Teviot Road Upgrade

We are widening Teviot Road to help ease traffic congestion.
Latest updates
Fence repairs
Council appointed contractor BMD will be in the area to repair a fence along Teviot Road near the Anderson Drive / Leanne Court intersection.
A partial lane closure will be in place during the works. Please drive to the conditions, and follow all signed traffic changes.
Works are expected to start Tuesday 26 May 2026 from 8:30am, and be completed within the day, construction and weather conditions permitting.
Primary works complete
All the primary works for the Teviot Road Upgrade Stage 1A have been completed. However, road users may see crews on site conducting repairs or finishing works as required.
Project overview
This complex upgrade will be delivered in multiple stages across the project zone.
Teviot Road is expected to see considerable traffic growth in future years because of residential and business expansion linked to the Queensland Government’s Priority Development Area of Greater Flagstone.
This upgrade will help ensure our local road network remains fit for purpose and can safely accommodate future traffic demands.
Middle Road and Teviot Road Interim Roundabout Improvements
As part of the Teviot Road Upgrade project, in December 2022 we delivered an interim upgrade to the roundabout at the Middle Road and Teviot Road intersection to help ease traffic congestion.
Project timing
Stage 1A (Greenbank Shopping Centre to just south of James Smith Recreation Area) commenced works in late August 2024 and is expected to conclude by end 2025, pending construction and weather conditions.
At this stage we do not have a timeline for constructing future stages.
We will keep the community updated as the project progresses.
Project features
The design includes:
- widening Teviot Road to four lanes (two lanes in each direction) between Greenbank Road and the Middle Road roundabout
- constructing a larger two-lane roundabout at the intersection of Teviot Road and Middle Road
- upgrading the intersections at Stoney Camp Road, Leanne Court, Pub Lane, and Greenbank Road
- widening Pub Lane to four lanes (two lanes in each direction) between Teviot Road and the Greenbank Shopping Centre roundabout
- improving walking and bike riding facilities.
Project benefits
The Teviot Road Upgrade will deliver a range of benefits including:
- improved safety
- more efficient traffic flow
- more reliable travel times
- a boost to the economy - in the short term through construction jobs and the longer term by improving connectivity.
Land requirements
To complete the project, some land will need to be acquired to widen sections of Teviot Road and Pub Lane.
We have identified and met with potentially impacted property owners. We aim to minimise property impacts as much as possible.