Operational plan report - Quarter 4

Total projects for 2020/2021 Quarter 4: 76

Corporate Plan priority area Total
Quality Lifestyles (QL) 25
Conveniently Connected (CC) 9
Economic Transformation (ET) 6
Image and Identity (II) 8
Green and Renewable (GR) 10
Next Generation Governance (NG) 18

Project status Total
On Track 0
Completed 68
Monitor 0
Not Completed 7
Not Proceeding 1

You can view each priority focus area below which includes a status update on Operational Plan key project delivery.

Quality Lifestyles (QL)

Project Target Status Commentary
QL1.1.1 - Develop the Community Infrastructure Strategy Annual Action Plan for 2021/2022.

Purpose: Outline the priorities of community infrastructure for 2021/2022.
June 2021 Completed During the June quarter the prioritisation criteria identified key variables for project selection to inform and develop 2021/22 Action Plan.

Based on this the Community Infrastructure Strategy Annual Action Plan for 2021/22 has been developed and presented to Councillors.
QL1.1.2 - Deliver construction works of a new PCYC at Cronulla Park.

Purpose: Provide a new facility to encourage increased participation in physical activity.
June 2021 Not Completed The main construction works for this project is complete. Practical completion of this project was on 23 July 2021.

As it is effectively complete, it is recommended that this project not be moved to the 2021/2022 Operational Plan.
QL1.1.3 - Construct an outdoor events space and redevelop the Kingston Butter Factory.

Purpose: Provide a performing arts space and social history museum. It will be a state-of-the-art cultural precinct for community celebration and entertainment.
June 2021 Not Completed Project works on the outside area are nearing completion. The works inside the Kingston Butter Factory building are progressing well after the delays due to rain and contaminated material.

The facility is due for handover in September 2021.

It is recommended that this project be moved to the 2021/2022 Operational Plan to track its completion.
QL1.1.4 - Complete construction of the Underwood Park Multi Sport Development.

Purpose: To increase participation in physical activity.
September 2020 Completed The Underwood Park Multi Sport Development achieved Practical Completion on 24 of September 2020. The facility is being well activated by the lessees with the Meals on Wheels organisation to move in to their new facility in the coming weeks.

Council are currently addressing some issues with drainage of the two storey building and the netball courts with Qbuild and the Principal Contractor through the defects process. Council is also completing designs to stabilise the banks on either side of the two storey building.

Completion of the netball storage shed has been delayed and works will not commence until possibly late December.
QL1.3.1 - Deliver the outcomes of the Libraries Learning and Discovery Strategy 2019-2023.

Purpose: Provide meaningful library programming to the community. This will be achieved through the six strategic priorities of:
  • access and inclusion
  • economic opportunity
  • nurturing learning and well-being
  • sustainability
  • connected community
  • embracing life-long curiosity and discovery.
June 2021 Completed Over the fourth quarter, Libraries have completed the following actions in support of the objectives of the Libraries Learning and Discovery Strategy:
  • Progression of the Libraries and Creative Industries branch community programming 2020 and beyond project. Over the fourth quarter, the project group actioned the programming priorities that supported COVID-recovery and key areas of learning for the community. Priorities included the return of COVID-safe in-library children's, teen and adult activities, employment assistance programs, one-on-one technology help and adult literacy support. The project team has also established the Libraries and Creative Industries branch's programming priorities for the second half of 2021.
  • 6,945 people participating in a library event or activity.
  • Delivery of hybrid library events that allows an in-library and virtual audience to participate at the same time.
  • Ongoing delivery of online programming including live streaming and on-demand events.
  • Recommencement of COVID-safe community use of library meeting rooms.
  • Delivery of eight business programs to support Queensland Small Business Month. These were delivered as in-person, live-stream, and hybrid events.
  • The launch of the Libraries' job-help program in May. 118 people have been assisted through this program.
  • Bulk deliveries of library items to 262 home library service customers.
  • Commencement of the Volunteer return plan.
About:

The Libraries Learning and Discovery Strategy informs the programming deliverables of the Libraries and Creative Industries' Business Plan. This strategy provides the framework to allow library staff to be guided in the development, implementation and evaluation of purposeful and engaging library programming and community engagement.
QL1.3.2 - Deliver the libraries early years services and 'First Five Forever' initiative.

Purpose: Support early years and literacy-based development for Logan families with children under five.
June 2021 Completed Over the fourth quarter First Five Forever has completed the following actions in support of the Libraries and Creative Industries 2020/21 Business Plan:
  • Delivery of COVID-safe, face-to-face children's literacy sessions at libraries.
  • Delivering COVID-safe community outreach through their network partnerships across the city.
  • Participation at the Springwood Early Feeding and Support clinic and Yarrabilba Family and Community Place.
  • Participation in 108 community network meetings.
  • Participation in the Welcome Jarjums to Country working group.
  • Progression of the Logan Little Learning Stars and the Community Literacy Champions as part of a State Library of Queensland grant.
  • Launch of the First Five Forever early years learning puppet Ace during Under 8's week.
  • Delivery of seven National Simultaneous Story Time sessions to 94 participants during Under 8's week.
  • Facilitation of the Mumma Got Skills craft workshop for mothers and their babies.
  • Support of the Bringing our Jarjums up Stronger event hosted by Gunya Meta at the Family Place in Woodridge during Reconciliation week.
  • Represented Logan City Council at the Infant Mental Health World Congress held in Brisbane.
  • During the 2020/21 financial year, 6,641 people participated in 592 First Five Forever programs for children under five years old.
About:

First Five Forever aims to support the learning outcomes for all Logan children aged 0-5 years old by providing programs that offer talking, reading, singing, playing, dancing, and moving.
QL1.4.1 - Deliver a health and wellbeing program for all ages and abilities.

Purpose: Provide opportunities for residents to take part in physical activities and health and wellbeing programs that are affordable and accessible.
June 2021 Completed Live Well Logan delivered over 110 active and healthy well-being activities between 1 April and 30 June 2021. During this time 2 days of activities were cancelled due to COVID lockdowns in South East Queensland.

Highlights of the program in this financial year include:
  • From July 2020 to June 2021, 44 service providers delivered over 140 programs resulting in over 7,000 individual participants attending the Live Well Logan program.
  • In July 2020 an 'Active and Healthy at Home' webpage was created to link out to providers platforms which enabled community to engage with and participate in programs online whilst in lockdown.
  • From November 2020 to February 2021 Live Well Logan engaged with the community to seek feedback on the current program, which received 291 responses. These responses were used to directly inform the activities available in the next Live Well Logan program.
  • From January to February 2021 Live Well Logan received 132 applications for Request for Proposals to become a service provider for the 2021/2022 Live Well Logan program.
QL1.5.1 - Deliver an Illegal Dumping Team project, funded by the State Government.

Purpose: Undertake key education and enforcement initiatives to reduce waste dumping issues in the city.
June 2021 Completed The Taskforce has continued in delivering positive community outcomes through surveillance and enforcement. Through partnership with DES, hotspot locations have been identified and signage has been placed on order. These signs will shortly be rolled out citywide to priority hotspot locations. In recognition of the ongoing community need, Council has funded a 12 month continuation of the Taskforce to deliver an expanded marketing, education and enforcement campaign in the interests of dumping and littering reduction.
QL1.5.2 - Deliver actions from the City of Logan Animal Care Strategy 2018-2022.

Purpose: Maintain healthy and safe places and spaces for residents, businesses and visitors.
June 2021 Completed At the end of the fourth quarter, actions from the Animal Management Strategy continue to be delivered.
These include:
  • The cat management plan draft has been completed however the project remains on hold until 21/22.
  • Annual inspections of regulated dog keeping conditions continue. In line with amended AMCDA regulations, new collars are being provided for all regulated dogs.
  • Implementation of the Barking Dog Management Plan has been completed and continues to be reviewed to determine additional opportunities for its' use.
  • The Be-Pet Smart program is being delivered (where possible) in line with directions from the QLD Health to ensure a COVID-19 safe delivery with provision of learning material to schools for their delivery to students.

QL2.1.1 - Deliver the Arts, Culture and Heritage Strategy 2018-2022 action plan.

Purpose: Improve community capacity and the image of the city. This will be achieved across the City of Logan through the five strategic outcomes of:
  • development
  • engagement
  • places and spaces
  • partnerships
  • communication.
June 2021 Completed The five key actions of Creative City: Logan City Council's Arts, Culture and Heritage Strategy 2018-2022 are development, engagement, places and spaces, partnerships and communication. These were delivered through exhibitions, activities, programs, events and activations during June.

