Operational plan report - Quarter 1, 2023 / 2024

Total projects for 2022 / 2023 Quarter 1: 34

Corporate Plan focus areas Total
Maintaining current levels of service (MS) 0
Proud city (PC) 3
Environment (EN) 8
Healthy connected community (HC) 4
Economy and growth (EG) 3
Infrastructure (IN) 5
High performing organisation (HP) 11
Total 34

Project status Total
On Track 30
Completed 1
Monitor 3
Not Completed 0
Not Proceeding 0
Total 34

You can view each priority focus area for Quarter 1, 2023 / 2024 below which includes a status update on Operational Plan key project delivery.

Proud City - Quarter 1, 2023 / 2024

Project Target Status Commentary
PC2.2.1 - City of Logan Safe City Strategy and Action Plan 2021-2025 June 2024 On Track During the first quarter of 2023 / 24, key actions of the City of Logan: Safe City Strategy and Action Plan 2021-2025 were delivered, including:
  • the annual City of Logan Safe City Awards
  • the launch of the 'You hold the key to prevent car theft' campaign
  • the completion of nine (9) Crime Prevention Through environmental Design (CPTED) audits throughout the city
  • the completion of six (6) community safety assessment for liquor licence applications
  • attendance at five (5) community engagement events specific to resident concerns relating to personal safety, perceptions of crime, frauds and scams and home and vehicle security.
PC2.3.1 - Disability Action Plan June 2024 On Track September 2023 key highlights include:
  • 1 action completed
  • 8 actions progressed
  • 10 internal working group members attended the quarterly meeting where they provided updates on their actions and information on additional actions they are completing.
During the first quarter of 2023/24, the following key highlights were achieved:
  • 17 actions completed
  • 32 actions in progress
  • 8 internal working group members attended disability and inclusion training
  • 10 internal working group members attended the quarterly meeting where they provided updates on their actions and information on additional actions they are completing.
PC2.3.2 - Reconciliation Action Plan June 2024 Monitor September 2023 key highlights include:
  • the development of Council's third RAP has been delayed due to continued discussions regarding priorities, resourcing and recruitment. A meeting with ELT will occur in October.
  • the Reconciliation Ambassador webpage has been updated to include new ambassadors and has become the main platform for sharing updates and information between Ambassadors.
During the first quarter of 2023/24, the following key highlights were achieved:
  • attended ELT on 20 July to discuss priorities, resourcing and recruitment
  • 60 new Reconciliation Ambassadors were inducted on 27 July
  • the Reconciliation Ambassador webpage has been updated to include new ambassadors and has become the main platform for sharing updates and information between Ambassadors
  • held 1 sharing circle at Berrinba Wetlands with 31 Ambassadors in attendance

Environment - Quarter 1, 2023 / 2024

Project Target Status Commentary
EN3.1.1 - Logan and Albert River Litter Clean Ups June 2024 On Track During the first quarter of 2023/24, the Logan River clean-up program continued with monthly clean-ups of the river from Geoff Philp Bridge to the mouth of the Logan River.

A Request for Quote has been prepared for the large debris clean-up project.
EN3.2.1 - Riverbank Restoration Projects June 2024 On Track During the first quarter of 2023/24, site visits were undertaken to inform the scope of the Logan and Albert Riparian Restoration project.

Over the quarter, 800 trees were planted at Logan River Parklands and 80 trees at Wolffdene South Reserve to enhance previous riparian rehabilitation works.
EN3.3.1 - Tree Planting Offset Projects June 2024 On Track During the first quarter of 2023/24, weed and planting maintenance works continued at existing offset sites.

