swim Logan

Deliver water safety awareness education sessions. Provide culturally appropriate learn-to-swim activities for:
  • First Nations people
  • newly arrived migrants and refugees.

Purpose: To increase participant swimming skills.
December 2022 On Track During the first quarter, the Swim Logan program continued to provide a range of water safety awareness education sessions to the community. The following key highlights were achieved:
  • 15 water safety awareness education sessions were delivered to migrants and refugees aged 16 years and over.
  • 10 learn to swim programs were delivered to migrants and refugees aged 16 years.
  • 19 aquatics staff in Logan undertook the Cultural Awareness in Aquatics course. This training aims to equip swim teachers with the skills needed to engage culturally and linguistically diverse communities.
  • The first Logan NAIDOC at the Pools celebration was held in July, allowing free entry to the indoor heated pools at Beenleigh and Logan North Aquatics Centres. 40 people made use of the free hour of swimming.
  • Nyerroolahle Logan's Youth Pool Lifeguard program was delivered in September at the Logan North Aquatic Centre and Royal Life Saving Headquarters in Gumdale.
  • 4 Aboriginal and Torres Strait Islander young people successfully completed their pool lifeguard certification.
A progress report was delivered to Council 14 September.
PC2.2.3 - KRANK School Holiday Program

Deliver a school holiday program for 5- to 17-year-olds.

Purpose: To encourage participation in active and healthy programs.
To increase community participation during school holidays.
June 2023 On Track During the first quarter, the KRANK program continued to provide a range of school holiday events and activities to the community. The following key highlights were achieved:
  • 2021/2022 Annual Progress Report was presented to the City Lifestyle Committee on 14 September 2022 and was endorsed at full Council on 21 September 2022.
  • 184 school holiday activities were delivered.
  • 1,530 young people participated in the June/July school holiday program.
PC2.2.4 - Active and Healthy Program

Deliver a health and wellbeing program for all Logan residents.

Purpose: To encourage participation in:
  • affordable and accessible physical activities
  • health and wellbeing programs.
June 2023 On Track During the first quarter, the Active and Healthy Program continued to deliver a range of health and wellbeing events and activities to the community. The following key highlights were achieved:
  • 2021/2022 Annual Progress Report was presented to the City Lifestyle Committee on 14 September 2022 and was endorsed at full Council on 21 September 2022.
  • 308 health and wellbeing activities were delivered.
PC2.2.5 - Libraries Learning and Discovery Strategy 2019-2023

Deliver the outcomes of the Libraries Learning and Discovery Strategy 2019-2023.
This is delivered through the 6 priorities of:
  • economic opportunity
  • nurturing learning and well-being
  • sustainability
  • connected community
  • access and inclusion
  • embracing life-long curiosity and discovery.

Purpose: To support Logan's community through purposeful library programming
June 2023 On Track

About

The Libraries Learning and Discovery Strategy informs the programming deliverables of the Libraries and Creative Industries Business Plan. This strategy provides the framework to allow library staff to be guided in the development, implementation and evaluation of purposeful and engaging library programming and community engagement.

Quarter 1 update

In the first quarter of the 2022/2023 financial year, the following actions were undertaken in support of the Libraries Learning and Discovery Strategy:

  • Delivery of activities in Libraries including Page Turners, Baby Time, Wriggle and Rhyme and the Be Connected Service.
  • Delivery of take-home packs for families.
  • Delivery of online school holiday sessions for children.
  • Delivery of face-to-face and live streamed library programming and events for adults and children.
  • Successful redevelopment and continued delivery of Libraries on-demand job help services, offering patrons assistance with job searching, cover letters, resumes and interview preparation.

Outcome

Library staff developed, implemented and evaluated purposeful and engaging library programming and community engagement in support of the Libraries Learning and Discovery Strategy. Logan Libraries' on-demand job help services content was successfully completed, with 55 outreach events delivered across the City and over 1000 people recorded having accessed job help services.
PC2.3.1 - Events Strategy deployment

Deliver strategic outcomes from the endorsed Events Strategy.

Purpose: To enhance delivery of the existing events portfolio.
June 2023 On Track As at the end of the first quarter, the project achieved the following:
  • Twelve-month calendar of events completed
  • Events delivered include: Eats and Beats (Berrinba Wetlands and LSKD), IGNITE Youth Expo, Years of Service, Logan Loves Seniors Day.
  • Events supported include: NAIDOC Day, Congo Cultural Day, Qld Bush Poetry Championships, Chinese New Year Celebrations, PGA Champs and pro-AM, AKACON.
  • Events support is ongoing through the Small Event Grant applications and Event Sponsorship Funding.
  • Noting the delivery of events grants has transitioned to the Community Grants team in Community Development.
PC2.3.2 - Reconciliation Action Plan

Progress a detailed development plan for Council's next Reconciliation Action Plan.

Purpose:
  • to strengthen relationships
  • build knowledge within Council
  • identify opportunities
  • work towards outcomes that will support the organisation and Logan's Aboriginal and Torres Strait Islander community.
June 2023 On Track

About

Logan City Council's Reconciliation Action Plan will strengthen relationships, build knowledge within Council, identify opportunities and work towards outcomes that will support the organisation and Logan's Aboriginal and Torres Strait Islander community.

Quarter 1 update

In the first quarter of the 2022/2023 financial year, the following actions were undertaken:

  • Significant engagement with internal and external stakeholders during the first quarter, to progress project planning for the development of Council's third Reconciliation Action Plan.
  • Coordination of Logan's 2022 NAIDOC event in partnership with the Logan District Aboriginal and Torres Strait Islander Corporation for Elders. A survey conducted with community members and stall holders about the suitability of the location, local entertainment, community spirit and overall event, validated its success and will help shape the continuing success and future of this important community event, while evolving partnerships between Logan City Council and the Aboriginal and Torres Strait Islander community of Logan.
  • Through Council's partnership with the Logan Central First Nations School Cluster, a Services Fair was held at Logan Central Library during the first quarter, showcasing Logan Central Library's internal and external services and programs to Logan's Aboriginal and Torres Strait Islander community. 24 stallholders participated in the event, with 805 community members visiting the library and 31 newly activated memberships.
  • Participation at several key stakeholder meetings and events including 2022 NAIDOC report finalisation with Logan Elders Board Members, Logan Central Services at the Station event, Child Protection Week at Ewing Park and the South East Queensland Indigenous local government officers meeting hosted by Moreton Bay Regional Council.
  • A sprint was undertaken to investigate and determine options for the progression of reconciliation at Logan City Council. Planning is underway for a draft business case that will involve internal and external consultation.

Outcome

Relationships between Logan City Council and the Aboriginal and Torres Strait Islander community of Logan were strengthened. A sprint to investigate and determine options for the future progression of reconciliation at Logan City Council was completed.

PC2.3.3 - Access and Inclusion Plan

Coordinate and support implementation of the Access and Inclusion Plan 2019-2022.

Purpose: To create a more accessible and inclusive city for everyone.
June 2023 On Track During the first quarter, the Access and Inclusion Plan progressed well and is on track. The following key highlights were achieved:
  • An Access and Inclusion Internal Working Group meeting was held with representatives from 10 branches.
  • Provided an online engagement opportunity via Council's 'Have Your Say' online platform for the community to provide their feedback to shape the next action plan due to commence in 2023.
  • Delivered a workshop on 6 September with internal staff from 9 branches to finalise actions for the new disability action plan to commence in 2023.
PC2.3.4 - Community development initiatives

Deliver community development initiatives that strengthen and build the community.