About:

The strategy is a whole of Council document that states Council's commitment to arts, culture and heritage. It defines the key areas, strategies and actions to guide the management, sites and provision, and plan for its future growth and development. The strategy outlines areas where Council will work to develop more opportunities for the community and its arts, culture and heritage professionals to watch, enjoy and participate in creative activities, with the aim of enhancing quality lifestyle, creative industries and business across the region. It is an integral part of developing the city as an emerging tourist destination.

Actions:

Development: Artist-led face-to-face public programs at Logan Art Gallery continue to be successful with COVID-19 safe plans for each event. Content and speakers confirmed for six Logan Live Boost Professional Development sessions. The consultant for the Music Action Plan worked with Creative Industries and Community Engagement to plan community consultation activities.

Engagement:

A COVID-19 safe opening of new exhibitions was held on 11 June with 178 attendees. Community consultation with First Nations and culturally diverse communities continues to assist in the development of thematic displays for the Living Museum of Logan. Arts in the Open event was held with community arts organisations. Online gallery presentations continue on social media platforms and interactive online activities were delivered. Electronic direct mail e-bulletins were distributed to Creative Industries database of public and volunteers promoting exhibitions, activities, events and funding.

Places and spaces:

COVID-19 safe requirements are being undertaken to ensure visitor safety at all Council venues. A total of 29,796 people visited Logan Art Gallery or participated in related outreach activities, including digital outreach; this includes 3,335 people in June. Three concept designs for the interpretive timeline for Kingston Butter Factory were presented and one is progressing to design development; discussions are underway with two artists to develop their designs elsewhere in the Kingston Butter Factory precinct. Beenleigh Town Square shade structure is near completion, and 10 artists developed concepts for the Loganlea Road street enhancement project.

Partnerships:

Creative Industries is partnering with Logan Hospital to provide input into developing an engaging look and feel for the community, as part of the hospital expansion project. Logan Live supporters and partners Queensland Government, BEMAC and JMC Academy are discussing with staff their input for this year's Boost program.

Communication:

Libraries and Creative Industries staff attended the annual Australian Museums and Galleries Association national conference in Canberra (7 – 10 June), and convened the Art, Craft and Design National Network session at the National Portrait Gallery. Creative Industries staff attended the Public Galleries Association meeting at the Home of the Arts (HOTA) Gold Coast. Electronic direct mail invitations and e-bulletins were distributed to residents promoting exhibitions, resources, activities, events and funding. Input was provided for the branding project for Logan Art Gallery, Mayes Cottage, Kingston Butter Factory and Living Museum of Logan. Logan Art Gallery Instagram account now has 1,210 followers.

Outcomes:

Social media remains the key platform for promoting Creative Industries' exhibitions, events and activities.
Visitors to the gallery have welcomed the Check in QLD app and the reintroduction of COVID-19 safe programs.
QL2.1.2 - Develop and curate content for the Living Museum of Logan at the Kingston Butter Factory Cultural Precinct.

Purpose: Share the stories of:
  • our culturally diverse communities
  • Logan's Aboriginal and Torres Strait Islander communities
  • themes of importance to Logan's people.
June 2021 Completed About:

The Living Museum of Logan will tell the stories of the people of Logan. It will be a non-collecting, family-friendly space where residents and visitors to Logan can be inspired and learn about Logan City.

Action:

Museum Curator continues external consultation with First Nations and culturally diverse communities to assist in the development of thematic displays for the Museum. Discussions with artists and fabricators about displays and public artworks undertaken. Furniture and Australian Institute of Aboriginal and Torres Strait Islander Studies map and Barunga Statement have been ordered for the First Nations space. Curatorial themes based on food and fashion have been developed for the 'welcome' and 'atrium' spaces. Three concept designs for an interpretive timeline were assessed and one is progressing to design development; discussions are underway with two artists to develop their designs elsewhere in the Kingston Butter Factory precinct. Meetings with Sports and Leisure Facilities and Marketing branches regarding fit out, programming and branding for Kingston Butter Factory. Filming and editing continues for the initial displays. Meeting was held with artist to refine exhibition design for Snapshot! exhibition.

Outcome:

Development of the Living Museum of Logan spaces, displays and programs continues.
QL2.2.1 - Deliver community services grants that fund community organisations.

Purpose: Support projects that respond to community priorities.
June 2021 Completed The following Community Development Funding grants were awarded between April and June 2021:
  • Eight community organisations were awarded Community Project Grants to the value of $27,056.87.
  • One community organisation was awarded a Community Response Grants to the value of $5,000.
Highlights of activities delivered this financial year include:
  • Throughout the 2020/21 financial year a total of 51 grants to the value of $222,108.89 were awarded through Councils Community Development Funding programs. The grants are available to local organisations to support community development outcomes and community priorities. As local organisations' priorities shifted to responding to community needs emerging during COVID-19, we adapted the grants to support this need.
  • In August 2020 we introduced a temporary COVID-19 Community Response Grant program. The program delivered 34 grants to the value of $150,127.52 to support local organisations meet emerging community priorities due to COVID-19. It enabled essential programs and services to continue throughout COVID-19. It also enabled organisations to respond with food relief, technology and online programs to support families and people who were isolated and/or doing it tough due to COVID-19. The program ceased in December 2020.
  • In March 2021 we introduced an ongoing Community Response Grant program. This grant meets an ongoing need for local organisations to have access to quick grants that support immediate needs in the community. Two Community Response Grants were awarded to the value of $10,000 this financial year. We have continued to offer Community Project Grants throughout the year. 15 Community Project Grants to the value of $61,981.37 were awarded throughout the financial year.
QL2.2.2 - Deliver a school holiday program for five to 17-year-olds.

Purpose: Encourage young people to take part in active and healthy programs during school holidays.
June 2021 Completed The April KRANK school holiday program ran from 6 to 18 April 2021 and delivered 94 in-person activities and 14 at-home activities with a total of 1,913 young people attending.

Bookings for the June/July 2021 school holiday program opened on Monday 14 June 2021.

Highlights of the program in this financial year include:
  • From June 2020 to April 2021, the KRANK school holiday program engaged with 38 providers to deliver 116 online and in-person interactive activities attended by over 7,500 young people in Logan.
  • 50 additional activities were programmed for the January 2020 school holiday period to assist with community demand.
  • Council engaged with young people across the city to identify what they would like to see delivered in future school holiday periods. 242 responses were received which directly informed the activities available in the next financial years school holiday program.
  • Request for proposals to be a KRANK provider opened in November 2020, with 108 applications received.
QL2.2.3 - Coordinate the implementation of the Access and Inclusion Plan 2019 - 2022.

Purpose: To create a more accessible and inclusive city for everyone.
June 2021 Completed Highlights of activities delivered during this quarter include:
  • Council's Access and Inclusion Internal Working Group met in May where actions of the Access and Inclusion Plan continue to be progressed.
  • A partnership with Carers Queensland, two workshops were held to support people with disability. The first workshop in May supported people to access the NDIS. The second workshop in June provided support for self-advocacy.
  • Procurement has been completed for Disability Awareness Training. This will deliver training to 2,000 staff within a three-year period.
  • Three new accessible services have been added to the Live Well Logan program to increase programs for people with disability and mental health.
  • New height adjustable public computer desks are now available in Council libraries.
  • Council's website has been updated to include the locations of our accessible services and customer service facilities.
Highlights of activities delivered this financial year include:
  • Completion of the first Annual Progress Report 2019-2020 which was endorsed by the City Lifestyle Committee on 30 September 2020.
  • First local government in Australia to achieve a gold standard level through the Plain Language Pro program for our website design. This means our website is easier to access and can be used with assistive technologies.
  • Council's website has been updated to include the locations of our accessible services and customer service facilities.
  • Advocated for the relocation of Loganlea Train station which will conform to the Disability Discrimination Act 1992.
  • Made the Planning Scheme available in accessible formats when requested.
  • Registered with the Australian Human Rights Commission Register of Disability Discrimination Act Action Plans and we are one of twelve local governments in Queensland that are registered.
  • Procurement was completed for Disability Awareness Training. This will deliver training to 2,000 staff within a three-year period.
  • Three new accessible services have been added to the Live Well Logan program to increase programs for people with disability and mental health. Two workshops on the NDIS were delivered in partnership with Carers Queensland. The topics were accessing the scheme and self-advocacy.
  • New height adjustable public computer desks are now available in Council libraries.
  • Of the 84 actions identified in our Access and Inclusion Plan 2019-2022, the following outcomes have been achieved to date: - 57 actions are on track - 25 actions have been complete - 2 action are on hold
QL2.2.4 - Coordinate the implementation of the Reconciliation Action Plan.