The contract for stage 1 planting of Ooah Park has been awarded and site preparation works have begun.
EN3.4.1 - Environmental conservation partnerships June 2024 On Track During the first quarter of 2023/24, Environmental Conservation Partnerships achieved the following:
  • 989 members in total participating in the program
  • 34 new Habitat Connections members joined the program - 510 properties in total (3 properties deregistered from the program)
  • 11 new Land for Wildlife properties were registered - 479 properties in total (2 properties deregistered from the program)
  • Formal agreements remain at 30 (Voluntary Restoration Agreement, Voluntary Conservation Agreement and Voluntary Conservation Covenant)
  • 39 Land for Wildlife property revisits were conducted
  • 160 individual community engagement interactions were provided to community members
  • 7.84 hectares were added to the Land for Wildlife habitat network bringing the total to 6,333.35 hectares
  • Environmental Conservation Partnerships Celebration Day was delivered with approximately 300 members attending, 15 stallholders and 2 presenters
  • 6 threatened species were recorded on Land for Wildlife properties and include the native guava, koala, Glossy black-cockatoo, macadamia, swamp tea tree and Plunkett mallee (18 threatened species have been recorded in total)
  • Oxley Creek Landholder Engagement project has progressed with on ground property restoration activities conducted on 8 properties
  • 64 Environmental Conservation Partnership members submitted orders for conservation incentives (yearly total is 152 orders)
  • 1,179 plants were ordered (yearly total to date is 3,544 plants)
  • 3 nest boxes were ordered (yearly total to date is 16)
  • 8 resource books were ordered (yearly total to date is 18)
  • 45 herbicide orders were made (yearly total to date is 53).
EN3.5.1 - Riverine Discovery Centre June 2024 On Track During the first quarter of 2023/24, Council endorsed an additional $1.5 million funding boost towards delivery of Stage 1 of the Riverine Discovery Centre.

A Request for Quote for the construction of Stage 1 of the Riverine Discovery Centre was released. Stage 1 construction is expected to commence in November 2023.

A Request for Quote to engage a consultant to inform interpretive content and include First Nations elements within the centre was progressed.

Skilling Queenslanders for Work trainees undertook tree planting, weed management and rubbish removal along the riparian area of the site as part the restoration works through our partnership with Reclink.
EN3.6.1 - Energy efficient lighting upgrades June 2024 On Track During the first quarter of 2023/24, site visits were undertaken to four Council buildings to finalise the scope for the LED lighting replacement project.
EN3.6.2 - Sustainable Solutions June 2024 On Track Loganholme Wastewater Treatment Plant is now in the design phase.

The next Chambers Reference Group meeting is scheduled for 30 October 2023.

All Sustainability Projects are on track and time.
EN3.7.1 - Solar Panel Recycling Service June 2024 On Track Evaluation of solar panel recycling providers continues with two existing Council e-waste recyclers being assessed for future capability.

Engagement with a third potential supplier identified by the Investment Attraction Incentive Fund is underway to assess technologies and capability for potential partnerships.

Healthy connected community - Quarter 1, 2023 / 2024

Project Target Status Commentary
HC4.1.1 - Community Infrastructure Network Plan March 2024 On Track Detailed network planning for indicative future locations and timing for Integrated Lifestyle Infrastructure Network Plan is progressing, in consultation with internal stakeholders.

Final draft recommendations for the updated Community Infrastructure Plan are being finalised.

The Sports Infrastructure Plan draft report and recommendations are being reviewed.

The Parks Plan is in development.

Milestones achieved:
  • internal stakeholder consultation on the draft community infrastructure network plan was completed
  • draft Sports and Recreation Plan was developed
  • approach, feedback and timeframes were confirmed with council's Chief Executive Officer
  • mapping for the network was developed.
Proposed actions:
  • draft plans are to be delivered in quarter 3, 2023 / 24
  • Councillor breifing session to be held in October 2023.
HC4.1.2 - Sport and Community Infrastructure Capital Works Program June 2024 On Track Projects remain on track for delivery of the capital works program, with approximately $9.4 million (28%) worth of projects currently in construction.

There are approximately $12.8 million (38%) of projects currently in procurement phase / pre-construction.

Design and scoping is progressing for the remaining 34% of the Capital Works Program.

Approximately $2.9 million (8.5%) of the Capital Works Program has been delivered.