Purpose: To respond to local priorities.
June 2023 On Track During the first quarter of 2022/2023, a range of community development initiatives were delivered to the community. The following key highlights were achieved:
  • Stories from the Kitchen dinner was held on 23 July and 13 September at Beenleigh Neighbourhood Centre and Crestmead Community Centre where 42 people attended from 20 different cultural backgrounds.
  • Chatty Café has been held on 20 July, 17 August and 21 September at five local cafes. A total of 50 residents have attended and 20 volunteers have signed up to run the program.
  • Joined the Welcoming Cities Network and became an official Welcoming Cities member on 24 August.
  • Community Training Program delivered:
    • Disability awareness training in August (15 attendees)
    • Belong training (supporting and working with LGBTIQIAP+) in September (22 attendees)
    • Mental Health First Aid training in September (10 attendees)
  • Supported the National Mental Health Commission in holding four community conversations in Logan to provide direct feedback in accessing or providing mental health and suicide prevention care. Over 100 people provided their feedback in person at these sessions held on 30 and 31 August.
  • Logan Youth Action Group (LYAG) meeting was held in July where 13 young people attended and September where 17 young people attended. They presented on their 4 project areas; education and employment, community safety, environment sustainability and mental health and wellbeing.
PC2.3.5 - Aboriginal and Torres Strait Islander Bursary Program

Deliver the Aboriginal and Torres Strait Islander Bursary.

Purpose: To support employment opportunities in Council for Aboriginal and Torres Strait Islander peoples.
June 2023 On Track As at the end of the first quarter, the project achieved the following:
  • Information was distributed to schools enabling the submission of applications for the bursary.
  • The is in line with the project's projected progress
PC2.3.6 - Living Museum of Logan

Deliver the Living Museum of Logan exhibition and programs in collaboration with the community.

Purpose: To:
  • share the stories of our culturally diverse communities and of Logan’s Aboriginal and Torres Strait Islander communities
  • share themes of importance to Logan's people
  • enhance visitor experience to the City of Logan
June 2023 On Track

About

The Living Museum of Logan tells the stories of the people of Logan, and is a non-collecting, family-friendly space where residents and visitors to Logan can be inspired and learn about the City of Logan.

Quarter 1 update

In the first quarter of the 2022/2023 financial year, the following actions were undertaken:

  • The official ribbon cutting of the Living Museum of Logan and Butterbox Theatre took place.
  • Living Museum of Logan community event was held and included insightful artist talks by the 4 artists commissioned to create public art works for the Museum and Kingston Butter Factory Cultural Precinct, as well as one artist whose art work was featured in the current 'Nourish' display.
  • First Nations elders attended a morning tea, acknowledging their knowledge, generous advice and collaborative work in the visioning and creation of a culturally significant First Nations space within the museum.
  • A well-attended public program was held in partnership with artist Dr Nicola Hooper, former Kingston Butter Factory community actor Michael Willmer and the Local Heritage Specialist, and shared the heritage of the Kingston Butter Factory through photographs and interactive public artwork 'Factory stories'.
  • Preparations commenced for the second round of displays for 'Nourish: food stories connecting people, cultures and countries', which will include new portraits and digital stories of the people of Logan.

Outcome

Installation of the Living Museum of Logan was completed and it is open to the public. The Museum tells the stories of the people of Logan and is a non-collecting, family-friendly space where residents and visitors are inspired, and learn about the City of Logan.

PC2.4.1 - Enhancement to City Administration Centre main entry

Deliver an enhanced main entry to the Logan city Council City Administration Centre.

Purpose: To provide a more attractive area for customers conducting routine business.
June 2023 Monitor As at the end of the first quarter, the following issues occurred with the project:
  • Due to current supply chain delays and the availability of external design consultants there was a delay in finalising the design.
  • Due to the current organisational structure changes, works associated with accommodation changes within the City Administration Centre is now to be aligned with the organisational structure changes. This in turn has required a reassessment of the works to be performed with the main entry enhancement project and available budget to be determined within the project scope.
Recovery actions
  • The project is seeking to finalise the design within the next 4-6 weeks of the second quarter, with consideration of the available budget to be allocated towards this project.
  • The project will seek to issue contracts for the required works in early 2023 with a completion date on or before 30 June 2023.

Environment

Project Target Status Commentary
EN3.1.1 - Albert and Logan Rivers accessibility and connectivity projects

Deliver initiatives identified in the Albert and Logan Rivers Accessibility and Connectivity Plans.

Purpose: To increase community connection, user experience and activation.
June 2023 On Track During the first quarter of the 2022/23 financial year, locations were scoped out for the delivery of the Logan and Albert River Vision art seat and Albert River trail. Discussions were held in regards to progressing the interactive canoe and kayak map. This project is on track.
EN3.2.1 - Riparian Restoration Projects

Deliver riparian rehabilitation along priority areas of the Logan and Albert Rivers.

Purpose: To enhance our green canopy and urban forest.
June 2023 On Track During the first quarter of the 2022/23 financial year, the following Logan and Albert River riparian rehabilitation actions were delivered:
  • Location scoped and site preparation commenced for the Trees for Fish community planting at Logan River Parklands.
  • Flood rectification work at Logan River Parklands project site was scoped and works commenced.
  • Skilling Queenslanders for Work group was appointed to commence Albert River Park riparian revegetation works in October, weather permitting.
  • Request for quotes developed and contractors engaged to continue maintenance works at Riverdale Park, Wolffdene South Reserve and Wendt Park.
  • This project is on track
EN3.3.1 - Environmental offset delivery

Deliver and maintain environmental (vegetation) offset planting sites.

Purpose: To enhance wildlife corridors and core habitat across the city.
June 2023 On Track During the first quarter of 2022/23 financial year, 3 months of maintenance was completed at existing environmental (vegetation) offset sites. Planning for the upcoming financial year commenced, which included establishment and stakeholder engagement for potential new Council owned and managed environmental (vegetation) offset sites. Development of the private land environmental (vegetation) offset program continued to progress. This project is on track.
EN3.4.1 - Environmental conservation partnerships

Deliver environmental conservation partnerships.

Purpose: To support the community to:
  • become more sustainable
  • conserve and restore private land.
June 2023 On Track During the first quarter of the 2022/23 financial year, Environmental Conservation Partnerships achieved the following:
  • 843 members in total participating in the program
  • 35 new Habitat Connections members joined the program (404 properties in total)
  • 13 new Land for Wildlife properties were registered making 439 properties in total (5 property deregistered from the program)
  • 1 new Voluntary Conservation Agreement and 1 new Voluntary Restoration Agreement taking the total formal agreements (Voluntary Restoration Agreement, Voluntary Conservation Agreement and Voluntary Conservation Covenant) to 28
  • 7 formal agreement annual visits were completed
  • 14 Land for Wildlife property revisits were conducted
  • 352 individual community engagement interactions were provided to community members
  • 22.58 hectares added to the Land for Wildlife habitat network bringing the total to 6,187.6 ha
  • Annual Environmental Conservation Partnerships Celebration day was held at Eagleby Wetlands on August 28 with 300 community members in attendance. This project is on track.
EN3.5.1 - Environmental events and activities

Deliver a range of environmental events and activities.