Purpose: To achieve Council's vision for reconciliation. To increase respect and understanding.
June 2021 Completed Highlights of activities during this quarter:
  • Council's RAP Ambassadors met in April to share updates and discuss practical actions to promote reconciliation across the organisation.
  • Council's RAP Working Group met in May to share updates and provide input into an interim Reconciliation Action Plan.
  • We established and recruited an identified First Nations Community Development Officer role in Council. This role will be responsible for leading our RAP. They will also work with First Nations and non-First Nations individuals, groups, organisations and internal stakeholders to deliver collaborative community development initiatives.
Highlights of activities delivered this financial year include:
  • Council participated for the first time in the biannual Reconciliation Australia Workplace RAP Barometer. It is a survey to monitor attitudes towards reconciliation at the workplace level. 295 Council employees completed the survey.
  • An internal online campaign for NAIDOC 2020 was held to showcase the importance of caring for and acknowledging Country.
  • In September 2020 we established a First Nations Community Action Group with Elders and representatives of Logans First Nations communities. The group meets bi-monthly and provides an opportunity to strengthen relationships between Council and Logan's First Nations communities. It also provides a platform for engagement and action on community priorities and Council initiatives.
  • We delivered an outcome report at the completion of our second RAP in December 2020. The report outlines that 50 of the 55 deliverables set out in Council's current RAP were either completed, ongoing or being progressed. The report was be presented to the City Lifestyles Committee in January 2021 and is available on Council's website.
  • We established and recruited an identified First Nations Community Development Officer role in Council. This role will be responsible for leading our RAP. They will also work with First Nations and non-First Nations individuals, groups, organisations and internal stakeholders to deliver collaborative community development initiatives.
  • The RAP Working Group has commenced planning for a third Reconciliation Action Plan and will prepare an interim plan so that Council can continue and deliver and monitor actions and outcomes between RAPs.
QL2.2.5 - Deliver the Community Development Action Plan.

Purpose: To work with the community to build a more cohesive and connected City of Logan.
June 2021 Completed The two year Community Development Action Plan reached its completion date in December 2020.

Over the two years, there were a total of 55 priorities identified within ten key work areas to help guide the Community Development program.

93% or 51 of the priorities have been achieved through partnerships, projects and initiatives. The remaining
four priorities are currently underway and are due for completion in 2021.

All 55 actions have been incorporated into the Community Development Action Plan 2021/2022. This action plan has been developed to guide the work and priorities of the Community Development program for the next 12 months.

Highlights from this financial year include:
  • Delivered collaborative activities during Seniors Week.
  • Established an Emergency Relief Network.
  • Secured more than $644,000 from the Federal Government's Driving Social Inclusion through Sport and Physical Activity grant program to deliver The Swim Logan project. The Swim Logan project educates participants on water safety and provide culturally-appropriate lessons at four Logan pools.
  • Developed in collaboration with Griffith University a new mental health initiative called the Walk and Talk for Wellness project. This was developed to respond and support mental wellbeing in the community. The program provides a low-cost walking counselling service for local residents.
  • Established the Logan Youth Action Group where young people aged 14-24 years from across Logan develop and deliver youth led initiatives in response to identified needs.
  • Established a First Nations Community Action Group, a partnership between Council, Elders and community representatives. The group meet quarterly and provides an opportunity for community and Council to partner and engage on relevant priorities to action identified community priorities, as appropriate, within Council's sphere of influence.
  • Established a Cultural Leaders Action Group providing a forum for engagement between Council and leaders from Logan's diverse communities. The group will also progress social cohesion priorities for the city.
  • Publicly promoted the Christmas donation drives of 14 local organisations through our webpage, social media and networks. This "Christmas Kindness" initiative responded to an identified need to support local emergency relief organisations who were seeing an increase in demand, but have not been able to raise funds due to COVID-19.
  • Sent seven Community Services e-newsletters to approximately 900 recipients. The e-newsletters provided updates to the community on events, training opportunities, funding and resources available.
  • Delivered online safety webinars to Logan seniors.
  • Provided direct phone support for seniors having difficulty connecting online.
  • Partnered with local services to provide free education sessions to seniors on how to use electronic devices.
  • Partnered with local services to provide free electronic devices (iPads) and technology support for seniors.
  • Delivered a neighbour connection card to give residents the opportunity to reach out to their neighbours and offer help.
  • Ran a 'Postcards from the Heart' initiative where residents were able to connect by sharing something positive through art on a postcard. This was displayed on the Logan Central Library during October 2020 for Queensland Health Week.
QL2.3.1 - Implement and evaluate the SafeRoads4Logan, Road Safety Strategy 2017-2021.

Purpose: Encourage safer travel for residents, businesses and visitors.
June 2021 Completed During the fourth quarter, weekly Traffic meetings continued between Queensland Police, Department of Transport and Main Roads and Logan City Council road safety officers to discuss data trends and coordinate targeted road safety operations/campaigns within Logan Police District).

Road Safety Strategy Workshops was held with road safety partners and key stakeholders to keep engaged, program events, discuss data to be used in evaluation and share other road safety learnings.

Speed Management Advisory Committee (SMAC) also met to discuss and approve changes to posted speed limits within the City.

Easter road safety campaigns, as well as National Road Safety Week and Queensland Road Safety week, were coordinated digitally (online) with consistent messaging across Queensland Police, Department of Transport and Main Roads and City of Logan media platforms.

Fatality Free Friday event, held at Grand Plaza under a COVID safe plan in May, was the main community engagement activity for the year, with quality road safety displays and conversations between various road safety partner/stakeholder representatives and the public.

Road safety staff from Council and Police also have an active role in recently established Logan Hooning Taskforce and Working Group.

Current strategy focus is the collation of various crash and injury data from road safety partners for strategy evaluation of current strategy and development of new strategy within the next 6 months.
QL2.4.1 - Deliver a crime profile that provides a detailed analysis of key crimes in the City of Logan.

Purpose: Help plan community safety and crime prevention activities for the next year.
June 2021 Completed Throughout this quarter, crime statistics for the Logan Local Government Area have been collected and analysed to identify priority issues, locations and emerging trends through the development of an annual Crime Profile for the City of Logan. Crime statistics for 2019/2020 have also been utilised to develop Divisional Crime and Safety Profiles to help inform planning for targeted crime prevention initiatives for the year ahead.

These documents have also been distributed to the Mayor and relevant Councillors.
QL2.4.2 - Deliver an awards event.

Purpose: Acknowledge those who work to create a safer City of Logan:
  • individuals
  • community groups
  • not-for-profit organisations
  • businesses
  • government agencies
June 2021 Completed The 2020 City of Logan Safe City Awards were held in November 2020. These awards acknowledge the work of volunteers, not-for-profit groups and government/businesses that have contributed to making Logan more welcoming, inclusive and safe through initiatives, activities or events over the past 12 months.

A total of 12 nominations were received and a total of 7 awards were presented to the community.
QL2.4.3 - Deliver a community survey.

Purpose: Gain an understanding of community perceptions on safety and crime in the City of Logan. This will support planning for community safety and crime prevention activities. It will also determine if the Community Safety Program is meeting the goals identified in the City of Logan Safe City Strategy and Action Plan.
June 2021 Completed Analysis of the 2020 survey results and development of a key findings report for the city and divisional key findings reports for Council's 12 divisions have been completed and distributed to the Mayor and relevant Councillors.

The city-wide key findings report has been made publicly available to the community on Council's website.

Results from the 2020 Safe City Logan community survey and crime profiles will assist the Community Safety Program in the planning of targeted community safety initiatives for the year ahead.
QL2.4.4 - Deliver expo-style 'building social capital' community hubs that bring together social support networks.

Purpose: Create opportunities for referral pathways for Community Corrections clients and other community members.
June 2021 Completed A Services on Station event was held on 13 May in the vicinity of the Logan Central Probation and Parole office at 6 Ewing Rd. The highest volume of service providers attended (approx. 20) and over 40 community members were provided information and linked into local services. Various donations and giveaways were distributed to those in need. The next event is scheduled for July 22, 2021 in Beenleigh.

The Building Social Capital hubs project underwent a rebranding in 2020 and are now called Services at the Square and Services on Station, to reflect the two locations where the hubs are held; Beenleigh Town Square and Station Road, Woodridge. Over the year, the Community Safety Program held 3 of these events, resulting in approximately 90 direct referrals made to local service providers.
QL2.4.5 - Install and replace CCTV safety cameras as scheduled.

Purpose: Ensure continued successful operation and expansion of the Logan Safety Camera Program network.
June 2021 Completed The Logan Safety Camera Program capital works and replacement schedule for 2020/2021 has been completed. Highlights of the work undertaken during the last quarter includes:
Installation of cameras at Millwood Park, Heritage Park and Intersection of East Beaumont Rd and Chambers Flat Rd, Parkridge and Kenny Road, Chambers Flat (Chambers Flat and Logan Reserve Community Centre).

This year the Logan Safety Camera Program installed and replaced CCTV safety cameras at identified locations across the city. This was to ensure continued successful operation and expansion of the Logan Safety Camera network.

