Chambers Flat Road upgrade

Logan City Council is upgrading a 3.8-kilometre section of Chambers Flat Road, from Mount Lindesay Highway (Munruben) to just north of Kings Way (Chambers Flat).

The upgrade will:

  • improve the safety and condition of the road for all users
  • provide a more reliable transport link through improved flood protection along the road corridor during wet weather events.

View the project work zone area (PDF 11.2 MB)

What are we doing?

As part of the Chambers Flat Road upgrade we will:

  • Widen the road to allow for wider 3.5m traffic lanes (while remaining as a two-lane road) and 3m wide sealed shoulders.
  • Improve flood protection along the road corridor by raising the road level and building a new bridge over Norris Creek (up to 8m higher than the existing level).
  • Improve sight distances at bends and crests to meet safe road design standards.
  • Improve intersection designs to allow for safer turning movements and enhance traffic flow. This includes providing dedicated turning lanes into Kings Way and Greenvale Road.
  • Install new road pavement and more efficient road drainage structures.
  • Relocate services, remove vegetation, install signage and carry out line marking and restoration activities.

Project Timing

Construction activities will take place in two stages:

  • an Early Works package
  • a Main Construction Works package.

Early works, including vegetation clearing, minor earthworks, service relocations and fence relocations are scheduled to begin in mid-2021. We expect to complete these by late 2021, pending weather and site conditions.

Main construction works will begin once early works are complete. We anticipate these will  take approximately 12 months, pending weather and site conditions. We will advise a construction start date once known.

What can I expect?

The Early works notification (PDF 298 KB) outlines the construction impacts you can expect during the Early Works stage of the project. 

Project updates

November 2021 update

  • Early works are on track to be completed by late 2021, with main construction works expected to commence in early 2022, pending weather and site conditions.
  • Our contractor is working to finalise all vegetation clearing / trimming and fence reconstruction works by early 2022.
  • Service providers including, Energex and NBN will finalise all service relocations by early 2022. If a temporary disruption to your service is required, your service provider will notify you to advise when these works are scheduled to occur.  
  • For more information please download the Chambers Flat Upgrade notice (PDF 725 KB).

Project design

View project works plans for the Chambers Flat Road Upgrade:

View intersection designs for the Chambers Flat Road Upgrade:

Have more questions?

Find answers to frequently asked questions about the Chambers Flat Road upgrade (PDF 160 KB).