Purpose: To:
  • encourage environmental stewardship
  • enhance environmental awareness across the community.
June 2023 On Track During the first quarter of the 2022/23 financial year, the Environmental Events and Activities program completed scheduling of this financial years events and activities. The following events and activities were delivered to the community:
  • Agents of Discovery Adventure Walk was held on 14 August at Berrinba Wetlands with 5 participants
  • Agents of Discovery Adventure Walk was held on 14 August at Riverdale Park with 15 participants
  • Two Guided Bushwalks were held on 20 August at Spring Mountain Forest Park with 17 participants.
  • Platypus Fun kids workshop was held on 27 August at Mundoolun with 5 participants
  • Belivah Creek Community Planting was held on 27 August at Willmann Park with 25 participants
  • Environmental Conservation Partnerships celebration day was held on 28 August at Eagleby wetland with 300 attendees
  • Agents of Discovery Adventure Walk was held on 10 September at Berrinba Wetlands with 2 participants
  • Agents of Discovery Adventure Walk was held on 10 September at Riverdale Park with 4 registrations but no participants
  • Two Wildflower Walks were held, one on 4 September at Plunkett Conservation Park with 16 participants and 19 September with 20 participants.
  • Pest Fishing Cup was held at JJ Smith Park with 234 participants. 21 Carp, 6 Tilapia and 4 Gold Fish were caught and correctly disposed of.
  • Agents of Discovery Adventure Walk was held on 25 September at Berrinba Wetlands with 1 participant
  • Agents of Discovery Adventure Walk was held on 25 September at Riverdale Park with 2 participants
  • Two non-bookable Agents of Discovery Adventure Walk were held, one at Berrinba Wetlands on 20 September with 29 participants and at Riverdale Park on 30 September with no participants.
  • This project is on track.
EN3.6.1 - Decarbonisation - extended solar and new hydrogen capability

Complete an investigation to identify options for delivering sustainable outcomes in the way Logan Water delivers its services.

Purpose: To support the increased use of:
  • renewable energy
  • energy efficient technology
  • carbon reduction capabilities.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • Suitable sites have been identified.
  • Logan City Council power demand now well understood.
  • The project is currently working with consultant PWC to identify most suitable model for a potential renewable portfolio.
EN3.6.2 - Climate change resilience actions

Deliver actions identified in the Climate Change Resilience Strategy 2021-2031.

Purpose: To achieve climate change resilience outcomes for Council.
June 2023 On Track During the first quarter of 2022/23, the following was achieved:
  • Carbon offset credits were purchased.
  • Verification through an independent audit of the 20/21 carbon inventory finalised
  • The draft 21/22 Carbon inventory developed.
  • Progress meetings and background work commenced to look at the future of the SEQ Climate Resilient Alliance collaboration.
EN3.7.1 - Waste management and resource recovery

Deliver actions identified in the Waste Management and Resource Recovery Strategy 2022-2032.

Purpose: To minimise waste to landfill and increase recycling
June 2023 On Track As at the end of the first quarter, 40% of the ongoing and short timeframe actions in the Implementation plan have commenced. This is in line with the project's schedule. Examples and highlights for the quarter include:

Action item 1 - A 3-phase marketing campaign to promote the benefits of the green waste bin service commenced in September. Each phase lasts 3 months features digital and print messaging targeted at specific divisions. Green waste bins in service now total 16,737, an increase of 859 in the past 3 months.

Action item 11- Officers have a participated and contributed in Council of Mayors (SEQ) forums and workshops, discussing topics such as local government recycling infrastructure, managing food organics and garden organic (FOGO) and residual waste management.

Action item 15 - Six school waste and recycling educational and awareness sessions together with landfill facility tours have been conducted.

Action 16 - A marketing campaign to promote home composting that included a $50 rebate on the purchase of a compost bin, compost aerator, worm farm or Bokashi composting system commenced in September. Council has now provided a total of 369 rebates to residents, 141 in the past 3 months.

Action item 27- Phase 1 of the transition to digital waste voucher commenced in July when 30,000 customers that receive e-mail rates notices were provided with the opportunity to access digital waste vouchers. As of the end of September 2022 over 3500 digital waste vouchers have been issued to over 3000 online accounts. Over 1200 digital vouchers have been presented for use at Council facilities.

Action item 30 - Landfill environmental monitoring, as required by the site Browns Plains Waste & Recycling Facility Environmental Authority, has been conducted with the results and commentary submitted to the Department of Environment and Science.

Action item 31 - A meeting of the Browns Plains Landfill Community Consultative Group was held on 20/07/2022 to provide a forum to discuss operational issues and raise any concerns relating to the Browns Plains Waste & Recycling Facility.

Action item 35 - Collaboration between Sub-Regional Alliance partners (Ipswich CC, Redland CC and Logan CC) continues. Tender evaluation and on-site ground investigation works are ongoing for the construction of the proposed Material Recycling Facility at the Browns Plains Waste & Recycling Facility.
EN3.8.1 - Electric Vehicle Feasibility Strategy

Deliver an electric and hybrid vehicle and plant assessment.

Purpose: To:
  • help determine efficiency and operational cost savings
  • outline which Council vehicles and plant would benefit from transitioning to electric or hybrid vehicle.
June 2023 On Track As at the end of the first quarter, Teletrac Navman has completed software development and testing. The company's State Manager has advised that they expect to showcase a report to Council by the end of October 2022. The report will identify vehicles that are suitable for electric transition based on utilisation and location.

To ensure the accuracy of Teletrac Navmans data, a scope of works has been developed to seek the services of a suitable service provider to carry out an electric vehicle feasibility study on the Council's fleet.

Next steps - Potential service providers will be researched and invited to quotation. A service provider will be engaged in December with a project start date of January 2023.

Healthy connected community

Project Target Status Commentary
HC4.1.1 - The Buzz at Yarrabilba

Deliver and activate a community centre in Yarrabilba.

Purpose: To support and foster social connections, learning and economic opportunities in an emerging community.
December 2022 On Track During the first quarter of 2022/23, construction of the facility remains on track for completion in October/November 2022. Key achievements during this period include:
  • Progression of the commercial lease with TAFE Qld
  • Tender assessment and negotiations for the operator of Pods 1 & 2.
  • The facility is on track for official opening in late 2022.
HC4.1.2 - Wilbur Street Youth Centre

Design a youth centre in Logan Central.

Purpose: To:
  • provide an inclusive and safe facility for young people
  • support recreation and participation in activities and programs
June 2023 On Track During the first quarter of 2022/23 the Wilbur Street Youth Centre concept design was reviewed and rescoped to align with project aims, community expectations and allocated budget. Functional brief for the centre has been drafted to progress to the next stage of design and construction.
HC4.1.3 - Beenleigh Aquatic Centre - renewal and upgrade

Design Stage 2 of the Beenleigh Aquatic Centre.