Working with the community, and community partners the Logan Safety Camera Program completed the following works:
  • Integrated CCTV cameras from the Health and Environment and Waste facilities and installed CCTV cameras at the Logan Hyperdome Library.
  • Worked with our Water Business Branch in the delivery of critical infrastructure security projects.
  • Worked with our Economic Development and Strategy Branch on upgrades to the Logan Village Green including the park and the river walk area, Cusack Lane underpass, Jimboomba and the Slacks Creek Green Link project, Dennis Road Shared Pathway and Murrajong Streetscape Works.
  • Worked with our Road Infrastructure Planning Branch regarding the installation of cameras at Magnesium Drive and Browns Plains Road roundabout as well as Dennis Road, Springwood.
  • Worked with local Councillors to install CCTV cameras in 13 different locations within the suburbs of Marsden, Heritage Park, Parkridge, Riverbend, Chambers Flat, Loganholme and Eagleby.
QL2.4.6 - Deliver a new Safe City Strategy and Action Plan. It will replace the current 2016-2020 Strategy and Action Plan.

Purpose: Provide tangible actions for the Community Safety Program that will help create a safer City of Logan.
December 2020 Completed The draft City of Logan: Safe City Strategy and Action Plan 2021-2025 was available for community consultation for a period of three weeks, from 17 September 2020 to 11 October 2020. Once the community consultation period had closed, community feedback was analysed and appropriately incorporated into the draft Strategy and Action Plan.

The final version of this document was adopted by the City Lifestyle Committee on 10 November 2020.
QL2.4.7 - Deliver at least 48 targeted crime prevention and community safety activities. Four will be delivered per division each year. These will respond to crime and safety concerns of each local community.

Purpose: Increase community safety and positive community perceptions about crime and safety.
June 2021 Completed During the fourth quarter, there were a total of 12 crime prevention and community safety initiatives undertaken across divisions 1, 2, 3, 4, 5, 6, 9 and 10

Over the 2020/ 2021 financial year, a total of 48 targeted divisional crime prevention activities were delivered Some of the activities included:

Crime Trivia for Seniors - The aim of this initiative is to provide senior members of the Logan community on how to reduce their vulnerability to crime in a fun and interactive way using crime-related trivia questions.

Drink Rite – This initiative focuses on educating adults about the alcohol content of different drinks, what makes a standard drink, and the effect alcohol has on the body and mind. Drink Rite, a Queensland Police Service initiative, are delivered in partnership with the Logan District Crime Prevention Unit Liquor Industry Action Group, Queensland Heath and our Community Safety Officers at different Logan-based responsible-service-of-alcohol venues.

Secure Your Tools – This initiative focuses on raising awareness amongst tradespeople and those working in the construction industry about easy actions they can take to reduce opportunistic crimes such as theft and vandalism at and around construction sites.
Business Crime Prevention – This initiative involves the distribution of business-specific situational crime prevention information to Logan-based small businesses to help them reduce opportunities for crime at their places of business.

Eyes and Ears Out and About – This initiative involves the distribution of information to community members about being an active bystander. An active bystander is someone that takes a proactive approach to noticing and reporting suspicious behaviour or incidents to the appropriate authorities. In doing this, active bystanders limit opportunities for anti-social and criminal behaviour in our community spaces.
QL2.4.8 - Deliver expo-style 'Youth Street Hubz' focused on young people. These will bring together social support networks for young people across the Logan community.

Purpose: Create opportunities for referral pathways for Youth Justice clients and other local young people.
June 2021 Completed The second Youth Street Hubz for 2021 was held at Crestmead Park on Thursday, 19 April. This event coincided with QLD Youth week. Between 250 and 300 young people and their parents/care givers attended the event at which they engaged with service providers in activities such as stress ball and badge making, ball games, arts and crafts, music and dance. Additional prizes were donated by YFS and a rock climbing wall was funded by Council. 10-15 agencies participated. This event had the highest attendance rate since its inception in terms of service providers and attendees.

The third Youth Street Hubz for 2021 was held at Crestmead Park on Thursday, 10 June. Approximately 150 young people and their parents/care givers attended the event. Five service providers attended this event and provided activities such as drumming, gaming, art, football and a dance comp. A BBQ was run by Youth Justice with Council covering catering costs.

Throughout the year, the community safety program have developed a network of key stakeholders to be involved in the Youth Street Hubz project, built positive partnerships with key stakeholders and Logan service providers, developed a hub, geared towards youths within Logan and held three successful hubs at Crestmead Park with more than 500 young people engaged and connected-in with local support services.

The concept of the Youth Street Hubz is still in its infancy. 2021 hubs will continue to run as a trial project with a review to be undertaken in December 2021.

Conveniently Connected

Project Target Status Commentary
CC1.1.1 - Deliver a report on the medium term needs for Logan's public transport system.

Purpose: Identify infrastructure requirements for the City of Logan for the next five to 15 years.
June 2021 Completed A report on the medium-term needs for Logan's public transport system was written to Council to fund the medium-term passenger transport strategy. Council after considering the report indicated that the matter may be considered in a future budget.
CC1.2.1 - Complete a condition survey of the sealed road network.

Purpose: Assess overall condition and prioritise future rehabilitation.
June 2021 Not Completed Field work is completed and 2000km of imagery and data has been provided by the contractor. Due to COVID-19 the processing was delayed but expecting final data of full network condition survey by the first week of August 2021.

It is recommended that this project be moved to the 2021/2022 Operational Plan to track its completion.
CC1.2.2 - Deliver the annual Road Maintenance Program.

Purpose: Maintain the quality of the local road network.
June 2021 Completed As at the end of June 2021, 100% of the annual Road Maintenance program of works was delivered.
CC1.2.3 - Deliver the annual road and drainage capital program.

Purpose: Improve active transport across the city.
June 2021 Completed Q4 delivery of the 20/21 Capital Works Program saw a significant increase in expenditure compared to the prior quarter (from $6.5M to $28.7M). At the end of the Fourth Quarter of the 2020/2021 Financial Year, delivery of the Capital Roadworks and Drainage Program has now achieved $63.4 million in overall expenditure. With a number of significant projects recently commencing construction and further key projects well progressed through the procurement stage this momentum is expected to continue into the 21/22 FY.

Significant projects, which were underway or completed in the Fourth Quarter include the following:
  • Black Spot Upgrade Grand Plaza Drive Pedestrian Improvements, Browns Plains ($0.3 Million)
  • Compton Road Shared footpath / cycleway, Slack Creek between Allgas Street and Baker Street ($3.2 Million)
  • Park Ridge State High School Carpark Upgrade, Park Ridge ($230,000)
  • Loganlea Healthy Street Project, Loganlea – In collaboration with ED&S ($5.7 Million - $2m Savings Expected)
  • Major Intersection Upgrade of Logan Reserve Road / Muchow Road, Marsden ($1.2 Million)
  • Early works for the Chambers Flat Road Upgrade, Kings Way to Mount Lindesay Highway, Chambers Flat ($25 Million)
  • Local road upgrade of Schmidt Road, Eagleby ($0.4 Million)
  • Local road upgrade of Stockleigh Road, Stockleigh ($1.0 Million)
  • Local road upgrade of Friar Street, Munruben ($1.5 Million)
  • Holmview Road local road kerbing and stormwater drainage upgrade, Beenleigh ($0.9 Million)
  • Early works associated with Stage 1 of local road kerbing and stormwater drainage upgrades to streets in Jimboomba ($8.6 million)
  • Local road kerb and stormwater drainage upgrade of Webb Road, Loganlea ($2.9 million)
  • Local road kerbing and stormwater drainage upgrades to Dickman Road, Forestdale ($0.45 Million)
  • Stormwater drainage upgrade in Stage 2 of the Defiance Road Catchment, Woodridge ($1.8 Million)
  • Pipe manufacture underway for stormwater drainage upgrades in Stages 2 & 9 of the Woodlands Drive Catchment, Rochedale South ($18 Million)
  • Grand Plaza Drive Culvert Rehabilitation, Browns Plains ($3.88 Million)
  • Teese Bridge timber bridge replacement with new concrete bridge, Veresdale Scrub ($1.7 Million jointly funded)
  • Kerb and channel rehabilitation at numerous locations to support future asphalt resurfacing works ($1.3 million)
  • Pavement resurfacing & reconstruction works across a number of locations ($5.9 Million)
There is currently $87.1 million of projects currently in various stages of pre-construction (including procurement and pre-award assessment) in preparation for construction commencement. This includes:
  • Major Intersection Upgrade of Browns Plains Road & Scrubby Creek Road, Browns Plains ($1.8 Million)
  • Major Intersection Upgrade of Albert Road & Station Road Intersection, Bethania ($1 Million)
  • Priority Infrastructure Upgrade of Gilmore Road, Berrinba ($11 Million)
  • Chambers Flat Road Upgrade, Kings Way to Mount Lindesay Highway, Chambers Flat ($25 Million)
  • Local road upgrade of Leopardwood Road, Cedar Grove ($1.2 Million)
  • Stage 1 of local road kerbing and stormwater drainage upgrades to streets in Jimboomba (South Street, Nichols Street, John Street, Mary Street & Hill Street) ($7.8 million)
  • Stormwater drainage upgrades of Woodbeck Street & Pheasant Street Catchment, Beenleigh ($1.6 Million)
  • Stormwater drainage upgrades of Stages 1-5 of the Kelly Street Catchment, Eagleby ($10 Million)
  • Stormwater drainage upgrades of Stages 1 & 2 of the Cowper Street Catchment, Eagleby ($10 Million)
  • Pavement reconstruction across a number of locations ($3.5 Million)
  • Stormwater Infrastructure Rehabilitation across a number of locations ($800,000)
  • Tully Bridge timber bridge replacement with new concrete bridge, Lyons ($1.4 Million)
  • 21-22 Asphalt Resurfacing Package 1 & 2 ($5 Million)
  • Scott Lane Culvert Replacement, North MacLean ($7.0 million)
CC1.3.1 - Deliver construction works for the Compton Road cycleway project.