Milestones achieved:
  • construction commenced for Jimboomba Park Rugby League Clubhouse
  • contract was awarded for Chris Green Clubhouse
  • a letter of intent was issued to the preferred supplier for the Everleigh Park Clubhouse with award of contract to follow.
HC4.2.1 - Libraries Learning and Discovery Strategy June 2024 On Track The following was achieved during the first quarter of2023/24:
  • delivery of activities in Libraries including Baby Time, Page Turners, Tech Help and English Conversation sessions
  • delivery of 2,918 take-home packs for families
  • delivery of school holiday activities for children, with 964 attendees
  • delivery of face to face library programming and events for children and adults, with 16,803 attendees
  • delivery of home library service to 473 individual library members and 23 aged care facilities
  • Library staff developed, implemented and evaluated purposeful and engaging library programming and community engagement in support of the Libraries Learning and Discovery Strategy. 368 outreach events were delivered across the City with 6747 people participating in these outreach events.
HC4.4.1 - Arts Culture and Heritage Strategy 2023-2027 June 2024 On Track During the first quarter of2023/24, the Arts, Culture and Heritage Plan 2023-2027 was endorsed by Logan City Council on 17 August 2023.

Arts, Culture and Heritage highlights for quarter one include:
  • Logan NAIDOC Family Fun Day with 2,500 attending the event
  • Logan Entertainment Centre's 21st celebration program with 940 attending the program of events
  • the opening of the Big Voices: Children's Art Matters exhibition at the Living Museum of Logan in July with 35 people attending the event
  • the launch of the Education Arts program in August with 45 teachers attending the event
  • the display of the Artwaves 2023 exhibition at Logan Art Gallery in September with 502 people attending the event.

Economy and growth - Quarter 1, 2023 / 2024

Project Target Status Commentary
EG5.4.1 - Olympics Legacy Venue Business Case June 2024 Completed Responsibility for the delivery of the business case for the Olympics Legacy Venue has transitioned to the Queensland Government.

This project is now complete.
EG5.5.1 - Logan Plan 2025 State Interest Review June 2024 On Track This project contributes to the progression of Logan Plan 2025.

The draft scheme was delivered to the Queensland Government for State Interest Review in September 2023.

Council will work with the State to achieve endorsement for public consultation in 2024/2025.
EG5.8.1 - Digital Infrastructure and Connectivity Program June 2024 On Track Opticomm are laying the fibre to the premise on eligible properties. Completion is anticipated by November 2023.All other aspects of this program/project have been completed. A final report will be submitted to the State Development Department by March 2024, as per funding guidelines once all construction is complete in November 2023.

Mobile:
  • no planned activity
Broadband:
  • ongoing monitoring of NBN on Fixed Wireless upgrades to Logan sites
  • ongoing fortnightly meetings with Opticomm are being held to discuss progress & ensure alignment on work and timeframes
Project progress for quarter one 2023/24:
  • Milestone 3 – July 2023 Headend Completion – There has been a delay with this milestone due to unforeseen developer activities on the site of the Headend installation. Opticomm are in direct communication with the developer with planned progress and timeframe for the Headend completion to work in with the developer's timeframes. Planned completion date is November 2023.It has been confirmed that this will not delay the entire project deadline as all other work is being completed parallel to this work. With the headend upgrade there will be a network outage of around 2,500 properties. Opticomm will handle the communications with affected residents during affected periods. This upgrade needs to occur during work hours due to the very high risk nature of the work needing to be done in daylight hours. The project in on track for civil completion by end of October 2023. Fibre deployment will occur all in one go for efficiency.
  • Milestone 1 - January 2023 Mobilisation has been completed
  • Milestone 2 - April 2023 Headend Survey and Design has been completed
  • Milestone 4 - Network Detailed Designs - Completed ahead of schedule (originally September 2023, completed in August 2023)
  • Milestone 5 - Completion of Fibre Network - due for completion in November 2023
  • residents are continuing to register for installation of fibre to the premise – a second works notice was sent from Logan City Council (LCC) in late September 2023. Opticomm will commence door knocking to speak directly with eligible residents in October 2023
  • quarterly State Reporting has been finalised and submitted as per updated scope on 13 October 2023
  • the next/ last funding release is expected when the project has been finalised, as per contract arrangements, by December 2023/ January 2024
  • an Extension of Time (EOT) approval was received by State Development Department on 10 August 2023 (the project was extended to 15 December 2023)
  • the final State Development Department payment is due by 15 March 2024
  • a site signage exemption approval was received by State Development Department on 8 August 2023.
Multi Function Edge Data Centre (MFEDC):
  • continuing engagement with potential providers
  • progressing with formal arrangements & strategic relationship with KalindaIT
  • progressing the MFEDC report to apply for further funding from State is on hold.
Low Earth Orbiting (LEO) Trial:
  • no planned activity.
Smart Internet of Internet (IoT) Platform:
  • no planned activity.