Purpose: To encourage increased participation and health outcomes for the City of Logan community
June 2023 On Track During the first quarter of 2022/23, broad-scale community and stakeholder engagement for the Beenleigh Aquatic Centre upgrade was completed to inform the design of the upgraded facility in Beenleigh. Council's team spoke with 130 community members face-to-face or over the phone, and 396 community members completed the online survey. The key findings are being used to draft a design brief.
HC4.1.4 - Community infrastructure implementation plan

Deliver the community infrastructure priorities outlined in the Community Infrastructure Implementation Action Plan 2022/2023.

Purpose: To provide quality facilities and spaces to meet the diverse needs of the community.
June 2023 On Track During the first quarter of 2022/23 the priority community infrastructure projects progressed well and key achievements include:
  • 25% of planned activities were delivered to plan. This is in line with expected project progress.
  • The Action Plan for 2022/2023 has been confirmed
  • Springwood Community hub a study to confirm land and built form requirements for future community hub commenced.
  • investigations for land for future CIS projects undertaken.
  • The Logan Central facilities gaps and opportunities project report was delivered to inform current and future projects in the area.
HC4.2.1 - Libraries Early Years and First 5 Forever initiatives

Deliver the libraries' early years services and First 5 Forever initiative.

Purpose: To support early years learning and reading for Logan families with children aged under 5 years
June 2023 On Track

About

First 5 forever aims to support the learning outcomes for all Logan children aged 0-5 years old by providing programs that offer talking, reading singing, playing, dancing and moving.

Quarter 1 update

In the first quarter of the 2022/2023 financial year, the following actions were undertaken:

  • Delivery of 267 COVID-safe, face-to-face children's literacy sessions to 4,297 participants across the city.
  • Delivery of 64 COVID-safe community outreach sessions to 1,846 participants, through network partnerships across the city.
  • Participation at 29 Key stakeholder meetings across Logan City.
  • Collaboration with the Parks Branch, ensuring delivery of high quality sessions that promote family connection, early literacy, Logan Libraries and parks across the City of Logan.

Outcome

The learning outcomes of Logan children aged 0-5 years old were supported. Pathways to resilience training was successfully delivered to early childhood educators.

HC4.2.2 - Animal management strategy

Deliver a new animal management strategy that creates a strategic roadmap for the future of animal management services.

Purpose: To improve public safety and animal-keeping outcomes in response to community demand and trends.
December 2022 On Track As at the end of the first quarter, the following was achieved:
  • Scoping for development of the Animal Management Strategy is complete.
  • A draft of the Animal Management Strategy is under development.
  • This is in line with the project's projected progress.
HC4.2.3 - School safety parking

Deliver a school safety parking campaign.

Purpose: To improve child safety and local neighbourhood amenity.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • Recruitment activities for the dedicated school liaison and parking officer are continuing.
  • A scoping workshop was conducted during September 2022 to support development of a school safety parking plan, being an appendix to the City Parking Strategy (deliverable in 2023).
HC4.3.1 - Active Logan Strategy Implementation 2020-2024

Deliver actions to support the delivery of the Active Logan Strategy Implementation 2020-2024.

Purpose: To improve our focus on:
  • active spaces
  • active people
  • active organisations.
June 2023 On Track As at the end of the first quarter, there are 11 Council branches actively working to deliver on the 129 actions identified in the Active Logan Strategy Implementation Plan 2020-2024. Over 60% of the actions were identified by Branches across the 4-year implementation plan duration as being commenced or completed.

Meetings with branches to discuss tracking and reporting are to be held by end of quarter 2.

During the next quarter (Q2) the project will continue reviewing methodology of tracking and reporting status of action across branches.
HC4.3.2 - Biosecurity strategy

Deliver a biosecurity strategy.

Purpose: To create a strategic roadmap for protecting the biosecurity, health and environment of the city.
April 2023 On Track As at the end of the first quarter, the following was achieved:
  • Scoping for development of the Biosecurity Strategy is complete.
  • Drafting of the Biosecurity Strategy has commenced.
  • This is in line with the project's projected progress.
HC4.3.3 - Illegal Dumping and Litter Enforcement Strategy 2022-2025

Deliver a strategic roadmap to reduce illegal dumping and littering in our community, through a 3-year action plan.

Purpose: To ensure the city of Logan is a clean and safe place to be.
October 2022 Completed As at the end of the first quarter, the following was achieved:
  • The Illegal Dumping and Litter Enforcement Strategy (2022 - 2025) was presented to the Executive Leadership Team (ELT) 25 August 2022.
  • Following this, the Strategy was endorsed by the City Lifestyle Committee on 14 September 2022.
  • A media release was then conducted.
  • Project complete.
HC4.4.1 - Arts, Culture and Heritage Strategy 2018-2022

Deliver outcomes of Council’s Arts, Culture and Heritage Strategy 2018-2022, and develop a new Strategy in consultation with community for 2023-2027.

Purpose: To improve community capacity and our city image through 5 outcomes:
  • development
  • engagement
  • places and spaces
  • partnerships
  • communication
June 2023 On Track

About:

The strategy is a whole-of-Council document that states Council's commitment to arts, culture and heritage. It defines the key areas, strategies and actions to guide the management, sites and provision, and plan for its future growth and development. The strategy outlines areas where Council will work to develop more opportunities for the community and its arts, culture and heritage professionals to watch, enjoy and participate in creative activities, with the aim of enhancing quality lifestyle, creative industries and business across the region. It is an integral part of developing the city as an emerging tourist destination.

The five key actions of Creative City: Logan City Council's Arts, Culture and Heritage Strategy 2018-2022 are development, engagement, places and spaces, partnerships and communication.

Quarter 1 update

In the first quarter of the 2022/2023 financial year, the following actions were undertaken:

  • A community event was held at the Living Museum of Logan on Saturday 20 August, welcoming artists and community to mark the opening of the museum and to share their significant contributions to the development of the first museum displays and commissioned public art.
  • Members of the First Nations working party were acknowledged at a morning tea event for their generous advice and guidance in the development of the First Nations space at the Living Museum of Logan.
  • Regional Arts Development Fund 2022/23 funding bid and a Queensland Arts Showcase Program outcome report for Logan Live Music 2021 were assessed and approved by Arts Queensland.
  • Community consultation for the Arts, Culture and Heritage Strategy 2023-2027 was completed during the first quarter.
  • A local heritage sector networking forum was held to support Logan's volunteer run museums.

Outcomes

Council's Arts, Culture and Heritage Strategy 2018-2022 continue to be delivered through community engagement, programs, services and venues. Local artists are recognised through the Regional Arts Development Fund.

Community engagement for the Arts, Culture and Heritage Strategy 2023-2027 was completed.

HC4.5.1 - Rosia Park

Complete:
  • statutory approval requests
  • 100% of design drawings
  • 15% of Stage 1 construction program.
Purpose: To provide facilities for an active and healthy community.
June 2023 Monitor

As at the end of the first quarter the application for environmental approval remains in progress. The team are exploring potential options to reduce the land area for the sports park and the impact on the Environmental Protection and Biodiversity (EPBC) process. The project is awaiting confirmation from the Department of Infrastructure, Transport, Regional Development and Communications on EOT for LRCI Phase 2 funding. The schematic design being finalised.