Purpose: Link the cycleway to Logan Road and provide connections to the Springwood Bus Station.
June 2021 Completed As at the end of the fourth quarter, planned construction works for this project have commenced for this financial year. Construction of the Compton Road Cycleway is currently ongoing and is scheduled to be completed by August 2021.
CC2.1.1 - Commission the Cedar Grove Wastewater Treatment Plant (WWTP) in the Cedar Grove Environment Centre.

Purpose: Improve services to the southern region of the City of Logan.
June 2021 Completed The Cedar Grove Wastewater Treatment Plant (WWTP) has been commissioned and is treating wastewater from the Greater Flagstone Priority Development Area (PDA).
CC2.1.2 - Deliver master planning works for the Chambers Flat Wastewater Treatment Plant (WWTP) and associated trunk infrastructure.

Purpose: Improve services to the southern region of the City of Logan.
June 2021 Completed Master planning works of the Chambers Flat Wastewater Treatment Plant site has commenced.

The next stage for its completion is dependent on the clarification of a diversion of Chambers Flat Road onto the site.
CC2.2.1 - Deliver a review of the planning scheme.

Purpose: Enable well planned development for residents and businesses.
June 2021 Completed Work on the version 9 Logan Planning Scheme 2015 amendment has been completed and documents are pending delegate sign-off before submission to the State.
CC2.3.1 - Deliver a review of the Local Government Infrastructure Plan.

Purpose: Deliver trunk infrastructure in the City of Logan.
June 2021 Completed As at the end the end of the fourth quarter, the land valuation and feasibility test of the Schedules of Work have been completed and the preparation for community consultation has commenced.

Economic Transformation (ET)

Project Target Status Commentary
ET1.1.1 - Deliver actions to generate $70 million of investment and 500 local jobs by promoting the City of Logan.

Purpose: Increase local jobs and stimulate economies.
June 2021 Completed In the fourth quarter investment announcements to the value of $7.4 million were recorded in the industrial tools supply and manufacturing industries.
The annual total investments recorded was over $229 million from 19 separate projects far exceeding the annual target of $70 million. These investments included projects in the healthcare, transport and logistics, manufacturing, office, retail and speculative construction industries.

As a result of these investments 449 new jobs were created and 311 jobs were retained in the city, exceeding the annual target of 500.
ET1.2.1 - Deliver 15 business-relevant workshops for businesses in the City of Logan.

Purpose: Build the capacity of the local economy.
June 2021 Completed In June two business workshops were delivered bringing the yearly total to 26, far exceeding the annual target of 15.

Three joint Chambers of Commerce events were hosted bringing guest speakers, Steven Bradbury, Robyn Moore and Angry Anderson to Logan.

Four seminars were delivered in partnership with Griffith University as part of their Entrepreneurship Series and five digital marketing workshops were delivered as part of Council's economic recovery activities.

A month long program of over 40 events was hosted or supported by Council during Small Business Month in May. Highlights include a Supplying to Council: what you need to know event, the Logan Manufacturing event, joint Chambers of

Commerce and Logan Office of Economic Development networking night and the Tourism networking night.

The Logan Office of Economic Development also hosted the State Budget Breakfast which attracted 150 registrations.
ET1.4.1 - Deliver two investment attraction events in the City of Logan.

Purpose: Attract investment and local jobs.
June 2021 Completed One investment attraction event was delivered in the fourth quarter in conjunction with the State Treasurer to understand current issues and what government can do to help businesses.

The annual target of two investment attraction events was met, the first being a Tech round table held in the second quarter.

ET2.1.1 - Prepare for Council Endorsement a new Economic Development Vision and Strategy for the City of Logan.

Purpose: To attract investment and provide a framework for the community, businesses and investors in the city.
June 2021 Completed As at the end of the fourth quarter, planned activities for the preparation of the new strategy were achieved, with a draft prepared.

After review of the draft strategy, significant changes to the document were requested. A revised draft is now under review and it is anticipated that a Councillor briefing presentation will be made for the 10th August.
ET2.3.1 - Plan and deliver the city's first innovation hub (coLab).

Purpose: Support entrepreneurship, scaling businesses and capability uplift. Attract investment and highly skilled jobs to the City of Logan.
June 2021 Completed As approved by Council (10/11/2020) a Heads of Agreement has been executed with GO1 to take up a tenancy at the existing Go1 global headquarters at 2904 Logan Rd, Underwood. Subsequently a licence agreement with GO1 to occupy the space has been executed. The Expression of Interest for Portfolio Company selection was advertised' subsequently three Portfolio Companies were selected as the first cohort for the coLab. The coLab Advisory Board has met monthly and additionally to provide advice and recommendations on the selection of Portfolio Companies. The coLab was launched on Friday the 26th of March with a significant number of key stakeholders in attendance.
ET2.4.1 - Develop a combined "Think Local, Buy Logan" social and local marketing campaign.

Purpose: To increase social and local spend in the city.
June 2021 Completed The 'Think local, Buy Logan' internal campaign objectives have been delivered.

An animated video was distributed to all staff by Council's A/Chief Executive Officer to provide awareness and education about best value decision making, supported by the Local Buy Policy.

To demonstrate Council's commitment to proactively supporting local businesses local benefits, amendments to the current Buy Local Policy have been adopted. This includes increasing opportunities for best value decision making that creates new jobs and upskills our workforce, with an advantage to businesses who demonstrate a commitment to local development growth and initiatives.

There will now be a shift to target the campaign externally with communication, media and marketing plans developed to deliver a Supplier engagement and network session.

Image and Identity (II)

Project Target Status Commentary
II1.1.1 - Deliver key marketing objectives from the City Positioning and Marketing Roadmap.

Purpose: Provide streamlined messaging to key audiences.
June 2021 Completed As at the end of the fourth quarter, streamlining of the marketing planning was conducted. Activities were also delivered to message this for internal branches into more strategic groupings and content approaches as aligned to the new city brand, position and road map.

Activities planned for this financial year achieved.
II1.2.1 - Implement amendments to the City of Choice initiative.

Purpose: Advocate the interests of the city. Create partnerships with other levels of government and non-government organisations.
June 2021 Not Completed As at the end of the fourth quarter, Council received a response from the Federal Government that did not address our request for engaging Council on a Memorandum of Understanding (MOU) to address employment program service delivery, instead pointing to existing employment programs.

A response to the Mayor's letter has not been received from the State Government. The Advocacy Program continues to follow this up with the Premier's office.

It is recommended that this project be moved to the 2021/2022 Operational Plan. The intent moving forward for this project is to engage with the Steering Committee to decide the future of this project.
II1.3.1 - Deliver the Catapult Program in collaboration with:
  • young people
  • industry
  • community
  • educators.
Purpose: Build job readiness and entrepreneurial capability for young people in Logan.
June 2021 Completed About:

During Quarter 4, the Catapult program launched for 2021 with 65 students from three foundation schools participating – Mabel Park State High School, Park Ridge State High School and Shailer Park State High School. Building on the work undertaken during the program pilot in 2020, the delivery model for 2021 has been refined to enable further opportunities for entrepreneurial capability development among participating students, more opportunities for educators to deepen their own skills in delivering entrepreneurial education, and more ways for businesses to engage in the program. Students now have access to school holiday programs to further their learning and build important networks, and teachers now benefit from a strengthened community of practice which enables them to regularly share knowledge and learn from each other to continue raising the standard of entrepreneurial education within schools across the City of Logan. Another 90 students are set to undertake the program during the second half of 2021 taking the total number to over 150.