Infrastructure - Quarter 1, 2023 / 2024

Project Target Status Commentary
IN6.2.1 - Loganholme Wastewater Treatment Plant (WWTP) Stage 8. Beenleigh WWTP Close June 2024 On Track During September 2023, the following activities were completed on the Loganholme Wastewater Treatment Plant Stage 8 project:
  • chemical dosing skids piping installation
  • Return Activated Sludge (RAS) and Waste Activated Sludge (WAS) pump skid and piping installation.
The following activities are in progress on the project:
  • truck refill/septage receival areas
  • road works construction
  • bioreactor west side diffuser disk installation
  • blower piping installation
  • wastewater holding tank construction
  • building doors/ fans/ louvers
  • cable, earthing grid, light poles and lightning protection poles installation.
The project is on track for completion and commissioning as scheduled in the second quarter of this financial year.
IN6.2.2 - Water and Wastewater Capital Works Program June 2024 On Track As at end of the first quarter of 2023/24, the expenditure on the capital works program was $35.45 million against a phased budget of $26.82 million.

A number of projects and renewal programs are ahead of schedule.
IN6.3.1 - 2023/2024 Parks Capital Works Program delivery June 2024 On Track At the end of first quarter of 2023/24, delivery of the Parks Capital Works program achieved $5.5 million expenditure ahead of the planned $3.6 million planned expenditure.

Project completions for the quarter include:
  • Park Ridge District Park Basketball Court
  • Nexus Forest Park fencing
  • Parkdale Park Park upgrade
  • Isle Of Ely Park redevelopment
  • Tygum Park bridge lighting
  • Ison Pump Track
  • Spring Mountain Reserve car park
  • Holmstead Drive Fairy Lights
Key risks to program remain contractor and material availability, and construction price inflation. These risks are being managed through early procurement of equipment (where possible), proactive management of the Parks Pre-Qualified Suppliers, and value/ scope management.
IN6.6.1 - Road and Drainage Capital Works Program June 2024 On Track At the end of the first quarter of 2023/24, delivery of the Capital Roadworks and Drainage Program achieved $40.3 million in overall expenditure. This was ahead of anticipated, planned expenditure targets by 29%.

Notable projects under construction throughout the first quarter include:
  • Loganlea Road Upgrade, Loganlea
  • Chambers Flat Road Upgrade, Chambers Flat
  • Jimboomba Stage 2 Local Road Kerb & Stormwater Upgrades
  • Gunungai Drive Cycleway, Slacks Creek
  • Stage 1 and 2 of the Cowper Avenue Catchment Master Drainage Project, Eagleby
  • Stages 1 to 5 of the Kelly Street Catchment Master Drainage Project, Eagleby
  • Mundoolun Road Rehabilitation and Road Upgrade, Mundoolun
  • Tully Timber Bridge Replacement, Lyons
  • Station Road Cycleway, Loganlea
  • Asphalt resurfacing, spray sealing works and pavement rehabilitation at numerous locations across the city (totalling $11.9 million).
The Capital Roadworks and Drainage Program delivers enhanced transport and drainage infrastructure across the City of Logan. The Program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure network.
IN6.7.1 - Monitoring room expansion investigation June 2024 On Track During September 2023, engagement was undertaken with the Corporate Property Branch to explore the potential minor redesign of the original Monitoring Room space to allow for future growth and expansion.