Recovery actions

  • The Branch are working with Council's consultants (NGH) to finalise the EPBC referral.
  • An update report of Rosia Park was provided to Council during the October 2022 committee round.
HC4.5.2 - Jimboomba Park Stage 2 (Rugby league clubhouse)

Complete:
  • 100% of design drawings
  • award of construction contract.

Purpose: To provide facilities for an active and healthy community.
June 2023 On Track As at the end of the first quarter the schematic design is complete, and the developed design is underway.

The developed design is expected to be achieved by the end of quarter 2.

The project will continue to work with consultants and club in quarter 2 to finalise the schematic design and commence developed design drawings.
HC4.5.3 - Renewal of the Logan North 50m Pool

Replace the Logan North 50m outdoor pool and associated plant and plant room.

Purpose: To keep providing aquatic programs and recreational activities at Logan North Aquatic and Fitness Centre.
December 2022 On Track As at the end of the first quarter, the project is finalising construction work including commissioning for handover which is expected early October 2022. Handover inspections are scheduled for the first week of October 2022.

The project will seek hand over in early October 2022.

Economy and growth

Project Target Status Commentary
EG5.1.1 - Destination Management Plan 2023-2028

Develop the Destination Management Plan 2023-2028.

Purpose: To identify future infrastructure needs and opportunities to grow Logan’s visitor economy
June 2023 On Track As at the end of the first quarter, the Destination Management Plan draft was completed. This is ahead of the scheduled 75% completion target for the draft. Consultation and review of the draft is now being conducted. Development of the plan is expected to be finalised by December 2022, with Council endorsement and adoption to be conducted thereafter.
EG5.2.1 - Logan Place Plan

Deliver the Logan Place Plan, our place making strategy covering:
  • policy
  • projects
  • programs across our centres.
Purpose: To:
  • incentivise public-private partnerships
  • rejuvenate our centres
  • foster pride, investment, and positive activity
June 2023 On Track As at the end of the first quarter, the following activities were achieved;
  • Councillors were briefed on the draft Night Time Economy Strategy, feedback was collated and the final strategy will be presented to Council in October for approval.
  • Key actions from the Night Time Economy Strategy will inform the Place Plan and future work program.
  • City centre implementation plans are being updated in line with the endorsed Urban Design Framework and new priority projects will be identified for implementation, subject to a budget allocation.
  • The drafting of the Place Plan document has been completed, is being reviewed within the EDS Branch with the next step to undertake internal consultation with branches to finalise a draft strategy for a briefing with Councillors early in 2023.
EG5.4.1 - Roadmap for Brisbane 2032

Deliver a roadmap for leveraging opportunities for the City of Logan associated with the 2032 Olympic Games.

Purpose: To secure better infrastructure, attract investment and create opportunities for our city
June 2023 On Track As at the end of the first quarter the Roadmap for Brisbane 2032 was drafted. The roadmap is being presented to the Executive Leadership Team (ELT) in October 2022 for consideration.
The roadmap will then progress to final consultation in quarter 2.
EG5.5.1 - Logan Plan 2025

Deliver activities for the Logan Plan 2025 program of work. This includes:
  • drafting of the new planning scheme
  • legal review
  • submission to the Queensland Government for State Interest Review.
Purpose: To support the delivery of Logan Plan 2025 as the key land use policy to guide future growth.
June 2023 On Track As at the end of the first quarter the principle policy positions were established and adopted at Special Council meeting on 6 September 2022 (minute no: 81/2022). Drafting of the Logan Plan 2025 is currently underway and is on schedule.
EG5.6.1 - Logan’s Assessment Portal

Launch Logan’s Assessment Portal powered by new software into Council’s existing development assessment processes.

Purpose: To support community participation in the way development and growth occur in the city.
This will be achieved by displaying application related material and decisions in a consistent format
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • Phase 1 now complete
  • Development Enquiry Tool now live.
EG5.7.1 - Operation improve residential building practices

Create a new Residential Building Task Force team within the Development Operations program.

Purpose: To improve building practices on residential construction sites.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • All positions have been advertised
  • Interviews have been conducted.
EG5.8.1 - Digital Infrastructure and Connectivity Program

Deliver the Digital Infrastructure and Connectivity Program.

Purpose: To:
  • create new opportunities in the digital economy
  • provide high speed, reliable internet options to all our community
  • support the City of Logan to be globally competitive.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • Entire DI&C Program 54% complete.
  • Mobile - Placed on hold pending announcements on mobile programs from Federal Govt following May 2022 elections
  • Broadband - Detailed technical survey in 3 search areas has resulted in prioritisation of Polygon 3 and 2(a). LCC resolution to proceed with State Govt considering proposal to programme Broadband scope for FY23. Reverted to NBN Co for update on Fixed Wireless program and Logan impacts.
  • MFEDC - Business Development continuing, including search options for suitable land parcels (including commercial property firms). MFEDC Business Case submitted to Council including BCR, Concept Design and qualitative benefits etc. Approved by Council.
  • LEO Pilot - Initial proposals for LEO service Value Added Resellers received for assessment. Renewed interests from one Satellite Service Provider. Initial proposal reviewed from service provider and was deemed to be at a significantly higher cost than anticipated for residential trial – discussion held with service provider to revise proposal. Another service provider sent proposal for residential trial which was deemed to be comparatively suitable - currently the proposal is under assessment.
  • Smart IOT Platform - Initial proposal received by service provider and reviewed – which was deemed to be not suitable for value of money. Currently continuing discussions on proposal. Confirmation letter received by Logan regarding cancellation of Federal Government 5G Innovation Initiative Funding – 15 July 2022. Continued engagement with potential providers to explore further opportunities.
  • Program Management - Continuous risk register updates
  • DI&C Program presentation to Council Directors/CEO (ELT).
  • DI&C Program Update Committee report finalised and submitted for Planning Committee 13/09.
  • Draft letter finalised and sent to State Government (DCHDE) regarding scope change.
  • Kick-off workshop with industry and Government stakeholders to explore potential opportunities.
EG5.9.1 - CoLab

Deliver the coLab Growth Hub.

Purpose: To support scaling ventures to achieve their high-growth objectives in the innovation-driven economy.
June 2023 On Track

As at the end of the first quarter, the following was achieved:

US Market Access Program

This program began with 9 scale up companies. Session 1 of the program was delivered on Friday the 9th of September with all participant companies delivering a customer focused pitch to the Entrepreneurs in Residence. Mentoring between the companies and Entrepreneurs in Residence was held before delivery of the next session. Session 2 was delivered on Friday the 23rd of September with 3 hours of training content provided by our facilitator. Participant companies will apply the training content to provide a work product for Session 3 proposed for delivery on Friday the 7th of October.

Residency

The current cohort of coLab Portfolio Companies continue to work with their dedicated Entrepreneur in Residence and have participated in mentoring sessions to assist the company's growth.

Branding and Marketing

A brand refresh has been completed including an improved brand, brand strategy, brand narrative and collateral/assets. Preparation for delivery of the new brand is currently being undertaken.

Infrastructure

Project Target Status Commentary
IN6.1.1 - SafeRoads4Logan Road Safety Strategy Action Plan 2022-2026 implementation

Implement current year actions for of the SafeRoads4Logan Road Safety Strategy Action Plan 2022-2026.