Alumni from the 2020 pilot program have continued to receive support from Council, Griffith University, the Logan Chamber of Commerce and Substation 33 during Quarter 4 as they move towards launching their business ideas. These students have also played a role as ambassadors for the program and have shared their own experiences with students new to the program. Work is continuing with relevant partners to collaboratively build clear pathways between Catapult and the attainment and creation of local jobs and work experiences for participants.

Outcome:

With the program still in its early stages, engagement among participants, growth in program uptake and anecdotal feedback from participating businesses indicate that the Catapult program is delivering value for community currently and is in a good position to develop further and realise tangible outcomes for students and for the Logan economy.
II2.1.1 - Deliver the Parks Asset Renewal Program.

Purpose: Provide and maintain healthy and active recreation opportunities for families.
June 2021 Completed Delivery of the 2020/21 Parks Asset Renewal Program was achieved. A minor number of projects will be finalised early in 2021/2022 financial year.

The 2021/2022 Parks Asset Renewal Program has been drafted and is currently in design.
II2.1.2 - Deliver park infrastructure through the Parks Capital Works Program.

Purpose: Increase tourism in the city. Create healthy and active recreation opportunities for families.
June 2021 Completed Delivery of the original Parks Capital Works Program was achieved. It is noted the delivery of a number of recently identified projects and larger Local Infrastructure Program funded projects will be completed in the 2021/2022 financial year.
II2.2.1 - Implement a Logan City Council Events Strategy 2020-2025.

Purpose: Guide the strategic direction of city-wide events across a five-year period.
June 2021 Completed As at the end of the fourth quarter, events continue to be delivered under COVID-19 frameworks. Eats & Beats, Berrinba Wetlands were delivered successfully along with the Logan Loves Volunteers Breakfast, and the annual Logan Eco Action Festival (LEAF) seeing strong community participation. Going into the new financial year a number of events will continue to be delivered under COVID-19 restrictions including:
  • IGNITE Youth & Careers Expo
  • Seniors Expo
  • city-wide Christmas Carols.
Activities planned for this financial year achieved.
II2.6.1 - Deliver detailed design work for a new general community space at Greater Flagstone.

Purpose: Enable the next stage of the proposed Greater Flagstone Integrated Service Hub to progress.
June 2021 Not Completed Consistent with feedback from previous quarters, the land has still not transferred from PEET to Council, and therefore the design work has not progressed. This work will commence once EDQ approves the land transfer and this is facilitated by PEET. The impact of this is that funding to deliver design work has been re-provided for 2021/2022 and is included as a priority in the 2021/2022 Annual Action Plan.

It is recommended that this project be moved to the 2021/2022 Operational Plan to track its completion.
II2.6.2 - Deliver detailed design for a new district level community centre at Yarrabilba.

Purpose: Enable construction to start on the Yarrabilba Integrated Service Hub.
June 2021 Completed Detailed design has been completed and the relevant Agreements have been finalised. Next steps for this project is the commencement of the facilities construction in the 2021/2022 financial year.

Green and Renewable (GR)

Project Target Status Commentary
GR1.1.1 - Deliver Council's 2020 Emissions Profile Report.

Purpose: Measure, track and reduce Council emissions. Contribute to Council's carbon neutrality target by 2022.
October 2020 Completed Council's 2019/2020 Carbon Emissions Profile Report was delivered during 2020/2021 financial year using available relevant information.

This an important step on the pathway to achieving carbon neutrality for Council's operations by the end of 2022.
GR1.1.2 - Develop a Climate Resilience Strategy.

Purpose: To enhance climate resilience with Logan City Council.
October 2020 Completed Following internal consultation during the 2020/2021 financial year, a Climate Change Resilience Policy and a draft Climate Change Resilience Strategy 2021-2031 were endorsed by Council at its meeting of 9 December 2020 for community consultation (Minute No 163/2020).

The public consultation on the draft strategy resulted in a total of 176 submissions from the community. The feedback was incorporated into the final Climate Change Resilience Strategy 2021-2031.
GR1.2.1 - Deliver a range of environmental events and activities across the City of Logan.

Purpose: Raise awareness and provide community education on the environment and sustainability.
June 2021 Completed In the 2020/2021 financial year the environmental events and activities program successfully delivered 28 events reaching 823 community members. Events delivered were:
  • Two community PlatypusWatch induction sessions were held on August 22 at Cedar Creek with 22 community members in attendance.
  • A PlatypusWatch Children's workshop was held at Cedar Creek with 10 community members in attendance.
  • Waterbug monitoring event was held at Cedar Creek with 10 community members in attendance.
  • A World Rivers Day Kayaking event was held on 27 September with 32 community members in attendance.
  • Waterbug monitoring event was held at Cedar Creek on October 31 with 20 people in attendance.
  • A Platypus pondering event was held at Waterford on November 7 with 35 people in attendance.
  • A Family "come and try" kayaking event was held at Waterford on November 28 with 33 people in attendance.
  • A waterbug monitoring event was held on January 20 at Cedar Creek with 13 community members in attendance.
  • Upper Oxley Creek Restoration project open property event was held on February 20 at Greenbank with 30 community members in attendance.
  • PlatypusWatch children and adults workshops were held on March 13 at Beenleigh with 15 community members in attendance.
  • Guided spotlighting at Berrinba Wetlands was held on March 20 at Berrinba with 30 community members in attendance.
  • Guided spotlighting at Berrinba Wetlands on April 18 with 11 community members in attendance.
  • Bird Places of Logan brochure at Eagleby Wetlands on April 17 with 30 community members in attendance.
  • Swift Parrot Guided Walk at Eagleby Wetlands on 15 May with 16 community members in attendance.
  • Waterbug monitoring at Cedar Creek on 15 May with 3 community members in attendance.
  • Greater Glider Education Seminar at Underwood on 29 May with 25 community members in attendance.
  • Nest Box Building Workshop with Oxley Creek Catchment Association at Greenbank on 29 May with 31 community members in attendance.
  • Environmental Conservation Partnerships celebration event at Greenbank on June 6 with 250 community members in attendance.
  • Greater Glider Spotlighting at Cornubia on June 11 with 15 community members in attendance.
  • Trees for Fish community tree planting event at Beenleigh on June 12 with 30 community members in attendance.
  • Greater Glider education workshop at Chambers Flat on June 12 with 10 community members in attendance.
  • Greater Glider education online webinar on June 16 with 80 community members participating.
  • Greater Glider spotlighting at Park Ridge on June 18 with 9 community members in attendance.
  • Greater Glider education and Nest box building workshop at Greenbank on June 19 with 18 community members in attendance.
  • PlatypusWatch Logan induction at Kingston on June 22 with 10 community members in attendance.
  • Koala kids workshop and Koala education workshop on June 26 at Chambers Flat with 35 community members in attendance.
These events work to achieve actions in numerous Corporate plans and strategies including the City of Logan Koala Conservation Strategic Plan, Logan River Vision, Albert River Vision, Priority Species framework and Upper Oxley Creek Catchment Plan.
GR1.2.2 - Deliver a Logan Environment Strategy that aligns with the Federal Strategy for Nature and Queensland Biodiversity Strategy.

Purpose: Provide overarching goals and actions. These will protect and enhance healthy and functioning biological systems in the City of Logan.
June 2021 Not Completed Development of the City of Logan Natural Environment Strategy has progressed well. To ensure the draft Strategy incorporates the community feedback obtained through Council's Community Vision engagement process and the new Corporate Plan, delivery of the draft Strategy has been delayed until August 2021. The draft Strategy will then be released for formal community consultation. As a result of this delay, the City of Logan Natural Environment Strategy is expected to be finalised in September 2021.

This project is already included in Council's 2021/2022 Operational Plan.
GR1.3.1 - Deliver priority on-ground wildlife movement solutions based on hot spot prioritisation mapping.

Purpose: Enhance road safety and reduce wildlife-vehicle collisions.
June 2021 Completed The delivery of the priority on-ground wildlife solutions was delivered successfully in 2020/2021. The six monthly inspections and maintenance works were completed at the three virtual fence trial locations of Park Ridge Road, Park Ridge, Rosia Road, Park Ridge and Cusack Lane, Jimboomba. The wildlife monitoring and summary report of the virtual fence at Rosia Road was completed. The wildlife awareness campaign was undertaken which included radio advertisements, electronic posters, social media posts, environmental e-newsletter article and internal staff notices.

This resulted in an increase in visits to the associated Council webpages and wildlife sightings reported to council. Information from the wildlife movement solutions hot spot mapping has been used in discussions for the delivery of future on-ground solutions as part of road upgrades.
GR2.1.1 - Deliver riparian rehabilitation along priority areas of the Albert River.