High performing organisation - Quarter 1, 2023 / 2024

Project Target Status Commentary
HP7.2.1 - City Parking Enforcement Strategy 2023 - 2026 June 2024 On Track At the end of the first quarter:
  • Extensive community engagement activities to best understand the expectation of the community in managing city-wide parking was completed.
  • The draft of the City-wide Parking Enforcement Plan (2023-2026) (Plan) was finalised and presented to council's Executive Leadership Team (ELT) on 7 September 2023.
  • The Plan was supported for progression to a future Councillor Briefing Session to be held on 12 October 2023.
  • Dedicated resources continued to patrol parking behaviour in and around schools.
  • Development of specialised school parking maps continued.
HP7.2.2 - Community champions project June 2024 Monitor At the end of the first quarter of 2023/24, the following was achieved:
  • Community Champions EOI received: 2
  • Community Champion Interviews conducted: 2
  • Number of applications at pre- acceptance stage: (Blue card, Police check) : 25 – 11 x have received a police check link and have not yet accessed it, 2 x have processed their police checks and are waiting on results, 12 x requests to send a link issued but not yet received an update from P&C
  • Active Community Champions: 10
  • Applicants not progressing after interview: There is potential for some community champions to be removed from the program due to not following process and self-activating in the recent Flagstone Fires. Membership to the program is under review.
No further applications will be accepted until we have successfully implemented this program and onboarded the initial group of volunteers. Further recruitments are on hold until further notice (no earlier than Q2 2024).

7 Training sessions for the current applicants were originally organised, however, due to a date clash with the referendum and other events, Evacuation Centre Training has been postponed and will be rescheduled in 2024.
Overview of training:
  • QDMA (Pre-req), QFES, 05/08/2023
  • QDMA (Pre-req), QFES, 08/08/2023
  • Disaster Recovery Expert Workshop, Red Cross, 17/08/2023
  • Psychological First Aid, Red Cross, 30/09/2023
  • QDMA (Pre-req), QFES, 19/10/2023
  • Volunteer Management, Volunteering Queensland, 25/11/2023.
HP7.2.3 - Disaster Management Community engagement framework June 2024 On Track At the end of the first quarter 2023/24, the following was achieved:
Community Presentations:
  • Disaster Preparedness Presentation 2/9/23 Islamic Women's Association of Australia.
Community Events:
  • Attendance at the Disaster Day hosted by local Politicians (J Chambers MP, C. Dick MP) @ Gould Adams Park, Kingston. Approximately 400 people attended this event.
Aged Care and Seniors Presentations and Workshops:
  • Disaster Preparedness Presentation 7/9/23 Ruby by Living Gems
  • Disaster Preparedness Presentation 13/9/23 Palm Lake Resort Waterford
  • Disaster Preparedness Presentation 13/9/23 River Glen Lifestyle Village
  • Disaster Preparedness Presentation 27/9/23 Seasons for Living.
Planning Activities:
  • planning activities for Big Safe Day Outs (x2)
  • ongoing Flagstone site visit revealed a new risk (being managed)
  • Hyperdome administration have withdrawn approval to use their site. Underwood Park has been flagged as the new location
  • flood marker project is ongoing with conceptual designs being drawn up
  • review of Evacuation centres & places of refuse has commenced with dates for site visits being locked in
  • meeting of LCC staff to address the homelessness strategy moving forward
  • Person Centred Emergency Preparedness Workshops (x6) ongoing
    • dates and venues secured
    • marketing and communication plan nearly completion
  • Business Continuity Planning Workshops for Disability Sector ongoing
  • Engaging with stakeholders
  • Dates and venues secured Marketing Material being developed.
Networking Activities:
  • Men Shed engagement to make Disaster Preparedness theme game – ongoing
  • meeting with 'Brookhaven Developers' to discuss possibility of delivering a presentation to newly settled homeowners in the Bahrs Scrub area
  • Community Recovery and Resilience Officer network meeting
  • attended the Residential Aged Care Forum organised Gold Coast City Council
  • attended Indigenous Community Police Consultative Group.
Get Ready / Marketing campaigns:
  • Bushfire campaign live
  • Multilingual videos were received late sept – to be used in marketing in future
  • Logan Early Warning campaign in planning for live date in Nov
  • Radio campaign.
Logan Early Warning:
  • Total registrations as of 30 September 2023: 24652
  • New Registrations 1647
  • Unsubscribe 2.
Mobile Phone App Users:
  • New Registrations 109
  • Unsubscribe 1.
HP7.2.4 - South-West Depot June 2024 On Track The preferred contractor has been engaged to complete the works, with the final design being completed now and construction to commence from early December 2023.