Purpose: To reduce incidents and improve safety on roads in the City of Logan and promote road safety.
June 2023 On Track During the first quarter Road Safety Strategy for Logan 2022-2026 was publicly released as a hardcopy document with an electronic copy also available on Council's SafeRoads4Logan web page. A number of items from the strategy's action plan (A1 to A31) were also progressed including:
  • Road Safety launch, expo and media releases during August Queensland Road Safety Week (Action A1).
  • Weekly meetings between Council, Police and Department of Transport and Main Roads (TMR) road safety officers (Action A5b).
  • Launch and first meeting of Road Safety and Active Transport Advisory Group on 28 July 2022 (Action A6).
  • 7 projects submitted to TMR for 2023/24 Federal Black Spot Program (Action A11).
  • Traffic calming issued for 3 existing streets in Marsden (speed platforms) and Kingston (one lane chicanes) (Action A23).
IN6.2.1 - Chambers Flat Wastewater Treatment Plant site master plan

Develop the draft and final site master plan for the Chambers Flat Wastewater Treatment Plan.

Purpose: To support the delivery of reliable and sustainable water services.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • Initial meetings have been held with the Chambers Flat community reference group. The group has put forward key goals that they each have for the site.
  • Logan Water has shared a preliminary site map that shows the proposed location of the treatment plant site and other area that at this stage will be reserved for Logan Water purposes. There remains a significant part of the site that can be used for community and environmental uses.
  • Further consultation is on hold until the alignment of the upgraded Kenny Road is finalised, this has been delayed at least three months as the roads team reassesses the proposed design considering the updated flood modelling.
IN6.2.2 - Loganholme Wastewater Treatment Plant (WWTP) Stage 8. Beenleigh WWTP close

Deliver critical upgrades to the Loganholme WWTP.
Decommission the Beenleigh WWTP.

Purpose: To respond to anticipated increases in growth and demand in water services
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • The project tracking to schedule. Major structures are complete and have passed hydrostatic testing.
  • In quarter 2 civil works around the major tanks can begin along with the duplication of the outfall pipeline to meet the increased flows of the new design.
IN6.2.3 - Water and wastewater capital works program

Deliver water and wastewater infrastructure through the Water and Wastewater Capital Works Program.

Purpose: To deliver safe and efficient water and wastewater infrastructure to support the community and city growth.
June 2023 On Track At the end of the first quarter Logan Water had completed $23.1m of capital works vs a first quarter budget of $30.7M. This is within acceptable limits of the anticipated $24m.

Current underspend in the Loganholme Stage 8 and Beenleigh to Loganholme pipeline expected to be recovered in coming months.
IN6.2.4 - Water for SEQ Plan

Contribute towards the development of the Water for SEQ Plan.

Purpose: To:
  • ensure the best possible outcomes for City of Logan communities
  • effectively inform the region’s future through input in the SEQ Regional Plan.
June 2023 On Track The Water for SEQ Plan is an initiative of the SEQ Water Service Providers (WSP) Partnership with a vision for integrated and collaborative water cycle management across South-East Queensland ensures water and sewerage services are reliable, affordable, and sustainable both now and in the future. The benefits and costs of an integrated and regional approach to water management are realised, pursued and shared equitably between stakeholders.

The SEQ WSPs are Seqwater, City of Gold Coast, Logan City Council, Redland City Council, Unitywater and Urban Utilities. Each of the agencies had a plan for their component of the region but there was no holistic plan or framework for bringing them together or for guiding and supporting other levels of government when putting together the SEQ Regional Plan.

This year the SEQ WSPs Partnership will engage consultants to facilitate the development and preparation of the regional planning high-level strategic Position Statement, and development and implementation of the related Communication and Stakeholder Plan. Logan Water's role in this process will predominately be in the last quarter of the financial year.
IN6.3.1 - Parks Asset Renewal Program

Deliver the Parks Asset Renewal Program.

Purpose: Provide and maintain healthy and active recreation opportunities for families
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • Total of 16 projects completed including shelter replacements, playground renewals, lighting improvements and other park embellishments.
  • The program is on schedule with 21% of the program delivered so far
  • This is within acceptable parameters.
Highlights include:
  • Plateau Park Shelter Replacement
  • Forestglen Park project
  • Crossing Park Playground Renewal
  • Doug Larsen Park lighting project
  • Activity Park Playground Renewal
  • Third Park House Demolition Project
  • Chris Green Park Toilet Demolition Project
  • Mikaga Park Embellishments
  • Bedford Park - Remove playground & shade sail
  • Jamie Nicholson Park toilet block
  • Passerine Park bin replacement
  • Red Ash Reserve concrete creek crossing removal
  • Hammel Park signage
  • Bill Carmody Park Playground Renewal
  • Porter Park Shade Sail replacement
  • Barbaralla Park upgrade
IN6.3.2 - Waterford West Park

Deliver the detailed design for the Waterford West Park.

Purpose: To enhance Council’s recreational infrastructure across the city’s green spaces.
June 2023 On Track As at the end of the first quarter the project is on schedule with new site plan developed. This is to mitigate the impacts of flooding, based on flood modelling data. Project documentation is expected in January 2023.
IN6.4.1 - Asset Management deep dive

Deliver an enhanced level of maturity of strategic and operational asset management for Council facilities and properties.
Purpose: To support delivery of the related project: Enterprise Asset Management Systems and long-term sustainability of Council’s infrastructure.
March 2023 Completed As at the end of the first quarter, this project has been completed.

The scope of the project was to do a review of the Corporate Facilities Program asset maturity. This included recommendations on actions to be taken to bring the Program up to an improved standard of asset management. Once the recommendations and actions have been implemented, the Corporate Facilities Program will be well positioned from a project readiness perspective to engage in a meaningful way with the EAMS Project.
IN6.4.2 - Asset Management Improvement Plan

Implement the Asset Management Strategy 2020-2023. This will be achieved by delivering identified actions from the associated Asset Management Improvement Plan (AMIP). This includes reviewing:
  • condition assessment and defect identification regime for each asset class
  • risk analysis and monitoring regime for infrastructure assets
  • operations, maintenance, and renewal plans
  • asset management resources across the organisation
  • implementing AMIP Key Performance Indicators.

Purpose: To improve organisational financial reporting and analytics capabilities.
June 2023 On Track During the first quarter work continued to mentor Branches to develop asset lifecycle models. Corporate Asset Management (CAM) also developed a timeline for Asset Management Planners across the organisation for finalised asset lifecycle models to be included in each Asset Management Plan for the introduction of the State's new Sustainability Framework in 2023/2024.

Note: With the restructure of the Business Transformation to the Portfolio Management Office (PMO), a targeted focus has been developed for CAM. This also supports the current resources able to deliver program of work. The program includes Organisational Asset Renewals Models to inform the State's new Sustainability Framework and Asset Infrastructure Information Management Plan. CAM will continue to be Subject Matter Experts for the Enterprise Asset Management Solution (EAMS) Project. All KPI's will be managed via the PMO.
IN6.4.3 - Organisational asset renewals modelling

Update the organisation's asset renewal governance and practices.

Purpose: To provide improved information for future decisions around new and existing service levels.
June 2023 On Track During the first quarter, the work continued in the Asset Management Improvement Plan project to mentor Branches to develop asset lifecycle models to feed into the next budgeting process.