Purpose: Enhance water quality, biodiversity connection and ecological values along the Albert river. Work towards achieving the Albert River vision.
June 2021 Completed The Albert River Riparian Rehabilitation project was successfully delivered during the 2020/2021 financial year. Approximately 330 native plant species, including 30 rare and threatened plants were planted along a 200 metre length of the Albert River bank at Luscombe Park.

At Wolffdene South Reserve, an additional 320 plants to further enhance the ecological value of the site from works in 2019/2020 were completed. Approximately 20 of these plants are rare and threatened species. Both Luscombe Park and Wolffdene South Reserve are under maintenance until June 2022.

The final detailed design report for Eagleby Wetlands bank stabilisation and fish Habitat project was completed in 2020/2021. This report and final design has been submitted to the State Government for works approval. Works will stabilise an approximate 65 metre length of the Albert River suffering severe erosion that is currently undermining the adjacent public pathway. In addition to bank reshaping, planting and rock armouring, the works will include root ball structures, which will enhance fish habitat along this stretch of the Albert River.
GR2.2.1 - Deliver a feasibility study to establish a Riverine Discovery Centre.

Purpose: Promote community environmental awareness and eco-tourism in the City of Logan.
June 2021 Completed During the 2020/2021 financial year, a Riverine Discovery Centre Feasibility Report was completed which included complex design requirements to minimise flood impact. Information from the report informed a South East Queensland Community Stimulus Program Grant application seeking funding for the construction of the Riverine Discovery Centre.

The application was successful with $2,750,000.00 being awarded for the construction of the Riverine Discovery Centre over the next 3 years.
GR2.3.1 - Deliver riparian rehabilitation along priority areas of the Logan River.

Purpose: Enhance water quality, biodiversity connection and ecological values along the Logan river. Work towards achieving the Logan River vision.
June 2021 Completed In the 2020/2021 financial year the Logan River Riparian Rehabilitation project was completed. Five riverside parks had rehabilitation works with over 18,000 native tube stock. This includes works at Logan River Parklands, Wendt Park, Riverdale Park, Bethania Shores and Spann Park. This project also included a large scale bank stabilisation project within Logan River Parklands where 2 log root balls were installed for fish habitat as well as 7 log pile fields to prevent future erosion. All sites are currently on maintenance for a period of 2 years. During June 2021, a section of the Wendt Park site that experienced severe erosion during the March 2021 floods had 500 lomandras planted to help further stabilise the bank.
GR3.1.1 - Deliver a report on service options available under the 2021 Waste Collection Contract.

Purpose: Prepare for commencement of the new waste collection contract in July 2021.
April 2021 Completed The greenwaste service report was considered and approved by Council during 2020/21 budget deliberations. A further report on how the service will be rolled out was considered by Council in a Briefing Session on 17 September 2020. Approval was obtained to proceed with the call for Expressions of Interest (EOI's) in the service on a dedicated web page with promotion via City Mag, brochures delivered with Kerbside Clean Up flyers, social media and various other means at Council facilities and customer service centres. 8,200 bin registrations had been received by the end of April 2021.

By the end of June approximately 8,500 greenwaste bin applications had been received and the bin roll-out commenced. Bins applied for prior to 26 April 2021 were delivered during June 2021. Bins applied for after 26 April 2021 will be delivered during July 2021.

Council in August 2020 resolved to not implement an on-demand KCU service and stay with the scheduled service.

Council considered a report on the innovation project in August 2020 and resolved to call for a business case from Lendlease. Lendlease conducted some stakeholder consultation to assist with development of the plan in December 2020. The business case was still awaited at the end of May 2021.
GR3.1.2 - Deliver a report for Council consideration on the evaluation of the regional waste disposal and resource recovery.

Purpose: To inform future waste management planning.
October 2020 Completed The Evaluation Report was considered by Council at its Planning, Environment & Economic Development Committee Meeting on 30 September 2020.

The recommendations of the report were endorsed for Council adoption. The process has identified a potentially viable regional recycling solution that remains under active consideration and requires further evaluation.

Next Generation Governance (NG)

Project Target Status Commentary
NG1.1.1 - Deliver enhancements and new features to the corporate website.

Purpose: Provide enhanced digital customer experiences.
June 2021 Completed The Digital Customer Experience Team have completed all website layout and design changes to comply with the endorsed rebranding strategy.

The e-Petitions design and development has been completed and endorsed by ELT and went live on 1st July with the first submission coming through the same day.

The enhanced Careers section is in the final design phase. The Website Transformation Project is formally completed with remaining focus areas of converting PDFs to web content or accessible documents and the finalisation of the enhanced careers section transitioned to BAU.
NG1.2.1 - Develop a proposal for proactive and targeted educational or compliance programs. These will link to systemic risks or priority city-wide issues of public importance.

Purpose: Increase compliance.
April 2021 Completed

Wrapping up the year at the end of the fourth quarter, the team looked at data relating to complaints and inspections across Development Application (DA) compliance teams. Technology was implemented to analyse data to identify trends of what is happening across the city for development, and where complaints are coming from in the community. The team also looked at the service levels for how long it takes to investigate different actions that came into the Development Assessment compliance areas.

Some highlights of the actions and outcomes achieved this year include:

  • Land Use Investigation – The team analysed over 1000 complaints received in the past financial year to identify what are the most concerning issues raised by the community. Based on this information, we designed educational campaign to be carried out in the coming financial year to residents live in targeted area on what they are allowed to do on their property.
  • Building Investigation – Pool Safety has always been a priority for the team and this year the team provided Pool Safety inspections to over 200 properties even under Covid-19 restrictions.
  • Construction Taskforce – Erosion and sediment control (ESC) has been one of the biggest complaint sources on development sites and this year the Construction Taskforce team has taken over the compliance component for ESC on large development sites to ensure faster response and more stringent compliance outcomes on site. At a result, a number of enforcement actions were taken against non-compliance sites including fines issued and sites shut down under the Environmental Protection Act 1994 and Planning Act 2016.
  • Plumbing Investigation – A large number of Logan homes are on septic systems for wastewater treatment given the rural residential lifestyle in some of our suburbs. The Plumbing Investigation team has identified that over 5000 the septic systems are non-compliant with the Plumbing and Drainage Act 2018 requirements and pose environmental and public health concerns. Therefore, the team has put forward a proposal for additional officers to be added to the team to work on this targeted project. With the appreciation of the importance of this piece of work, the Logan leadership team has approved a service enhancement in the first half of this year to allow this project commences in the coming financial year.
NG2.1.1 - Deliver a news and community website.

Purpose: Provide stronger communication channels to the community.
June 2021 Not Completed Council at its meeting 19 May 2021 endorsed a decision to move this project to the next financial year, with the Marketing and Events Branch tasked with its delivery (Minute No. 225/2021).

This project will be delivered in the next financial year, and renamed Our Logan digital offering.
NG2.1.2 - Develop a revised community engagement strategy, with input from the community.

Purpose: Further enhance Council's commitment to broader engagement practices and processes.
June 2021 Completed Community consultation occurred and the feedback provided was reviewed. The draft strategy was updated to reflect feedback from the community and the final strategy has been endorsed by Council.

The Community Engagement Program are currently developing an action plan to support the strategy.
NG3.1.1 - Develop and implement a compliance management system.

Purpose: Ensure effective and accountable governance.
June 2021 Completed The development and implementation of Council's compliance management system is now completed. This system will allow the capture and reporting of compliance obligations which are tailored to the local government regulatory environment.
NG3.1.2 - Develop and implement a governance framework.

Purpose: Promote best practice for corporate governance.
June 2021 Completed The Governance Framework was approved by Ordinary Council at its meeting held on 28 October 2020 (Minute No. 136/2020). This project is now complete.
NG3.1.3 - Deliver actions to secure Quality Management System ISO9001:2015 certification.

Purpose: Ensure a consistently high quality of service is delivered to customers and stakeholders.
June 2021 Completed Quality Business Documents conducted a de-brief with Plant Fleet Services on the 11 June 2021. A discussion was also conducted on "What Happens Now". Quality Meetings will now be conducted monthly with a fixed agenda to allow for the continual improvement of the system. The Quality Certificate was issued on the 6 May 2021, received on the 15 June 2021 and is displayed in Plant Fleet Service Reception area. Project is now complete.
NG3.1.4 - Engage all stakeholder groups across the city to develop a long-term plan and city vision.

Purpose: Inform the strategic direction for the City of Logan.
June 2021 Completed The Community Vision Report was finalised and formally received by Council on 21 June 2021 as part of the 2021-2026 Corporate Plan adoption process.
Project complete.
NG3.1.5 - Deliver the Asset Management Strategy.

