The design phase of the project is progressing, while we wait to receive the Environmental Protection and Biodiversity Conservation (EPBC) approval from the Department of Climate Change, Energy, the Environment and Water (DCCEEW). EPBC approval can take several years to complete, and Council do not have any control over how long this takes.
Logan Water early works are continuing, while we also coordinate service relocations with Energex, Opticomm and Telstra.
Select demolition activities are in progress.
Updates will be published here as the project progresses.
As part of Council's Major Roads Capital Works Program, we are upgrading School Road to connect with the Chambers Flat Road / Park Ridge Road intersection. This project aims to:
Construction details and timings will be shared as soon as they are confirmed.
Initial service location work is expected to be low impact.