Supporting the State's introduction of a new Sustainability Framework and associated reporting requirements for Local Governments, there will be 2 new asset-related financial indicators that Council will be audited on, as part of the audited financial process. This will commence at the end of the 2023/2024 financial year. As a proactive measure, Council will be internally self-assessing these measures at the end of the 2022/2023 financial year.
IN6.5.1 - Parks Capital Works Program

Deliver park infrastructure through the Parks Capital Works Program.

Purpose: To Increase tourism in the city. To create healthy and active recreation opportunities for families.
June 2023 On Track As at the end of the first quarter, projects in the Parks Capital Works Program are progressing on schedule with:
  • Anticipated program milestone for the end of quarter 1 was 5% budget spend, but is ahead of schedule at 12%
  • Consultation activities complete
  • Projects are in the design and documentation phase
  • Where possible equipment is being procured early to mitigate supply chain delays.
This is in line with the expected progress of the project for the end of the first quarter.

It should be noted that forecasted inclement weather in quarter 2 and quarter 3 may impact delivery of these projects. We are monitoring this and working on wet weather mitigation plans.
IN6.5.2 - Flagstone Community Hub

Deliver detailed design work for the Flagstone Community Hub.

Purpose: To support development of the new Greater Flagstone community centre.
June 2023 On Track During the first quarter of 2022/23, the land title for the Flagstone district community centre was transferred to Council. Council commenced a review of community needs and facility scope which will include community engagement to identify and confirm local needs.
IN6.5.3 - Yarrabilba Community Hub

Deliver the Yarrabilba Community Hub.

Purpose: To provide a new integrated community facility that delivers critical social services for the community.
November 2022 On Track As at the end of the first quarter, construction works are in progress. Works remain on track for completion in October 2022. Final inspection scheduled for mid-October 2022.

The project expects handover mid-October 2022.
IN6.6.1 - Road and Drainage Capital Works Program

Deliver the road and drainage infrastructure 2022/2023 projects through the Road and Drainage Capital Works Program.

Purpose: To deliver sustainable transport infrastructure that provides city and regional connection.
To deliver drainage infrastructure that collects and discharges stormwater safely and effectively
June 2023 On Track At the end of the first quarter, delivery of the Capital Roadworks and Drainage Program has achieved $31.6 Million in overall expenditure which was slightly ahead of planned expenditure targets by 17%.

Notable projects under construction throughout the first quarter includes:
  • Stages 2 and 9 of Woodlands Drive Catchment Master Drainage Project, Rochedale South ($15.8 million)
  • Stage 1 of Jimboomba Local Road Kerbing and Stormwater Drainage Upgrade ($8.6 million)
  • Gilmore Road, Berrinba - Road Upgrade ($8.1 million)
  • Chambers Flat Road Upgrade, Chambers Flat ($38 million)
  • Browns Plains Road & Scrubby Creek Road Intersection Signalisation, Browns Plains ($2.8 million)
  • Woodbeck Street Catchment Master Drainage Project, Beenleigh ($1.7 million)
  • Middle & Teviot Road Roundabout Upgrade ($1.1 million)
  • Asphalt resurfacing, spray sealing works and pavement rehabilitation at numerous locations across the city (totalling $16.5 million)
The Capital Roadworks and Drainage Program delivers enhanced transport and drainage infrastructure across the City of Logan. The Program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure network.
IN6.7.1 - Monitoring room expansion investigation

Deliver an investigation into the expansion of the Logan Safety Camera Program Monitoring Room.

Purpose: To support the expansion of the Logan Safety Camera Program network.
June 2023 On Track During the first quarter of 2022/2023, the Monitoring room expansion investigation project progressed well and is on track. The following key highlights were achieved:
  • A Request For Quote to procure a consultancy firm to determine the current and future needs of Council's camera monitoring room including the identification of potential growth opportunities and requirements has been prepared. Quotations are expected to be invited from suppliers in October 2022.
IN6.7.2 - Strategic Land Acquisition Program

Establish a 3-year Strategic Land Acquisition Program to coordinate the acquisition of commercial land and sale of surplus land.

Purpose: To support the efficient delivery of trunk infrastructure and generate investment and employment opportunities in our city.
June 2023 On Track As at the end of the first quarter, the City-wide and Underwood precinct continued development as planned.
An update report to Council was also in development, and is anticipated to be presented to Council in November 2022. The report will include an update regarding the Innovation Precinct and seek further direction from Council.

High performing organisation

Project Target Status Commentary
HP7.2.1 - Community engagement framework

Deliver initiatives within Council's Disaster Management's Community Engagement Framework.

Purpose: To promote and enhance community education, resilience and recovery.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • The bushfire preparedness campaign has been completed. This campaign has been running since mid-July and concluded on 30 Sep 22. Task complete.
  • Concurrent to the bushfire preparedness media campaign the DMP commenced the storm preparedness campaign. This campaign will be occurring over a number of mediums, including shopping centre digital screens, print media and radio advertising. The majority of this advertising will conclude on 10 Oct 22, with advertising only continuing in the "Our Logan Magazine' and on LCC screens until the end of October. Task is 85% complete.
  • As we move into the high risk weather season, the DMP is switching it's advertising focus from bushfires and storms, to general community education and preparedness. The DMPs advertising focus will be on preparedness and the Logan Early Warning APP through the second half of October and the first half of November 22. Advertising scripts and images have been approved and will commence in mid-October. Task 50% complete.
  • The DMP has also commenced preparation for 'Get Ready QLD Week' (10-14 Oct 22). Task 50% complete.
HP7.3.1 - Digital Transformation Program

Deliver year 1 of the Digital Transformation Program. This includes upgrades to modernise the processes and technology to digitise Council systems.

Purpose: To ensure Council's IT systems are able to support the evolving needs of the organisation and community.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • ELT have approved the Business Cases for the EAMS, Information Management Modernisation and Pathway Modernisation and projects. The former two, have also been approved by Council, with the Pathway Modernisation project Business Case scheduled for consideration by Committee and Council in October.
  • The Cyber Uplift Phase 2 project has rollout out mandatory training and achieved over 82% compliance in the first month. The Tech One Modernisation project has successfully transitioned the Finance module to CiA.
The Digital Transformation Program is being delivered jointly between Information Technology Services Branch, and the Portfolio Management Office. With the implementation of Council's EPMO, the Digital Transformation Program will be a key item that the EPMO will be managing and as such, reporting channels would best be suited to be allocated to the Portfolio Management Office.

Recommendation
It is recommended that the responsible Branch for this project be amended to the Portfolio Management Office.
HP7.3.2 - Implementation of QR Codes

Deliver a new data delivery system in fleet assets.

Purpose: To provide current driver information on the operation of fleet assets
June 2023 On Track At the end of the first quarter, The following was achieved:
  • Information Technology Services Branch (IT) have been engaged to review potential QR code providers to ensure they meet Councils IT security requirements.
  • The IT Integration and Delivery Team Leader has advised the QR code provider evaluation is now at the top of IT list to review.
  • A decision by IT on a QR code provider is due by the end of October 2022.This will provide guidance on our preferred supplier moving forward.
  • All data that will be applied to the QR codes have been reviewed.
HP7.3.3 - Business Transformation program design and delivery

Deliver planned actions from the:
  • Corporate Innovation Strategy
  • Business Process Excellence (BPX) road map.