Purpose: Build organisational capability in sustainable asset management practices. Enable cost optimisation to meet the current and future needs of the city.
June 2021 Completed The progress of key deliverables as per the Asset Management Strategy improvement plan continue and are currently being delivered per schedule.
These Include:
  • The Service Enhancement for the implementation of Council's Enterprise Asset Management System (EAMS) was developed based on the Strategic Business Case and cost estimates. The Service Enhancement was supported by Council during the budget process with funding approved to commence the project in 2021/2022.
  • Further development of next generation asset management templates with Parks and Stormwater Asset Management Plans being updated;
  • Scale up Asset Management Technical Reference Group (community of practice) across the organisation;
  • Further investigation into dashboard reporting capability;
  • Progressing the development of Council's Asset Information Handover Specification, with particular focus on Transport & Stormwater Assets as these are most critical in Developer handover;
  • Development of Condition Assessment Guideline for council's asset classes.
NG3.1.6 - Deliver the Corporate Innovation Strategy.

Purpose: Build organisational capability in using innovation models. Enable services to be delivered in new and better ways.
June 2021 Completed The Corporate Innovation Strategy reaches our two year milestone in August 2021. In its second year of operation, the focus of the strategy was to 'Embed and Scale'. Staff across the organisation are applying innovation to address problems and challenges and to improve services to the organisation and city. There are three core service areas offered to the organisation under the Corporate Innovation Strategy. Some key highlights for the 2020/2021 financial year include:
  • Innovation Culture and Capability Uplift Services: Council invested in a number of staff across the organisation to complete the globally recognised T7 Masterclass in Innovation. This investment provided a foundation in which to embed and scale a corporate standard in how innovation can be used to solve business and city challenges. This foundation underpinned three key initiatives that have been rolled out this year to build staff knowledge and capability for innovation practice. The first initiative was the design and implementation of monthly online Lunch and Learn Sessions which have been attended by over 430 staff and is tracking at a 85% favourability rating. The second initiative was the design and development of an online training program for staff. Built within Council's Learning Management System it will build staff knowledge and capabilities in the use of innovation methods and tools. This is a self-paced learning program that will be offered to all staff as a service offering as part of the 2021 Staff Annual Performance and Review process where development needs are identified. The third initiative was the delivery of a two-day Hackathon in partnership with the Leadership Development Program. Using an experiential learning model, 21 emerging leaders within Council were trained in the use of innovation tools and methods to create solutions for existing business challenges. This initiative received a 93% favourability rating.
  • Corporate Innovation Consultancy Services: Embedding the capabilities derived from the Masterclass in Innovation Program, the T7 Alumni have been activated by providing consultancy services to the organisation to help tackle existing business problems. Teams across the organisation were supported to work cross functionally and collaboratively, share resources and knowledge to tackle problems and test viable solutions. Over 20 corporate initiatives and have been provided consultancy and facilitation services over the last 12 months and over 100 staff have been exposed to a range innovation tools and techniques.
  • Innovation Communication and Engagement: Driving a culture of innovation requires a strong communication and engagement strategy. In this financial year, one of two key highlights include the distribution of 44 Electronic Digital Mail updates which were designed and circulated to staff involved in innovation corporate initiatives to keep stakeholders engaged and informed. Communication and Engagement was also supported through the design and implementation of the monthly PodCast club. A digital platform that is focused on knowledge exchange, the PodCast club edition provides a range of podcasts and articles highlighting innovation practice. As a voluntary opt in subscription, the Podcast Club at the end of the financial year has over 104 staff subscribed. Following a review of the PodCast Club in May, our new initiative "Innovation Unearthed" will be launched in July 2021. There are already 300 staff registered to be subscribed once this initiative rolls out.
NG3.2.1 - Deliver an advocacy campaign leading into the State Government election in October 2020.

Purpose: Secure infrastructure investment for the City of Logan from the State Government.
October 2020 Not Proceeding Council made a decision to remove this project from the Operational Plan at its meeting 18 November 2020 (Minute number 153/2020).

A decision was made to pause Council's FairShare4Logan platforms in March 2020 due to the COVID-19 pandemic. No budget was allocated towards a state election campaign in 2020/2021. Assistance was offered and provided to Councillors who wished to advocate for divisional priorities with State Candidates, as per the program's usual scope of business.
NG3.2.2 - Deliver the Advocacy Strategy 2020-2024 and implement a program of priorities.

Purpose: Build strategic relationships to influence policy and investment in the best interests of the city.
June 2021 Completed Council endorsed the Advocacy Strategy 2021-24 at its meeting on 23 June 2021. The Advocacy Program is preparing the Advocacy Action Plan to support implementation of this strategy. A quarterly update will be provided in September.
NG3.3.1 - Deliver actions from the City of Logan Biosecurity Plan 2017-2022.

Purpose: Manage invasive pests, plants and animals across the city.
June 2021 Completed At the end of third quarter, the Biosecurity Surveillance Program and invasive biosecurity matter control are on target year to date:
  • 258 monthly water body inspections which lead to 61 treatments
  • 2346 weed treatments on parks, public land and roadsides
  • 487 weed treatments provided by Council on private property
  • 2689 weed inspections
NG4.1.1 - Deliver a Safety Culture Action Plan and an organisational wellness strategy.

Purpose: Ensure the safety of our people, contractors and community. Build resilience and maximise the physical and mental health and well-being of our people.
June 2021 Completed Health Safety and Wellbeing remains a strategic priority. With a now fully functioning Health Safety and Wellbeing Program Team projects outlined in the 2020 Strategic Plan have commenced across all areas of council. These projects focus on the continual improvement of risk identification, control and mitigation to as low as reasonably practicable. Health, Safety and Wellbeing score cards are now produced on a monthly basis and are demonstrating a reduction in lagging indicators such as Lost Time Injuries and an increase in leading indicators including near hits and hazards. Councils Lost Time Injury Frequency Rate for the July 2020 - June 2021 saw a decrease of 3% from the previous year.
NG4.1.2 - Deliver 14 strategic people projects.

Purpose: Enable and support our people to deliver on the Corporate Plan 2017-2022.
June 2021 Completed As at the end of the fourth quarter, the rescoping of this project - as a result of the COVID-19 pandemic during the financial year - saw planned activities achieved. As at the end of the financial year the People Plan project had 16 projects in total marked for delivery. Of the 16 original projects:
  • 7 projects were complete
  • 5 projects were partially completed
  • 3 projects were not started
  • 1 project was moved to ongoing operational work
This initiative will continue to be tracked internally in the organisation, with the view of producing the next People Plan in the second half of the next financial year.
NG5.1.1 - Deliver an updated hazard and risk profile for the city.

Purpose: Improve disaster management capabilities.
June 2021 Completed Several community engagement initiatives were delivered during quarter 4, focussing on the following topics:
  • Home Fire Safety
  • Bushfire preparedness
  • Disaster preparedness for business
  • Logan Early Warning
  • Disaster Dashboard
  • SES recruitment
Methods of engagement included:
  • Facebook posts, polls and advertisements
  • Articles in the Our Logan magazine
  • Advertisements in the Jimboomba Times newspaper
  • Mobile Truck Billboard
  • Shopping Centre Advertising
  • Google Display Prospecting
  • Translated information on 4EB radio
  • Advertisements on Rebel FM Radio
  • Distribution of educational materials through Logan's 9 libraries
  • Promotion of key messages via super banners on the Logan City Council website and via the Customer
  • Service Centre and Library TV screens
The Disaster Management Program also partnered with Queensland Fire and Emergency Services (QFES) to deliver a number of initiatives and education opportunities for the Logan community focussing on:
  • Smoke Alarm Awareness
  • Home Fire Safety
  • Bushfire Safety
Initial discussions were had with Council's Community Development Program, National Disability Services and the local team from the National Disability Insurance Scheme in Logan to identify opportunities to deliver local engagement with the disability sector in line with the Disability Inclusive Disaster Risk Reduction project. Further research and engagement will continue in the new financial year.
NG5.1.2 - Deliver the annual review of the Local Disaster Management Plan, sub-plans and Standard Operating Procedures.

Purpose: Ensure policies, practices and operational procedures align with agencies. Identify opportunities for continuous improvement.
June 2021 Completed The following plans were re-endorsed at the LDMG Meeting held 27 August 2020
  • Local Disaster Management Plan
  • Recovery Sub-Plan
  • Spontaneous Volunteers Sub-Plan
  • Community Information and Warnings Sub-Plan
  • Evacuation Sub-Plan
  • Hazard Specific Sub-Plan
  • Rapid Response Sub-Plan
NG5.2.1 - Finalise the Logan and Albert River floodplain study and plan.

Purpose: Improve flood management strategies in the event of a flood disaster.
June 2021 Completed The flood study is complete. Floodplain management strategies will be developed as part of the 2025 Planning Scheme project which requires a risk assessment to be delivered in support of a new flood hazard overlay and code.