Completion is expected as per the target date of June 2024.
HP7.2.5 - Community Engagement Strategy for the City of Logan 2020-2024 June 2024 On Track A new 2-year contract with Granicus was negotiated for the Have Your Say platform, and the team is coordinating an in-house IAP2 training session for up to 13 interested staff across the organisation. The aim is to deliver this before Christmas or early in the new year.

Work is continuing to review and refine strategic and operational community engagement documents. The aim is to better position the function's strategic role across the organisation and make it easier for other branches to understand how to best work with the communications team. New guidelines, a simplified community engagement template and detailed procedure for Community Engagement staff are being developed.

Live engagement during September includes:
  • Logan Village Riverfront Precinct
  • Logan Plan 2025 (ongoing)
  • Fishing for the Future
  • Krank School Holiday Survey.
Planning is continued for engagement around:
  • Logan Olympic Legacy.
HP7.2.6 - Customer Experience Strategy 2020 - 2024 June 2024 On Track The following actions were completed in September 2023, in support of the outcomes of the Customer Experience Strategy 2020 - 2024:
  • completed engagement to all Directorate Management Teams for the Customer Centricity Roadmap
  • Corporate Customer Experience Coordinator participated in the Development Assessment and City Safety and Liveability Service Reviews
  • work commenced on an upgrade to the current online customer portal.
The following actions were completed during the first quarter of 2023/24, in support of the outcomes of the Customer Experience Strategy 2020 - 2024:
  • the Customer Charter went live in July 2023
  • the Customer Charter Communication Plan was implemented
  • in-principal support was received from ELT to proceed the Customer Centricity Roadmap to CLT Consultation
  • Customer Centricity Roadmap consultation was completed with the Executive Leadership Team (ELT), the Collective Leadership Team (CLT) and relevant branches.
  • Corporate Customer Experience Coordinator participation in Service Reviews
  • work commenced on an upgrade to the current online customer portal.
HP7.2.7 - Value for Money Program June 2024 On Track The Value for Money (VfM) framework is currently being reviewed to ensure that all relevant initiatives are identified and to clarify the process of accessing the strategic reserve.

In the first quarter of 2023/24, potential new VfM initiatives have been identified, and are being assessed against agreed criteria for inclusion in the VfM Program.