Purpose:
To support transformational change through:
  • alignment
  • implementation
  • management
  • measurement.
This will be achieved through identified innovation and improvement initiatives.
June 2023 On Track In the first quarter, the following milestones were achieved:
  • Delivery of 3 Lunch and Learns. The July session was an innovation showcase on the Logan Biosolid Gasification project, while August and September were focused on Process Thinking and the 4 stages of Problem solving. Staff attendance for Quarter 1 was 109 staff and the customer retention rate is tracking at 85% at the end of Quarter 1.
  • Community of Practice concept design drafted for Manager review. This initiative is placed on hold, pending the establishment of the new Portfolio Management Office.
  • The Community of Practice glossary was completed, with terms and definitions finalised and aligned to definitions recorded in the ISO Standards
  • Two editions of the Innovation Unearthed were distributed in Quarter 1 and subscription numbers totalled 358 with an average open rate of 27.6% (Industry benchmark 19.4%) and an average click through rate of 13.5% (Industry benchmark: 2.8%). The story introducing the Portfolio Management Office was the most read article and the accompanying video explainer was viewed 175 times.
  • The Innovation and Improvement Customer Service has primarily been focused on support the two new initiatives for the PMO including service reviews and value for money.

With the Branch restructure and the establishment of the Portfolio Management Office, the Business Transformation program design and delivery project will be absorbed within the scope of the related project HP7.5.1 - Enterprise portfolio and transformation delivery. Work will still be progressed under a revised scope within the Enterprise portfolio and transformation delivery project and will be reported as such.

Recommendation

It is recommended that this project be removed from the Operational Plan 2022/2023 and realigned under the project HP7.5.1 Enterprise portfolio and transformation delivery.

HP7.4.1 - Contract management software

Deliver enhanced contract management functionality through the implementation of TechOne Contracts module.

Purpose: To ensure Council’s contract management systems are up to date and meet the needs of the organisation
December 2022 On Track As at the end of the first quarter, the following was achieved:
  • To ensure alignment with EAMS and to avoid loss of business functionality, a direction by Management to implement all contacts as standard contracts have been agreed which is a base foundation with all contracts captured as a standard contract with associated purchase order/s enabling a link to some financial transactions (purchase orders and invoices).
  • Information Technology Project team have scheduled showcases with Procurement to progress the project deliverables. The project milestone is 'on track' for go the Contracts Module to transition to CiA by December 2022.


About the project

The Technology One (T1) Modernisation has within its scope to implement the Contract Management module in T1 and replace the end-of-life Open Window system. The project is working to a December implementation. The EAMS project will need to enhance the Contracts solution to achieves its benefits for Council's assets.

HP7.4.2 - Infrastructure Asset Information Management Plan

Implement an asset information management plan and governance framework for asset managers.

Purpose: To support asset management planning and enable informed decision-making for Council's long-term sustainability and service delivery.
June 2023 On Track During the first quarter, the following was achieved:
  • The final draft plan was out for review and the project received stakeholder comments and feedback.
  • The feedback was reviewed and collated to inform required changes.
  • Preparations continued for the presentation of the draft at the AM SDCT for early October 2022.
HP7.4.3 - Enterprise Asset Management System

Start delivering foundational components of the Enterprise Asset Management solution (EAMs). This will be delivered in line with the implementation plan defined in the detailed EAMS business case.
The project is set to be delivered over a 2-year period from July 2022 through to July 2024. It covers all identified foundational asset classes and includes go-live and hyper care.

Purpose: To ensure the right business solutions are delivered that:
  • are supported by integrated technologies and best practices
  • enable efficient and effective management of assets with ability to retain quality asset information
  • support operational and future strategic infrastructure decision making
June 2023 On Track

As at the end of the first quarter, the program remains on track as per the approved EAMS Detailed Business Case (Council minute number 69/2022). The program is now three-quarters through base build configuration of the solution. Program Business Analysts are allocated and embedded into business branches across Council. The Analysts are working with business subject matter experts to document as-is processes, undertake data quality assessments and map existing data to future-state EAMS requirements. All key governance controls are now in place for program management, quality control and business change management. The EAMS project is a project that is being delivered under the related project HP7.3.1 - Digital Transformation Program.

Recommendation

It is recommended that this project be removed from the Operational Plan 2022/2023 to ensure that the project is reported through the Digital Transformation Program.

HP7.5.1 - Enterprise portfolio and transformation delivery

Establish an enterprise portfolio, program and project management capability.

Purpose: To support transformation project planning, management, and delivery in the organisation
June 2023 On Track As at the end of the first quarter, the following was achieved:

Consultation
  • Individual Councillor briefings have occurred with Chairs.
  • Briefings have been booked with the remaining Councillors.
  • All DMT briefings have occurred.
  • Invitations to attend BMT's have been offered to Managers.

Communication and Engagement
  • Status update emails sent to the Branch
  • Ways of working together workshop in the planning phase.
  • PMO SharePoint site on The Buzz is under construction.

Systems and Processes
  • Draft charter in progress for presentation to ELT on 13/10/2022.
  • Foundational governance documents are being prepared.
  • Template and process documentation and development is in progress.
  • Reporting framework development is in progress.
  • Flight plan is consistently being refined with roles and responsibilities assigned.
HP7.5.2 - Risk management framework improvements

Deliver identified improvements to the risk management framework.

Purpose: To support improved risk management practices in the organisation
June 2023 On Track As at the end of the first quarter
improvements to Council's risk management framework have been proposed and are currently being reviewed. These includes uplift and improved alignment to standards ISO 31000:2008 Risk Management and ISO 37301:2021 Compliance.

The project also worked on develop council's operational risk register and improved education across the organisation by delivering risk training sessions. 21 sessions were delivered to the organisation in this calendar year to date, with more projected to be delivered during the year.
HP7.6.1 - Safety Innovation

Develop an innovative new safety tool for our staff. The project will be delivered in partnership with Apple and Telstra.

Purpose: To be an industry leader in safe work practices for our people.
June 2023 On Track As at the end of the first quarter, the following was achieved:
  • App development now complete.
  • The project team are now working with Information Technology Services Branch on transition and setting up Telstra Purple managed services.
HP7.6.2 - People Plan 2022-2026

Deliver the People Plan 2022-2026 projects scheduled for the current financial year.

Purpose: To enhance our people's capability to achieve our Corporate Plan 2021-2026.
June 2023 On Track The People Plan 2022-2026 has been finalised and published. In addition, work has commenced and continues on the focus areas of:
  • culture
  • performance management framework
  • employee value proposition.
HP7.7.1 - Advocacy Action Plan

Deliver on priorities identified in the Advocacy Strategy 2021-24, as well as other emerging advocacy priorities.

Purpose: To influence federal and state government decisions that support Logan's identified advocacy priorities.
June 2023 On Track As at the end of the first quarter, the Advocacy Program held on-on-one meetings with Councillors seeking feedback on the performance of the program and insights regarding their advocacy priorities. Iterative drafts of the framework for "Transform Logan 2045" have been produced for the CEO in preparation for strategic planning discussions at the end of October. The Advocacy Program also coordinated a submission to the Queensland Parliamentary inquiry into the decriminalisation of certain (minor) offences.