There will be a soft VfM relaunch through updating the intranet site once the framework has been finalised.
HP7.2.8 - 2022-2026 People Plan June 2024 On Track At the end of the first quarter of 2023/24, the following key projects were delivered:
  • Strategic Workforce Planning – presented and discussed workforce planning with the Executive Leadership Team (ELT), feedback was accepted and moved to action. Identifying requirements for a people information dashboard.
  • Optimising Information Management – approval was received for TechOne Recruitment and Onboarding Systems and scoping work commenced. An out of the box recruitment platform is expected to be implemented in November 2023.
  • Leadership Development – developed a proposed, recommended approach for Program Leaders focused on proficiency in technical, people and teaming. Gained ELT agreement with the concept to move forward.
  • Diversity, Equity & Inclusion (DEI) – supported Leadership Development Program (LDP) project teams with their DEI awareness initiatives.
Current considerations:
  • Culture and Engagement – Branch culture plans are in review to identify culture success stories. Options have been identified to refresh our approach to culture. Expecting to be back on track after agreeing direction with ELT.
  • Excellence in Performance – developed an updated TechOne prototype, drafted a response to ELT for feedback and engaged business to understand the current experience. Expecting to be back on track next month pending business availability for engagement.
HP7.3.1 - Animal Management Plan June 2024 On Track During the first quarter of 2023/24, the Animal Management Program:
  • continued to provide ongoing representation on the state government animal management taskforce specific to dangerous dogs including actively advocating for legislative reform
  • commenced its first animal management related prosecution
  • carried out a review of animal specific website content
  • sought endorsement from the Executive Leadership Team (ELT) for the new Dog Safety Framework which will be shared organisation wide.
Key actions of the Animal Management Plan delivered during September 2023 include:
  • audit of animal registration receipts and preparation of final animal registration renewal notices for distribution in October 2023
  • proactive patrols of parks, reserves and known streets with recorded incidents of anti-social animal behaviour were conducted to ensure compliance, and uphold animal keeping requirements in public
  • SMS alerts were distributed to known pet owners to notify them of scheduled firework displays
  • noise monitoring technology was deployed in response to animal noise nuisance complaints
  • two warrant seizures of Regulated Dogs were undertaken.
HP7.3.2 - Illegal Dumping and Litter Enforcement Strategy (2022-2025) June 2024 On Track At the end of the first quarter:
  • The annual report card for the Illegal Dumping Taskforce was completed in preparation for presentation to Council 8 November 2023
  • 100% of year 1 actions from the Illegal Dumping and Litter Enforcement Strategy are complete
  • 40% of year 2 actions from the Illegal Dumping and Litter Enforcement Strategy are complete
  • 30% of year 3 actions from the Illegal Dumping and Litter Enforcement Strategy are complete
  • Infringements to the value of $ 151,187.00 have been issued for waste offences to date.
  • A meeting has been scheduled with the Residential Tenancies Authority to explore mechanisms to manage waste dumping in, on or distributed by rental properties in Quarter 2 2023.
HP7.3.3 - Digital Transformation Program delivery June 2024 Monitor Status continues to be 'Monitor' due to the Project Control Group (PCG) requesting an additional option for Logan Water to be evaluated within the business case. This request has extended the business case timeline from the 13th October to the 1st November (PCG approval) and it will be presented to council's City Governance Committee on 29 November instead of 6 November.

As at the end of September the following was achieved by the Digital Transformation Program (DTP):
Business Case
  • Shave and Brett consultants were requested to complete an analysis of the additional scope consideration for Logan Water. This report will be reviewed and provide input to the business case including benefits realisation
  • the business case continues to be reviewed and updated as additional data becomes available
  • revised business case dates approved by PCG.
Program Management
  • workshops with Logan Water to work through Enterprise Asset Management Solutions (EAMS) go-live and Logan Water's additional business case scope item
  • contracts working group advisory body established and kick off meeting held. Working group to develop and endorse enterprise-wide contract management processes, policies and other aspects required to support both the technological uplift and Council's objectives for a sound contract management practice beyond the Enterprise Resource Planning (ERP) system go-live
  • Finance and Supply Chain Project Management Plan feedback has been updated based on branch feedback
  • Finance and Supply Chain kick-off workshops booked for 10 October
  • 3 x supernumerary roles approved by PCG and to be allocated to Finance Branch to free up Subject Matter Experts (SMEs) capacity
  • Delivery Partner tender completed and contract negotiations commenced. Awaiting Recommend to Award approval. Estimated time of arrival for Delivery Partner to commence is week of 8 October
  • PCG approved Human Resource Service Enhancements to be delivered by DTP. Recruitment 'To Be Design' workshops and configuration document completed.
EAMS
  • Roads "To Be" workshops continue with TechOne onboarded as Technical Partner
  • project team reviewing all completed 'To Be' process design documents developed with the Branches
  • Major asset data preparation activities continued in Logan Water, Roads and Parks via their business teams with support from the EAMS project team and its partners
  • the project team continued replanning and developing an updated Project Management Plan including the delivery approach and plan and revised schedule.
Business Readiness
  • ongoing Branch Manager and Program Leader engagements to introduce Business Readiness team
  • the business readiness team are working closely with Finance Branch and the Talent Acquisition Partner Team to understand business readiness requirements and lock in key dates for training, User Acceptance Testing (UAT) and data migration.
IM Framework
  • Information Management Framework has been endorsed by PCG and handed over to the business
  • this project is complete.
Architecture
  • Architecture workstream on hold pending outcome of business case.